INTERNAL AUDIT PROGRESS REPORT

Agreed Finance 4 papers

AI summaryBury Council's Audit Committee has approved changes to the 2025/26 internal audit plan, removing two audits and reallocating days, and noted the quarterly progress report covering October to December 2025.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedPlan changes and progress report both noted
MoneyNo financial implications from the report
What happens next2025/26 audit plan continues11 audits ongoing, 1 draft, 4 allocated
Who it affectsCouncil departments and schoolsAudits and follow-up reviews across the authority

What was decided

The committee approved the changes and amendments to the 2025/26 audit plan, which include removing the Elton High School audit, removing the Capital Programme audit, and transferring 30 days to the investigations and whistleblowing allocation.

The committee noted the internal audit progress report and the work undertaken by Internal Audit during 1 October to 31 December 2025. Report P3, P4

Why

Elton High School is due to convert to academy status in September 2026, so the 14-day audit could not be completed with follow-ups before conversion.

The 17-day Capital Programme audit is removed because no major capital schemes are expected to complete within 2025/26, and is being considered for 2026/27.

The investigations and whistleblowing contingency was overspent by 27 days as at 31 December 2025, requiring 30 days to be transferred from the unplanned work and advice allocation.

What happens next

The 2025/26 audit plan, providing 689 days across Council departments and Persona, will continue to be delivered, with 11 audits in progress, 1 draft report issued, and 4 audits allocated to auditors. Report P11, P12, P13

Outstanding or partially implemented recommendations after second follow-up are reported to the Governance and Assurance Board, which met three times since the last progress report. Report 2.3

Future progress reports will be produced regularly, and the next quarterly update will inform Members of audit activities going forward.

Options considered

  • Chosen: Approve changes and amendments to the 2025/26 audit plan. Reflects school academy conversion, absence of capital schemes, and investigation overspend
  • Chosen: Note the report and the work undertaken by Internal Audit. Standard practice for progress updates to enable Member monitoring Report P5

Implications

  • Legal: The Council must maintain a sound system of internal control under the Constitution's Financial Regulations, and this report evidences compliance. Report P30
  • Equalities: Internal Audit provides assurance that services are delivered in line with policies that consider Equality Act 2010 requirements. Report P26
  • Other: No environmental impact considerations apply, as no decision is required under that heading. Report P27, P28
  • Other: Performance measures and targets up to 31 December 2025 are not highlighting any major areas of concern. Report P19

Who and where

  • All Council departments subject to internal audit reviews Report P20
  • Persona (shared service receiving 36 audit days in 2025/26)
  • Schools including Elton High School, Hollins Grundy Primary School, St Andrew C of E Primary School Ramsbottom, and St Andrew C of E Primary School Radcliffe Report 2.6, P11, P12

Timeline

  • 8 April 2025: 2025/26 Internal Audit Plan approved by Audit Committee
  • 1 October to 31 December 2025: Reporting period covered by this progress report, including 13 completed weeks Report P3
  • During 1 October to 31 December 2025: 8 audit reports finalised, 5 first follow-up reviews and 8 second follow-up reviews completed Report P4, 2.3
  • 31 December 2025: Position date for the updated audit plan shown in Appendix A
  • 17 February 2026: Audit Committee meeting at which the report was considered Report P2
  • September 2026: Elton High School due to convert to Academy status

Plain English for the jargon

  • ISO: The International Organisation for Standardisation
  • CCTV: Close Circuit TV
  • VAT: Value Added Tax
  • GDPR: General Data Protection Regulation
  • DfT: Department for Transport
  • PCIG: Procurement Continuous Improvement Group
  • LGO: Local Government and Social Care Ombudsman
  • DPO: Data Protection Officer
  • DPIA: Data Protection Impact Assessment
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemAU.123

Resolved

It was agreed: That the changes and amendments to the 2025/26 audit plan be approved. That the report and the work undertaken by Internal Audit be noted.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Audit Committee

Classification: Decision Type: Open N/a

Report to: Audit Committee Date: 17 February 2026 Subject: Internal Audit Progress Report Report of: Section 151 Officer

Summary 1. This report outlines the work undertaken by Internal Audit from 1 October to 31 December 2025 which includes the progress to date to complete the 2024/25 audit plan and commence the 2025/26 audit plan. The report enables Members to monitor the work of the Internal Audit service, raise any issues for further consideration and provide an opportunity to request further information or to suggest areas for additional or follow up work. The conclusions drawn from the report are:

 Work on the 2024/25 plan is completed, and the 2025/26 plan has commenced, with 11 reviews ongoing, 1 report at draft stage and 4 audits allocated to auditors.  8 audit reports have been issued during the quarter 3 period.  5 first follow up exercises and 8 second follow up exercises have been completed between the period 1 October to 31 December 2025.

Recommendation(s)  Members note this report and the work undertaken by Internal Audit.  Members to approve the changes / amendments to the 2025/26 audit plan.

_________________________________________________________ Report Author and Contact Details: Name: Adrian Blackshaw / Judith Smith Position: Senior Auditors Department: Corporate Core - Finance E-mail: [email protected] / [email protected] ________________________________________________________________ 1.0 Background 1.1 This report outlines the work undertaken by Internal Audit from 1 October to 31 December 2025. 1.2 Management is responsible for establishing and maintaining appropriate risk management processes, control systems, accounting records and governance arrangements i.e., the control environment. Internal Audit plays a vital role in reviewing whether these arrangements are in place and operating properly and providing advice to managers. On behalf of the Council, Internal Audit review, appraise and report on the efficiency, effectiveness and economy of these arrangements and provide assurance to the organisation (Chief Executive, Executive Directors, and the Audit Committee) and ultimately the taxpayers, that the Council maintains an effective control environment that enables it to significantly manage its business risks. The service helps the Council achieve its objectives and provides assurance that effective and efficient operations are maintained. 1.3 The assurance work culminates in an annual opinion given by the Head of Fraud, Audit Insurance and Risk on the adequacy of the Council’s control environment, based on the work undertaken, and this opinion feeds into the Annual Governance Statement. 1.4 The Internal Audit Plan for 2025/26 provides for 689 days to be delivered across all Council departments and Persona. The Audit plan covers a range of themes and was approved by Audit Committee at the meeting on 8 April 2025. 1.5 Work has been concluded on the outstanding reviews from 2024/25, and work is progressing on the 2025/26 audit plan. Regular progress reports are produced, informing Members of audit activities, and this is the third report of the 2025/26 financial year covering the period from 1 October to 31 December 2025 which includes 13 completed weeks.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Progress Report Plan 2025.26 v1Appendix A 281 KB Download
PDF
Internal Audit Progress ReportAppendix B 192 KB Download
PDF
Performance Measures and Targets 2025-26: End of Qtr 3: v1Appendix C 400 KB Download
PDF
INTERNAL AUDIT PROGRESS REPORTDecisions 413 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 14 attended
RB
Councillor Russell BernsteinCommittee Member, present
DB
Councillor Donald BerryCommittee Member, present
IG
Councillor Iain GartsideCommittee Member, present
MH
Councillor Martin HayesCommittee Member, present
JH
Councillor Jodie HookCommittee Member, present
GM
Councillor Gavin McGillCommittee Member, present
EM
Councillor Elliot MossChair, present
EO
Councillor Eamonn O'BrienAdvisory Member, present
MR
Councillor Miriam RahimovCommittee Member, present
LR
Lynne RidsdaleCouncil Staff, present
MR
Councillor Michael RubinsteinCommittee Member, present
BT
Benjamin ThomasCo-Optee, present

All 14 on the meeting page

On this subject at Bury

Search all
  1. INTERNAL AUDIT PROGRESS REPORTThis decision
  2. Internal audit annual report 2025 -2026Agreed
  3. Global internal audit standards self-assessment and development plan (qaip) 2026/27Agreed
  4. Internal audit progress reportAgreed
  5. Internal audit plan 2026/2027Agreed
  6. Internal audit charter 2026/2027Agreed

More from Bury Audit Committee

All decisions
MeetingDecisionOutcome
19 Oct 2026 Minutes of the last meetingIt was agreed: That the Minutes of the last meeting held on 22 nd July 2026 be approved as a correct record and signe... Agreed Open
19 Oct 2026 Exclusion of press and publicIt was agreed: 1. That the press and public be excluded from the meeting under Section 100 (A)(4), Schedule 12(A) of ... Agreed Open
22 Jul 2026 Internal audit annual report 2025 -2026It was agreed: That the contents of the report be noted. Agreed Open
22 Jul 2026 Global internal audit standards self-assessment and development plan (qaip) 2026/27It was agreed: 1. That the report be noted. 2. That the Internal Audit Development Plan 2026/2027 be approved. Agreed Open
22 Jul 2026 Internal audit progress reportIt was agreed: That the report be noted. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies