Bury Metropolitan Borough Council
Overview and Scrutiny Committee, Tuesday 10 February 2026 at 7.00pm

SIMISTER AND BOWLEE DEVELOPMENT FRAMEWORK

Agreed Scrutiny 3 papers

AI summaryBury scrutiny committee notes draft Simister Bowlee Development Framework and gives feedback, as 1,550-home plan heads to six-week public consultation from 13 February 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedOn draft Simister Bowlee Development Framework SPD
MoneyNo direct costCovered by existing Planning Services budget
What happens nextCabinet approval to consultSix-week consultation from 13 February 2026
Who it affectsSimister Bowlee siteBury and Rochdale, 1,550 new homes planned

What was decided

Overview and Scrutiny noted the content of the draft Simister Bowlee Development Framework Supplementary Planning Document. Report P6

Members were invited to provide feedback on the draft document before it goes to Cabinet. Report P6

Why

The framework is needed to give the Simister Bowlee allocation planning weight and to meet the masterplan requirement of PfE Policy JPA1.2. Report P2, P3, P18

Statutory consultation is required before the document can be adopted as a Supplementary Planning Document under the Planning and Compulsory Purchase Act 2004 and the 2012 Regulations. Report P11, P42, P59

What happens next

Cabinet is asked to approve the draft SBDF for a six-week public consultation starting 13 February 2026 and running until 27 March 2026. Report P5, P8, P50, 5.2

Following consultation, a final version will be brought back to Cabinet for formal approval to adopt it as an SPD, expected in summer 2026. Report P5, 5.2

The Executive Director of Place is to be given delegated power to make minor editorial amendments before consultation starts. Report P9

The money

  • around 335 affordable homes in Bury Affordable housing provision (around 25% of Bury homes) Report P15

Options considered

  • Chosen: Approve the SBDF for six-week public consultation. Required by statutory consultation rules before SPD adoption. Report P8, P11, P12
  • Rejected: Do not approve the SBDF for consultation. Would prevent stakeholder comment and prevent the Council from adopting the SPD, which requires statutory consultation. Report P12

Implications

  • Legal: The draft SPD has been prepared under the Planning and Compulsory Purchase Act 2004 and the Town and Country Planning (Local Planning) (England) Regulations 2012, and recommending it for consultation then future Cabinet adoption is within the Council's legal powers. Report P42, P59
  • Equalities: An Equality Impact Assessment has identified potential impacts across some characteristics that will need mitigations as the development progresses; no outstanding equalities concerns at this stage. Report P53, P54
  • Climate: Chapter 9 embeds sustainable development to support Greater Manchester's carbon neutral city region ambition by 2038; biodiversity net gain and ecological mitigation are part of the scheme. Report P37, P15, P56
  • Financial: No direct financial implications: work has been done by Planning Services within existing approved budgets and consultation costs are also covered by existing budgets. Report P60
  • Risk: Risk that stakeholders do not engage in consultation is mitigated by following the statutory framework and keeping the process under review. Report P57, P58
  • Other: The site sits within the wider Northern Gateway (JPA1.1), which has a separate SPD adopted in March 2025, and supports the Atom Valley Mayoral Development Zone. Report P13, P30

Who and where

  • Future residents of the Simister Bowlee development (1,550 new homes, 1,350 in Bury, including around 335 affordable homes in Bury) Report P15
  • Existing residents of Bury and Rochdale who may use new community, retail, school and green infrastructure Report P15, P16
  • Statutory and registered consultees (around 2,500 contacts) who will be contacted directly about the consultation Report P47
  • Northern Gateway Development Vehicle LLP and other landowners and stakeholders involved in preparing the framework Report P21

Timeline

  • 21 March 2024: Places for Everyone Joint Plan adopted, including Simister Bowlee residential allocation under Policy JPA1.2 Report P13, P17
  • March 2025: Separate Northern Gateway (JPA1.1) SPD adopted Report P13
  • 13 February 2026: Proposed start of six-week public consultation on the draft SBDF Report P8, P50
  • Tuesday 24 February 2026, 4-8pm: Drop-in session at Radcliffe Market Report P49
  • Wednesday 25 February 2026, 4-8pm: Drop-in session at Elton High School Report P49
  • Thursday 26 February 2026, 4-8pm: Drop-in session at Parrenthorn High School Report P49
  • Thursday 5 March 2026, 4-8pm: Drop-in session at Edgar Wood Academy (Simister Bowlee Development Framework only) Report P49
  • 27 March 2026: Proposed end of six-week consultation period Report P50
  • Summer 2026: Final SBDF to be brought back to Cabinet for formal approval and adoption as an SPD Report 5.2

Plain English for the jargon

  • SPD: Supplementary Planning Document
  • PfE: Places for Everyone Joint Development Plan
  • SBDF: Simister Bowlee Development Framework
  • NGDV: Northern Gateway Development Vehicle LLP, the main site promoter
  • MDZ / MDC: Mayoral Development Zone / Mayoral Development Corporation
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemOSC.94

Resolved

It was agreed that Overview and Scrutiny: i. Note the content of the Simister Bowlee Development Framework Supplementary Planning Document (Appendix 1); ii. Provide feedback on the content of the Simister Bowlee Development Framework Supplementary Planning Document (Appendix 1)
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Overview and Scrutiny Committee

Summary

1. The draft Simister Bowlee Development Framework (SBDF) sets out the masterplan and phasing strategy for the Simister Bowlee site. This is one of Bury’s residential sites allocated through the Places for Everyone Joint Plan (PfE), which was adopted in March 2024.

