Capital Budget
Capital Expenditure April – September 2025
The Capital Budget for 2025/26 is estimated to be £25.874m. As at the end of Period 6 (30 September 2025), there is an actual spend of £2.862m which is about 11.1% of the total budget
A significant percentage of the works are scheduled to start in October/November 2025 with completion of the projects to be between December 2025 and March 2026. We are currently reporting a total projected underspend of £3.678m consisting of a marginal underspend of £0.218m in respect of carbon reduction works, an underspend of £1.020m of the Planned Maintenance Programme and an underspend of £2.440m in respect of New Build and Acquisitions.
It should be noted that, the Planned Maintenance programme has a further committed spend of £2.832m for internal works (kitchens and bathrooms and heating) which will commence in January 2026 but will not be completed before the end of the financial year. This will be funded by the underspend of £1.020m from this year’s programme and the remaining £1.812m will be funded from next year’s Planned Maintenance budget.
Planned Maintenance 2025/26
The forecast at Period 6 for planned maintenance works in this financial year is £9.157m. The works include the following:
Internals: Kitchens, Bathrooms, Heating
The full year forecast at the end of Period 6 is £1.478m. Works are scheduled to build up in October/November 2025 with planned completions in January/February 2026.
Externals: Windows, Doors, Pointing, Lintels
The full year forecast at Period 6 is £1.938m. Works are scheduled to build up in October/November 2025 with planned completions in February/March 2026.
Externals: Roofing incl. fascias, soffitts & rainwater
The full year forecast at Period 6 is £4.381m. Works are scheduled to build in October/November 2025 with a planned completion of January/February 2026.
Upgrade of Communal Areas in Flats
The full year Forecast at Period 6 is £1.257m. Works are scheduled to start in October/November 2025 with a planned completion of January/February 2026.
Demolition of Garages
The full year forecast at Period 6 is £0.103m. Works scheduled to start in October/November 2025 with a planned completion of January/February 2026.
1 Carbon Reduction
The full year forecast at Period 6 is £9.320m. Several Contracts have been awarded with works scheduled to start in October/November 2025 with planned completions in February/March2026. The current energy schemes are as follows:
Freetown Estate and Stanley Close
The full year forecast at Period 6 for this scheme is £2.415m. A fabric first approach is adopted to make a building’s physical components highly energy efficient, reducing energy demand and carbon emissions. The works include top up loft insulation, removal of cavity wall degraded insulation and refilled with more thermally efficient cavity wall insulation, new windows and doors, ventilation upgrade, energy efficient lighting and solar photovoltaics, Heat pumps to 30 properties
Chesham
The full year forecast at period 6 is £1.443m. A fabric first approach is adopted, and the works comprise of loft insulation upgrade, removal of cavity wall degraded insulation and refilled with more efficient cavity wall insulation, new windows and doors, ventilation upgrade, energy efficient lighting and solar photovoltaics.
Hollinghurst Estate
The full year forecast at Period 6 is £1.646m. A fabric first approach is adopted, and the works consist of loft insulation upgrade, removal of cavity wall degraded insulation and refilled with more energy efficient cavity wall insulation, new windows and doors, ventilation upgrade, energy lighting and Solar photovoltaics.
Langley Hall, Leemans Hill and Park Lane
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Half-year update on improvement programmeDecisions | 381 KB | DownloadRead as text |
Follow Housing Advisory Board at Bury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Jun 2026 | Tenants voice forum update reportIt was agreed: 1. That the update be noted 2. That further work on tenant communications and reporting be supported 3... | Agreed | Open |
| 9 Jun 2026 | Housemark review findings and next stepsIt was agreed: That the findings of the Housemark review be noted. That the improvement action plans for complaints a... | Agreed | Open |
| 9 Jun 2026 | Temporary accommodation strategyIt was agreed that: The Board noted the report. | Agreed | Open |
| 9 Jun 2026 | Housing advisory board terms of referenceIt was agreed that: The quorum arrangements should be amended to include at least one tenant representative Chloe Ash... | Agreed | Open |
| 5 Mar 2026 | Tenants voice forum update reportIt was agreed that: 1. Members noted the ongoing work to improve communications governance, performance reporting vis... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.