Key Decision - Outturn 2009-10- Customer Services and Resources Portfolio
ApprovedScrutiny1 paper
Strategy and Resources Scrutiny Committee approved this item on Monday 5 July 2010. Below is the council's own wording, with the papers it was decided on.
To consider the 2009/10 outturn and carry forward requests Decision of Executive Councillor: (i) Resolved to recommend to Council for approval a carry forward request of £23,440, as detailed in Appendix C of the committee report. (ii) Resolved to recommend to Council for approval a carry forward request of £255,300 for the Customer Access Strategy, as detailed in Appendix C of the committee report. (iii) Resolved to seek approval from Council to carry forward capital resources to fund re-phased capital spending of £668,000 from 2009/10 into 2010/11, as detailed in Appendix D of the committee report. Reason for the As set out in the officer’s report. Any alternative options considered and rejected: N/A Scrutiny Considerations: The Scrutiny Committee considered and approved the recommendations by 7 votes to 0. The Executive Councillor agreed the recommendations.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
Executive summary
1.1This report presents a summary of the 2009/10 outturn position (actual income and expenditure) for services within the Customer Services & Resources portfolio, compared to the final budget for the year. The position for revenue and capital is reported and variances from budgets are highlighted, together with explanations. Requests to carry forward funding arising from certain budget underspends into 2010/11 and future years are identified.
Recommendations
The Executive Councillor is recommended:
a) To agree that the carry forward request of £23,440, as detailed in Appendix C, be recommended to Council for approval.
b) To agree that the carry forward requests totalling £255,300 for Customer Access Strategy, as detailed in Appendix C, be recommended to Council for approval.
c) To seek approval from Council to carry forward capital resources to fund re-phased capital spending of £668,000 from 2009/10 into 2010/11, as detailed in Appendix D.
Report Page No: 1 3. Background
Revenue Outturn
3.1The outturn position for the Customer Services & Resources portfolio, compared to the final revenue budget, is presented in detail in Appendix A.
3.2Appendix B to this report provides explanations of the main variances.
3.3Appendix C sets out the final list of items, for this portfolio, for which approval is sought to carry forward unspent budget from 2009/10 to the next financial year, 2010/11 and future years.
3.4The overall revenue budget outturn position for the Customer Services & Resources portfolio is set out in the table below:
Variation – (Under)/Overspend for the year (264,725) Carry Forward Requests: Customer and Democratic Services – Legal 23,440 Services Customer and Democratic Services - 255,300 Customer Access Strategy
Total Carry Forward Requests 278,740
Net Variance 14,015
The net variance represents a 0.28% variance on final budget for the year
Capital Outturn
3.5Appendix D shows the outturn position for schemes and programmes within the Customer Services & Resources portfolio, with explanations of variances.
Report Page No: 2 3.6 An overall underspend of £756,000 has arisen. £668,000 is due to slippage and re-phasing of the capital programme is required to transfer the budget into 2010/11. The remaining variance of (£88,000) is a result of net underspends on individual capital schemes and programmes.
4. Implications
4.1The net variance from the final budget, after approvals to carry forward budget of £278,740 from 2009/10 to the next financial year, 2010/11 and future years, would result in an increased use of General Fund reserves of £14,015.
4.2In relation to anticipated requests to carry forward revenue budgets into 2010/11 and future years, the decisions made may have a number of implications. A decision not to approve a carry forward request will impact on officers’ ability to deliver the service or scheme in question and this could have staffing, equal opportunities, environmental and/or community safety implications.
Background papers
These background papers were used in the preparation of this report:
• Closedown Working Files 2009/10 • Directors’ Variance Explanations – March 2010 • Capital Monitoring Reports – March 2010 • Budgetary Control Reports to 31 March 2010
Appendices
• Appendix A - Revenue Budget 2009/10 - Outturn • Appendix B - Revenue Budget 2009/10 - Major Variances from Final Revenue Budgets • Appendix C - Revenue Budget 2009/10 - Carry Forward Requests • Appendix D - Capital Budget 2009/10 - Outturn
Report Page No: 3 7. Inspection of papers
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.