Resolved (unanimously) the application from Kings Church, as set out in the project appraisal at Appendix B of the officer’s report was suitable for funding from resources allocated to Community Development Capital Project Grants for the East Area. Resolved (unanimously) to recommend to the Executive Councillor for Community Development and Health that a capital grant of up to £100,000 be awarded to Kings Church for the improvement and refurbishment of their premises, subject to compliance with the Council’s legal agreement. Resolved (by 10 votes to 0) The Area Committee recommended to advise the Executive Councillor for Community Development and Health that, having considered the request from Squeaky Gate Studios for an additional £7,602, this was suitable for funding from resources allocated to Community Development Capital Project Grants for the East Area.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1The project This project aims to improve the existing chapel building, ensuring that it is ‘fit for purpose’ as a community hub and church, serving the Petersfield area and beyond. The project will be achieved by adding a first floor to the existing chapel building; maximising the available community space; upgrading the existing kitchen and toilet block and creating additional facilities for people with disabilities: a disabled users’ toilet and a lift for access to the first floor.
The benefits of the project will be to enhance the community asset represented by King’s Church and to sustain and open up much wider opportunities for community use. The tangible benefits will be the addition of community space and the upgrade of the community resource; with the intangible benefit of creating a social and learning space for the Church’s diverse community guests. The immediate benefit will be to sustain and improve the resource, making it a more convenient, attractive, and accessible environment, with the future potential of serving many more people in the years to come.
Target Start date 3rd October 2011 Target completion date 30th April 2012
D:\moderngov\data\published\Intranet\C00000147\M00000696\AI00003904\$q35fw3sn.doc Page 2 of 10 1.2 The Cost Total Capital Cost £194,686.00 (inc. VAT)
Total Revenue Cost There are no revenue implications for the City Council
Capital Cost Funded from:
Funding: Amount: Details:
Existing Funds £20,000 Funds available from the Church
Fundraising £74,686 Fundraising activities by the Church
Capital Grant £100,000 East Area Capital Grant application
Capital Grant to be funded from (S106 Agreement References) 02/1132/FP 22,167 03/0037/FP 7,534 03/0547/FP 1,237 03/1006/FP 1,237 03/1405/FP 2,374 04/0009/FP 4,748 04/0295/FP 1,188 04/0488/FP 4,796 04/0965/FP 2,579 04/1015/FP 1,878 04/1373/FUL 1,929 05/0014/FUL 1,194 05/0100/FUL 2,462 05/0343/FUL 1,431 (PART) 06/0328/FUL 7,818 06/0732/FUL 7,595 99/0314/FP 27,833 Total £100,000
D:\moderngov\data\published\Intranet\C00000147\M00000696\AI00003904\$q35fw3sn.doc Page 3 of 10
1.3The Procurement PROJECT PHASES CONTRACTS TYPE Weeks Phase 1 - Mezzanine TBC 10 Construction, fire alarms and smoke detectors Phase 2 - Heating Installation Lump Sum (Fixed Contract) 3
Phase 3 - Lift Installation and TBC 3 carpet fitting Phase 4 - Construction of New Lump Sum (Fixed Contract) 7 Toilet Block and Disabled Toilets Phase 5 - Upgrade Kitchen Lump Sum (Fixed Contract) 5 and Kitchen Furnitures Note: Detailed quotations have been obtained for all the above work.
2 Capital Project Appraisal & Procurement Report
2.1What is the project?
Phase 1 The first phase of the project will be the removal of the current partition and one false ceiling in the existing chapel and the construction of the mezzanine floor. This will involve the delivery and installation of the mezzanine and two staircases: a rear staircase and a double width ambulant staircase. The mezzanine underside will be fitted with a suspended ceiling, lighting and a new distribution board. Phase 1 will also include the installation of smoke detectors and a fire alarm system, plus the erection of a number of partition walls, creating community rooms downstairs and religious space upstairs. This phase will take approximately ten weeks to complete (October – December 2011) and will be the primary expense of the project. It will cost £95,280.00 (incl. VAT).
Phase 2 The second phase will be the installation of a new energy efficient heating system into the chapel venue. This will service the entire building and take an estimated three weeks to install. This work will cost £11,000.00 (incl VAT) and is programmed to take place in December 2011.
Phase 3
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Policing and Safer NeighbourhoodsRESOLVED unanimously to write to the Acting Police and Crime Commissioner highlighting the Committee’s concern regard...
Election of Chair and Vice Chair - EACResolved unanimously that Councillor Barnett be Chair for the ensuing year. Councillor Barnett assumed the chair from...
Policing and Safer NeighbourhoodsResolved unanimously to approve the following as local areas of concern: i. Anti-social driving ii. Cycle theft iii. ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.