Environment Scrutiny Committee, Tuesday 4 October 2011 at 4.00pm

New and Replacement Bus Shelter Project Appraisal

Approved Scrutiny 2 papers

Environment Scrutiny Committee approved this item on Tuesday 4 October 2011. Below is the council's own wording, with the papers it was decided on.

Item11/55/ENV

Resolved

There were currently 176 bus shelters across Cambridge, 25 owned by the County Council, 89 by Clearchannel (formally Adshel) and the remaining 62 owned by the City Council. The Officer’s report proposed to replace approximately 60% of the 62 City Council owned shelters and also provide 10 new shelters at existing bus stops. Decision of Executive Councillor for Planning and Sustainable Transport: (i) Approved financial recommendations – · Approved commencement of the project, which was already included in the Council’s Capital Plan (PR018) with additional £50,000 funding. The total capital cost of the project was £267,000, this was to be funded £217,000 Reserves and £50,000 R&R for new and replacement shelters. · The revenue costs of the project were £8,400, these would be the subject of a separate revenue bid. (ii) Approved procurement recommendations - · Approved the carrying out and completion of the procurement of new and replacement bus shelters. · If the quotation or tender sum exceeded the estimated contract value by more than 15%, the permission of the Executive Councillor and Director of Finance would be sought prior to proceeding. Reason for the As set out in the Officer’s report. Any alternative options considered and rejected: Not applicable. Scrutiny Considerations: The committee received a report from the Project Delivery & Environment Manager regarding the new and replacement bus shelter project appraisal. In response to Member’s questions the Project Delivery & Environment Manager confirmed the following: (i) The Streetscene Operations Manager and colleagues monitored the performance of Clearchannel regarding provision and maintenance of bus shelters. The Project Delivery & Environment Manager undertook to liaise with Planning Officers, residents and Area Committee Councillors concerning the proposed new and replacement shelters. Further local consultation would only take place with directly affected residents for new shelter sites. The Project Delivery & Environment Manager undertook to provide maps to Members setting out proposals for bus shelter locations and actions required (eg repair/replacement). (ii) The design of bus shelters would be appropriate for their locations (eg in conservation areas). Bus shelters would have a design life of 20 years. The City Council would be responsible for the maintenance of any shelters that it put in. (iii) Adshel had previously put in bus shelters at their own expense, covering the cost through advertisements on the shelters. It would therefore require planning permission to move the shelters. The relocation of shelters could be reviewed at the end of the agreement with Clearchannel/Adshel in 2019. (iv) It was the responsibility of the County Council, not City Council, to provide bus timetable information. The Officer undertook to liaise with county colleagues concerning the introduction of real time display information as part of the bus shelter overhaul. The committee resolved unanimously to adopt the recommendation. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) Not applicable .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Summary

1.1The project There are currently 176 bus shelters across Cambridge, 25 owned by the County Council, 89 by Clearchannel (formally Adshel) and the remaining 62 owned by the City Council.

This project proposes to replace approximately 60% of the 62 City Council owned shelters, identified from a condition survey and also provide 10 new shelters at existing bus stops, identified from passenger volumes and stakeholder consultation.

D:\MODERNGOV\DATA\PUBLISHED\INTRANET\C00000177\M00000709\AI00004156\$I5O5QGHE.DOC Page 2 of 9

Target Start date 5th October 2011 Target completion date 31st March 2012

1.2The Cost

Capital Cost Funded from:

Funding: Amount: Details: Bus Shelters Capital Reserves £217,000 Programme PR018

Other £50,000 Bus Shelter R&R Budget

TOTAL £267,000

Revenue Cost

Year 1 £8,400

Ongoing £8,400

1.3The Procurement All construction services will be procured externally from Cambridgeshire County Council through their contract with Cambridgeshire Highways. This arrangement is regulated by the existing Agency Agreement between the City and County Council. The procurement of highway construction services through this route was approved by Environment Scrutiny Committee in October 2010. An extension to this approval is also being sort from Strategy and Resources Scrutiny Committee in October, whilst the procurement of a new City Council Civil Engineering Construction framework is completed.

The Streets and Open Spaces Project Delivery Team will provide all design and supervision services within the current budget.

D:\MODERNGOV\DATA\PUBLISHED\INTRANET\C00000177\M00000709\AI00004156\$I5O5QGHE.DOC Page 3 of 9 2 Capital Project Appraisal & Procurement Report

2.1What is the project? The City Council currently owns and maintains 62 bus shelters across the city, many of which are in need of replacement being difficult to maintain due to the lack of available spare parts following the demise of the manufacturer. This project proposes to replace 60% of the existing shelter stock, targeting those with the greatest need, identified through a condition survey that has recently been carried out. The continuing need for existing shelters will also be assessed, as bus routes may have changed over time reducing the level of use of certain shelters.

It is also proposed to provide 10 new shelters at existing bus stops. The routes with higher passenger volumes will take priority, along with areas of the City where bus use is predominantly by vulnerable groups such as the elderly and infirm.

Consultation will take place with key stakeholders such as the County Council and bus operators and proposals will be presented to Area Committees for comment and review.

Further consultation with directly affected residents will be carried out for the 10 new shelter sites, any objections will be presented to Ward Councillors to determine.

2.2What are the aims & objectives of the project?

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bus Shelter Project Appraisal_Sept 2011_Amended /55/ENVReport 175 KB DownloadRead as text
PDF
New and Replacement Bus Shelter Project AppraisalReport 172 KB Download

At this meeting

Whole meeting

Who was there

9 of 10 attended
SK
Councillor Simon KightleyChair, present
PS
Councillor Paul SaundersVice-Chair, present
LH
Councillor Lewis HerbertCommittee Member, present
GM
Councillor Gail Marchant-Daisley Labour Spokes for Planning and Sustainable TransportCommittee Member, present
GO
Councillor George Owers Labour Spokes for Environmental and Waste ServicesCommittee Member, present
PT
Councillor Philip TuckerCommittee Member, present
DT
Councillor Damien TunnacliffeCommittee Member, present
MW
Councillor Margaret Wright Green SpokesCommittee Member, present
RZ
Councillor Roman ZnajekCommittee Member, present
AP
Councillor Adam PogonowskiReserve

On this subject at Cambridge

Search all
  1. New and Replacement Bus Shelter Project AppraisalThis decision
  2. New and Replacement Bus Shelter ProgrammeApproved
  3. New and Replacement Bus Shelter ProgrammeApproved

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies