Cambridge City Council
Environment Scrutiny Committee, Tuesday 10 January 2012 at 4.00pm

Route Optimisation Project for Refuse and Recycling Collections - Options for Change

Agreed Scrutiny 3 papers

Environment Scrutiny Committee agreed this item on Tuesday 10 January 2012. Below is the council's own wording, with the papers it was decided on.

Item12/7/ENV

Resolved

The Officer’s report set out options for change to the domestic waste service and a methodology for considering these options. Consultation with staff would be carried out under the council’s Organisational Change Policy – October 2010. The implementation of the agreed scenario would take place in July 2012, with an extensive resident communications campaign prior to this. Decision of Executive Councillor for Environmental & Waste Services: (i) I nstructed the Director of Environment to undertake consultation with the staff and unions about a preferred option based on the scenarios set out in the foregoing report and subject to modelling data to be provided at the meeting of the Committee on 10 January 2012. (ii) Instructed the Director of Environment to implement the preferred option subject to the results of the staff and union consultation and also subject to consultation with the Executive Councillor, Chair and Opposition Spokespersons. Reason for the As set out in the Officer’s report. Any alternative options considered and rejected: Not applicable. Scrutiny Considerations: The committee received a report from the Head of Refuse and Environment regarding the Route Optimisation Project for Refuse and Recycling Collections - Options for Change. The Officer also referred to an addendum document available as part of the fourth circulation agenda. In response to Member’s questions the Executive Councillor for Environmental & Waste Services plus Head of Refuse and Environment confirmed the following: (i) Waste collections for new developments would be introduced wherever possible with the same collection methodology for existing houses. This will standardise the service wherever possible across the city, reducing the need for specific vehicles for specific material and increasing the efficiency of the service. The Environment Committee authorised Executive Councillor, Chair and Spokes, in consultation with officers to take the decision to implement the above in March 2010. As it is a key decision affecting the whole City, it was decided to return it to scrutiny committee. Informal consultation would be undertaken with refuse collection crews concerning the two options to seek views on which is the most efficient. Formal consultation would then be undertaken on the preferred option. The formal public consultation would reflect feedback from the public survey, and provide a steer if opinions were split in the crew's informal consultation. The aim was to ascertain route practicability as opposed to purely cost savings. (ii) Officers were in discussion with the contracted recycling company to ascertain if it was feasible to take plastic containers under the current contract. South Cambridgeshire District Council had different contract specifications with another company, which required them to take plastic containers. (iii) The introduction of in-cab technology aimed to provide information on when bins were either put out or not for collection by households. (iv) Planning plus Refuse and Environment Officers were undertaking joint work to model optimum routes for refuse collection services. The software modelled rounds to service properties on new and existing developments. (v) Information concerning waste collection rounds was being compiled from various sources into the model as part of the route optimisation review, to ensure that it would be available in a central resource in future. (vi) Comments from members of the public in the 2011 Waste & Recycling Strategy showed opposition to microchipping bins to monitor recycling. Officers stated there was no intention to microchip bins in future. (vii) A review of waste composition would feed into waste collection scenarios as part of the route optimisation review. This would be the basis of a strategy. For example, a weekly bin collection may not be required if the public favoured green bins (for food waste etc). Recycling bank location and provision was also being considered as part of the route optimisation review. The Chair decided that the recommendations highlighted in the Officer’s report should be voted on and recorded separately: The committee approved recommendation (i) unanimously. The committee approved recommendation (ii) by 5 votes to 0. The Executive Councillor approved the recommendations. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) Not applicable .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Executive summary

1.1This report sets out options for change to the domestic waste service and a methodology for considering these options. An update report will be tabled at the Committee recommending the Executive Councillor to instruct the Director of Environment to consult staff and unions on a preferred option. Unfortunately it is not possible to provide the modelling results now as this exercise is not complete. This report is designed to give members as much information as possible before the meeting so that the tabled update need only be brief. This report contains information about the criteria by which the various scenarios will be judged. The two aims below are included within the list of criteria.

1.2The aims of the Route Optimisation project are:- • To reduce the cost of refuse & recycling operations at Cambridge City Council from the 2011/12 base budget in time for 2012/13 financial year. • To reduce the fuel usage based on 2010/11 figures and consequently carbon emissions from the refuse & recycling fleet at Cambridge City Council from 2012/13.

1.3Consultation with staff will be carried out under the council’s Organisational Change Policy – October 2010. Officers are keen for staff to be fully engaged with this process and to support the proposed improvements.

1.4The route optimisation software is designed to take the existing collection round information and within certain set parameters (eg Report Page No: 1 length of working day) calculate the optimum amount of resource required to operate services efficiently and determine the most efficient routes for the collection services.

1.5The implementation of the agreed scenario will take place in July 2012, with an extensive resident communications campaign prior to this.

Recommendations

The Executive Councillor is recommended:

2.1To instruct the Director of Environment to undertake consultation with the staff and unions about a preferred option based on the scenarios set out in the foregoing report and subject to modelling data to be provided at the meeting of the Committee on 10 January 2012;

2.2To instruct the Director of Environment to implement the preferred option set out in 2.1 subject to the results of the staff and union consultation and also subject to consultation with the Executive Councillor, Chair and Opposition Spokespersons.

Background

3.1This project began in June 2011 with the purchase of route optimisation software. Baseline or current collection round data has been entered into the system to build an accurate picture of existing collection rates and routes. In order for the computer model to be accurate an extensive mapping exercise was required. This data takes account of the number of bins at each property, the average weight of each bin, properties that share bins and how long it takes to collect bins in each street. The model also looks at other parameters such as:- • safe working practices eg single sided collections on busy roads • legal working practices eg number of breaks required in a certain period, daily rests and weekly rests. • standard working week • geographic matters that apply specifically to Cambridge eg the number and location of busy main roads, etc. • how long it takes to tip the collected load and how frequently this is required • restrictions on collection times eg schools arrival and departure times, not collecting in residential areas before 7am etc.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Route Optimisation Addendum /7/ENVAddendum 33 KB Download
PDF
Route Optimisation App A: Waste and Recycling Survey Report_Compressed /7/ENVAppendix 47 pages Download
PDF
Route Optimisation Project for Refuse and Recycling Collections: Options for ChangeReport 81 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 12 attended
SK
Councillor Simon KightleyChair, present
PS
Councillor Paul SaundersVice-Chair, present
LH
Councillor Lewis HerbertCommittee Member, present
GM
Councillor Gail Marchant-Daisley Labour Spokes for Planning and Sustainable TransportCommittee Member, present
GO
Councillor George Owers Labour Spokes for Environmental and Waste ServicesCommittee Member, present
PT
Councillor Philip TuckerCommittee Member, present
DT
Councillor Damien TunnacliffeCommittee Member, present
MW
Councillor Margaret Wright Green SpokesCommittee Member, present
RZ
Councillor Roman ZnajekCommittee Member, present
AP
Councillor Adam PogonowskiReserve
JS
Councillor Jean SwansonExecutive Councillor, present
TW
Councillor Tim WardExecutive Councillor, present

On this subject at Cambridge

Search all
  1. Route Optimisation Project for Refuse and Recycling Collections - Options for ChangeThis decision
  2. Implementation of Route Optimisation outcomes for change in April 2012.Approved

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies