CAMBRIDGE CITY COUNCIL
Report Environmental Projects Manager by: To: East Area Committee on 15 April 2011
Wards: Abbey, Coleridge, Petersfield, Romsey
Environmental Improvements Programme
1.0DECISIONS TO BE MADE
NONE
2.0BUDGET
Please see over. EAST AREA COMMITTEE Environmental Improvements Programme 2010-2011
Total Budget Available to 31/3/11 £436,199
COMPLETE Total Spend Forecast TOTAL Previous Spend SCHEME Approved Years 2010/11 COST Budget ADOPTED PROJECTS £ £ £ £ Mill Road Hanging Baskets 2010 3 0 7,210 7,210 7,210 Cherry Hinton Road Shop Forecourts 5,650 64,350 70,000 70,000 Rope Walk 3 41,699 4,042 45,741 47,000 Riverside Conflict Reduction Scheme 60,000 60,000 120,000 120,000 Cavendish Road 26 14,974 15,000 15,000 Staffordshire Street Verge Parking 2,117 82,883 85,000 85,000 Devonshire Road Cycle Bridge Planting 3 41 17,459 17,500 17,500 Perne Road Pedestrian Crossing 3 900 64,100 65,000 65,000 Highway Verges Scheme 0 93,500 93,500 93,500 Mill Road Cemetery 3 0 5,000 5,000 5,000 Romsey Planting 0 22,000 22,000 22,000 Rustat Road Footpath 3 0 10,000 10,000 10,000 Burnside Toad Crossings 3 0 2,500 2,500 2,500 total cost to implement adopted projects 448,018
Uncommitted Budget -11,819
Total Total Spend Estimated to Date Cost SCHEMES UNDER DEVELOPMENT* £ £ Ashbury Close to Golding Rd 0 47,500
total estimated cost of projects in development 0 47,500
Uncommitted Budget -59,319
*Projects agreed by Ctte to be investigated, but no budget committed. Costs shown are estimated and will depend on detailed design and site investigation. N.B. The estimated costs shown above are merely given as a rough guide until the projects can be designed and costed.
15 April 2011 3.0 UPDATE ON PROGRESS OF EXISTING SCHEMES
3.1Riverside conflict reduction and environmental improvement scheme This scheme is currently under construction and is 40% complete. Issues with late delivery of granite materials and amendments required to design levels have delayed delivery. The scheme is due to be complete by early June.
3.2Cherry Hinton Road Shop Forecourts This scheme continues to require considerable Officer time to deliver. I am however pleased to report that the eleven bespoke agreements with the numerous property owners and lessees have now all been signed, a total of thirty two signatures. We are now able to instruct our Contractor to commence construction work as soon as possible. This is expected by the end of the month following a lead in period for ordering materials.
3.3Perne Road The provision of this new pedestrian crossing is now complete.
3.4Staffordshire Street Diversionary works to utility apparatus by BT and Virgin Media are currently underway. The construction of the new parking bays will then commence and are expected to be complete by the end of May.
3.5Romsey Planting Work to improve the planting areas in the Romsey area is currently underway, with the majority of the replacement planting due to take place in the autumn.
3.6Greville Rd Verges The traffic regulation order and associated lining are complete for this scheme, including the installation of the bollards along both verges. The repairs and reseeding of the verges are currently under way and are expected to be complete shortly.
3.7Birdwood/Chalmers Verges Construction work is due to start on 11th April to install the verge strengthening system and is expected to be complete by early May.
3.8Rawlyn Road Verges The road widening at either end of Rawlyn Road is now complete. 3.9 Galfrid Road Verges The provision of blockwork surfaced layby at the corner of Galfrid Road and Whitehill Road is now complete.
3.10Rustat Road Footpath Extension This scheme is now complete. The replacement hedge will be planted in the autumn.
3.11Burnside Toad Crossings These are now complete.
3.12Mill Road Cemetery The £5000 grant has been provided.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Environmental Improvements Programme UpdateReport | 53 KB | DownloadRead as text |
Follow East Area Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2021 | Open ForumAgreed it was vital that residents understood the documentation and would be happy to arrange assistance when looking... | Agreed | Open |
| 3 Dec 2020 | Policing and Safer NeighbourhoodsRESOLVED unanimously to write to the Acting Police and Crime Commissioner highlighting the Committee’s concern regard... | Decided | Open |
| 17 Sep 2020 | Election of Chair and Vice Chair - EACResolved unanimously that Councillor Barnett be Chair for the ensuing year. Councillor Barnett assumed the chair from... | Decided | Open |
| 17 Sep 2020 | Policing and Safer NeighbourhoodsResolved unanimously to approve the following as local areas of concern: i. Anti-social driving ii. Cycle theft iii. ... | Approved | Open |
| 17 Sep 2020 | Outside Body Appointment: Cambridge Airport Consultative CommitteeResolved that Councillor Davey be the representative for the Cambridge Airport Consultative Committee for the ensuing... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.