Key Decision - Outturn 2009-10- Customer Services and Resources Portfolio

Approved Scrutiny 1 paper

Strategy and Resources Scrutiny Committee approved this item on Monday 5 July 2010. Below is the council's own wording, with the papers it was decided on.

Item10/42/SR

Resolved

To consider the 2009/10 outturn and carry forward requests Decision of Executive Councillor: (i) Resolved to recommend to Council for approval a carry forward request of £23,440, as detailed in Appendix C of the committee report. (ii) Resolved to recommend to Council for approval a carry forward request of £255,300 for the Customer Access Strategy, as detailed in Appendix C of the committee report. (iii) Resolved to seek approval from Council to carry forward capital resources to fund re-phased capital spending of £668,000 from 2009/10 into 2010/11, as detailed in Appendix D of the committee report. Reason for the As set out in the officer’s report. Any alternative options considered and rejected: N/A Scrutiny Considerations: The Scrutiny Committee considered and approved the recommendations by 7 votes to 0. The Executive Councillor agreed the recommendations.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Executive summary

1.1This report presents a summary of the 2009/10 outturn position (actual income and expenditure) for services within the Customer Services & Resources portfolio, compared to the final budget for the year. The position for revenue and capital is reported and variances from budgets are highlighted, together with explanations. Requests to carry forward funding arising from certain budget underspends into 2010/11 and future years are identified.

Recommendations

The Executive Councillor is recommended:

a) To agree that the carry forward request of £23,440, as detailed in Appendix C, be recommended to Council for approval.

b) To agree that the carry forward requests totalling £255,300 for Customer Access Strategy, as detailed in Appendix C, be recommended to Council for approval.

c) To seek approval from Council to carry forward capital resources to fund re-phased capital spending of £668,000 from 2009/10 into 2010/11, as detailed in Appendix D.

Report Page No: 1 3. Background

Revenue Outturn

3.1The outturn position for the Customer Services & Resources portfolio, compared to the final revenue budget, is presented in detail in Appendix A.

3.2Appendix B to this report provides explanations of the main variances.

3.3Appendix C sets out the final list of items, for this portfolio, for which approval is sought to carry forward unspent budget from 2009/10 to the next financial year, 2010/11 and future years.

3.4The overall revenue budget outturn position for the Customer Services & Resources portfolio is set out in the table below:

Customer Services & Resources Portfolio £ 2009/10 Revenue Summary Final Budget (5,081,820) Outturn (5,346,545)

Variation – (Under)/Overspend for the year (264,725) Carry Forward Requests: Customer and Democratic Services – Legal 23,440 Services Customer and Democratic Services - 255,300 Customer Access Strategy

Total Carry Forward Requests 278,740

Net Variance 14,015

The net variance represents a 0.28% variance on final budget for the year

Capital Outturn

3.5Appendix D shows the outturn position for schemes and programmes within the Customer Services & Resources portfolio, with explanations of variances.

Report Page No: 2 3.6 An overall underspend of £756,000 has arisen. £668,000 is due to slippage and re-phasing of the capital programme is required to transfer the budget into 2010/11. The remaining variance of (£88,000) is a result of net underspends on individual capital schemes and programmes.

4. Implications

4.1The net variance from the final budget, after approvals to carry forward budget of £278,740 from 2009/10 to the next financial year, 2010/11 and future years, would result in an increased use of General Fund reserves of £14,015.

4.2In relation to anticipated requests to carry forward revenue budgets into 2010/11 and future years, the decisions made may have a number of implications. A decision not to approve a carry forward request will impact on officers’ ability to deliver the service or scheme in question and this could have staffing, equal opportunities, environmental and/or community safety implications.

Background papers

These background papers were used in the preparation of this report:

• Closedown Working Files 2009/10 • Directors’ Variance Explanations – March 2010 • Capital Monitoring Reports – March 2010 • Budgetary Control Reports to 31 March 2010

Appendices

• Appendix A - Revenue Budget 2009/10 - Outturn • Appendix B - Revenue Budget 2009/10 - Major Variances from Final Revenue Budgets • Appendix C - Revenue Budget 2009/10 - Carry Forward Requests • Appendix D - Capital Budget 2009/10 - Outturn

Report Page No: 3 7. Inspection of papers

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Key Decision: Outturn 2009-10- Customer Services and Resources PortfolioDecisions 105 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
AT
Councillor Amanda TaylorChair, present
MB
Councillor Max BoyceCommittee Member, present
RD
Councillor Robert DrydenCommittee Member, present
LH
Councillor Lewis HerbertCommittee Member, present
CH
Councillor Chris HowellCommittee Member, present
RS
Councillor Raj ShahCommittee Member, present
TW
Councillor Tim WardCommittee Member, present
IN
Councillor Ian Nimmo-SmithCommittee Member, present
SA
Councillor Salah Al BanderCommittee Member, present

On this subject at Cambridge

Search all
  1. Key Decision - Outturn 2009-10- Customer Services and Resources PortfolioThis decision
  2. Non Key Decision - Community Empowerment and Local Participation in Decision MakingRefused
  3. Key Decision - 2009/10 Outturn - Strategy PortfolioApproved
  4. Key Decision - 2009/10 Revenue and Capital Outturn, Carry Forwards and Significant Variances - General Fund - OVERVIEWRefused
  5. Non-Key Decision - Customer Access Strategy OutcomesAgreed
  6. Key Decision - 2009/10 Revenue & Capital Outturn, Carry forward requests and significant variancesRefused

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open