2. A key requirement of PfE Policy JPA1.2 is that any proposals within the Simister Bowlee allocation must be in accordance with a comprehensive masterplan that has been agreed by Bury and Rochdale local planning authorities and that it shall include a design code and an infrastructure phasing and delivery strategy.

3. The draft SBDF establishes the key principles for the development of the site and establishes a framework against which future planning applications on the site will be considered. It sets out high level design principles and an approach to the delivery and phasing of the necessary supporting infrastructure. To give the SBDF appropriate planning weight in the decision- making process, it is proposed that it is formally adopted as a Supplementary Planning Document (SPD).

4. Overview and Scrutiny Members are asked to note the content of the Simister Bowlee Development Framework and provide feedback.

5. Cabinet members are asked to approve the draft SBDF for a 6-week period of consultation to establish stakeholder views on its content. Following consultation, all representations received will be fully considered and changes made where appropriate before the SBDF is brought back to Cabinet for approval to formally adopt it as an SPD. Recommendation(s) 6. It is recommended that Overview and Scrutiny:

i. Note the content of the Simister Bowlee Development Framework Supplementary Planning Document (Appendix 1); ii. Provide feedback on the content of the Simister Bowlee Development Framework Supplementary Planning Document (Appendix 1)

7. It is recommended that Cabinet:

i. Approves the draft Simister Bowlee Development Framework Supplementary Planning Document (Appendix 1) as the basis for public consultation for a six-week period commencing on 13 February 2026.

ii. Delegates power to the Executive Director of Place to make minor non- material editorial amendments to the draft Simister Bowlee Development Framework Supplementary Planning Document before consultation commences.

Reasons for recommendation(s)

8. To enable stakeholders to have the opportunity to submit comments on the draft Simister Bowlee Development Framework and to comply with the statutory requirements for consultation. Alternative options considered and rejected

9. To not approve the SBDF for consultation. This would prevent stakeholders from commenting on the SBDF and would prevent the Council from being able to proceed to adopt the SBDF as a Supplementary Planning Document because it is a statutory requirement that such documents must be consulted on before adoption. _________________________________________________________ Report Author and Contact Details: Name: Cris Logue Position: Assistant Director (Strategy, Planning and Regulation) Department: Place E-mail: [email protected] ________________________________________________________________ Background 10. The Places for Everyone Plan (`PfE’) is a joint development plan document of nine of the ten Greater Manchester authorities (excluding Stockport MBC) which was adopted on 21st March 2024.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Simister Bowlee-Development-Framework Consultation DraftAppendix 1 8.8 MB Download
PDF
SIMISTER AND BOWLEE DEVELOPMENT FRAMEWORKDecisions 394 KB DownloadRead as text
PDF
Simister: JPA1.2 SBDF EqIA (October 25)Decisions 462 KB Download

At this meeting

Whole meeting

Who was there

11 of 16 attended
JA
Josh AshworthDS Officer, expected
DV
Councillor Dene VernonChair, present
JS
Councillor John SouthworthCommittee Member, present
MR
Councillor Miriam RahimovCommittee Member, present
AA
Councillor Ayesha ArifCommittee Member, apologies, sent representative
TP
Councillor Tom PilkingtonCommittee Member, apologies
DG
Councillor Debra GreenCommittee Member, present
TR
Councillor Tahir RafiqCommittee Member, present
EM
Councillor Elliot MossCommittee Member, present
CB
Councillor Carol BirchmoreCommittee Member, present
GM
Councillor Glyn MarsdenCommittee Member, present
JH
Councillor Jackie HarrisCommittee Member, present

All 16 on the meeting page

On this subject at Bury

Search all
  1. SIMISTER AND BOWLEE DEVELOPMENT FRAMEWORKThis decision
  2. Simister Bowlee Development FrameworkApproved
  3. Simister Bowlee Development Framework Consultation DraftApproved

More from Bury Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
10 Feb 2026 Elton reservoir development frameworkIt was agreed that Overview and Scrutiny: i. Note the content of the Elton Reservoir Development Framework Supplement... Agreed Open
3 Sep 2024 MINUTESIt was agreed that the minutes from 24 th July 2024 be approved as a correct record and signed by the Chair. Matters ... Agreed Open
3 Sep 2024 Health and safety reportIt was agreed: - The report be noted Agreed Open
24 Jul 2024 Corporate Parenting ChampionIt was agreed: 1. Councillor Green be appointed as the Corporate Parenting Champion. Agreed Open