Resolved (unanimously): (i) To approve the capital scheme (which was not included in the Council’s Capital Plan), subject to resources being available to fund the capital and revenue costs associated with the Scheme. The total capital cost of the project was £120,000, and it was proposed that this be funded from specific, identified R&R funds for the purpose, of £99,000 plus DEFRA grant of £21,000 which had already been secured. There were no additional revenue costs arising from the project. The costs associated with the maintenance contract were expected to be similar to current costs. (ii) To approve the carrying out and completion of the procurement of replacement air quality monitoring equipment and associated maintenance contract as detailed in the officer’s report. If the quotation or tender sum exceeded the estimated contract value by more than 15% the permission of the Executive Councillor and Director of Finance would be sought prior to proceeding.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
To: Executive Councillor for Environmental and Waste Services Report by: Jas Lally Head of Refuse and Environment Relevant scrutiny Environment Scrutiny Committee 5/10/2010 committee: Wards affected: All Wards
REPLACEMENT OF AIR QUALITY MONITORING EQUIPMENT Not a Key Decision
1. Executive summary Cambridge City Council monitors air quality at 5 locations as part of its statutory responsibilities. The monitoring instruments at 3 of these locations are now overdue for replacement and require more frequent repairs; some equipment is obsolete and no longer covered by the service contract.
Monitoring with accurate instrumentation is a statutory requirement because the levels of air pollution in Cambridge breach the National Objectives. Accurate measurements are required to declare or remove an Air Quality Management Area. PM2.5 monitoring is a new requirement where a 10% reduction between 2010 and 2020 is to be pursued.
The data provided by these instruments is required for annual progress reporting to Defra.
Objective 3c in the Environmental Services Service Plan is to procure the replacement of air quality monitoring equipment at the permanent air quality monitoring stations in the City.
Funds have been set aside in the Repair and Renewal Fund to fund the purchase of the capital equipment. Also, DEFRA grant funding has been allocated towards the cost of new equipment to monitor PM2.5.
The service/maintenance contract will be included in the tender; the revenue costs are anticipated to be similar to the current costs, so there are no additional revenue implications expected.
The service and maintenance contract for equipment at the two other permanent air quality monitoring stations are anticipated to be similar to the current costs.
Report Page No: 1 2. Recommendations
The Executive Councillor is recommended:
Financial recommendations:
The Executive Councillor is asked to recommend this capital scheme (which is not included in the Council’s Capital Plan) for approval by Council, subject to resources being available to fund the capital and revenue costs associated with the Scheme. The total capital cost of the project is £120,000, and it is proposed that this funded from specific, identified R&R funds for the purpose, of £99,000 plus DEFRA grant of £21,000 which has already been secured.
There are no additional revenue costs arising from the project. The costs associated with the maintenance contract are expected to be similar to current costs.
Procurement recommendations:
The Executive Councillor is asked to approve the carrying out and completion of the procurement of replacement air quality monitoring equipment and associated maintenance contract as detailed below.
If the quotation or tender sum exceeds the estimated contract value by more than 15% the permission of the Executive Councillor and Director of Finance will be sought prior to proceeding.
The estimated contract value is £178,000.
3. Background The project The replacement of air quality monitoring equipment at three of the permanent air quality monitoring stations in the City, including in one an instrument to measure very fine particles. A maintenance obligation for a period of 3 - 5 years will be included as part of the contract.
There is an additional option to include the service and maintenance contract for equipment at the two other permanent air quality monitoring stations.
DEFRA has granted £21,000 towards the costs of the equipment; Repair and Renewal funds will be used to fund the balance.
Report Page No: 2 Target Start date October 2010 Target completion date May 2011 The Cost Total Capital Cost £120,000
Capital Cost Funded from:
Funding: Amount: Details:
Reserves £0 09510 - Environmental Services Repairs & Renewals £99,000 R & R Fund Section 106 £0
Other £21,000 Defra Grant
Revenue Cost
Year 1 £26,500
Ongoing £26,500
The Procurement
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.