CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cambridge City Council
Strategy and Resources Scrutiny Committee, Monday 16 January 2012 at 5.00pm

Budget-Setting Report (BSR) - Revenue and Capital Budgets

Approved Scrutiny 3 papers

Strategy and Resources Scrutiny Committee approved this item on Monday 16 January 2012. Below is the council's own wording, with the papers it was decided on.

Item12/18/SR

Resolved

To consider the draft revenue and capital budgets. Decision of the Executive Councillor for Strategy & Climate Change : Please note: All page references relate to the BSR which can be found at: Link 1 : The circulated amendments to the BSR – Revenue and Capital Budgets 2011/12 (Revised), 2012/13 (Budget) and 2013/14 (Forecast) can be found at: Link 2: The Executive Councillor for Strategy & Climate Change resolved to: General Fund Revenue Budgets and Cash Limit / Savings Target: [Section 4, page 30 of the BSR refers] Budget 2011/12: a) Approve, with any amendments, the revised budget items shown in Appendix D (page 75 of the BSR) - as amended for the attached replacement page 79 in Appendix D (see Link 2 above). b) Approve, with any amendments, the overall revised budget for 2011/12, as shown in Section 4 (page 30 of the BSR) and Appendix G(a) (page 109 of the BSR) for General Fund Services. Budget 2012/13: c) Agree any recommendations for submission to the Executive in respect of: • Bids to be funded from External or Earmarked Funds [Appendix H, page 112 of the BSR, refers] – as amended for the attached replacement page 113 in Appendix H (see Link 2 above). • Non Cash Limit items [Appendix E, page 86 of the BSR refers] • Revenue Savings and Bids [Appendix F, page 87 of the BSR refers] • Priority Policy Fund (PPF) Bids [Appendix I(a), page 116 of the BSR refers] – based on the position as outlined in Section 4 (page 37 of the BSR refers). d) Recommend to Council the Council Tax base, as set out in Appendix C (a) (page 74 of the BSR), and the level of Council Tax for 2012/13, based on a 99% collection rate [Section 3, page 27 of the BSR refers]. e) Recommend to Council to approve: (i) the Prudential Indicators as set out in Appendix T(a) (page 193 of the BSR refers) and to confirm that the “Authorised Limit” determined for 2012/13 will be the statutory limit determined under section 3 of the Local Government Act 2003. (ii) to delegate to the Director of Resources, within the borrowing totals for any financial year within (i) above, to effect movement between the separately agreed figures for ‘borrowing’ and ‘other long term liabilities’. (iii) the Treasury Management Annual Borrowing and Investment Strategies set out in Appendices T(b) (page 199 of the BSR refers) and T(c) (page 201 of the BSR refers), particularly: • to increase the maximum sum that can be invested with HSBC Bank Plc from £12m to £16m. · to amend the limit for a single named institution from £6m to £10m; (retaining the existing maximum sum which may be invested with counterparties belonging to the same company group at 1.5 times the level for a single named institution); and • to have the flexibility to use other financial means available to the Council, such as bank call accounts, notice accounts, money market funds, treasury bills and gilts. However, use of such financial instruments would be subject to an assessment in conjunction with the Council’s treasury management advisors (Sector) to ensure that it would not prejudice the council’s deposit priorities. (iv) amendments to the Council’s Approved Lending (Revised Counterparty) List, shown in Appendix T(c), Annex 3 (page 210 of the BSR refers) f) Delegate to the Director of Resources authority to finalise changes relating to the corporate and departmental restructuring and any reallocation of support service and central costs, in accordance with the CIPFA Best Value Accounting Code of Practice and the Service Reporting Code of Practice for Local Authorities (SeRCOP). Capital: [Section 6, page 47 of the BSR refers] Capital & Revenue Projects Plan: [section 6, page 50 of the BSR] g) Approve the following project appraisals, that have been referred by Executive Councillors: From the Executive Councillor for Arts, Sport and Public Spaces: (i) Cherry Hinton Hall Grounds improvements (ii) Coleridge Recreation Ground improvements From the Executive Councillor for Community Development & Health: (i) Centre at St Paul’s –Redevelopment of the main hall (ii) Clay Farm Community Centre (separate Report on CD&H agenda) From the Executive Councillor for Housing: (i) Energy Efficiency Grant (ii) Landlord Accreditation Grant From the Executive Councillor for Environmental & Waste Services: (i) Vehicle replacements 2012/13 From the Executive Councillor for Customer Services and Resources: (i) Content Management System Replacement (ii) Introduction of a metered electricity supply on Cambridge Market (iii) Electronic Market Management System h) Agree any recommendations to the Executive in respect of the bids outlined in Appendix O(a) (page 159 of the BSR) – as amended for the attached (see Link 2 above). From the Executive Councillor for Planning and Sustainable Transport: Approve the removal of H28 – Park Street Car Park, as identified in Appendix P (page 182 of the BSR refers, from the Council’s Hold List, for submission to the Executive. i) Agree the Capital & Revenue Projects Plan, as shown in Appendix M (page 141 of the BSR) for the General Fund (which will be updated to incorporate rephrasing, new bids and the above recommendations) and Appendix S (to be included in Version 3 of the BSR – see Note) for the Housing Capital Investment Programme. Note that revised Housing Capital Investment Plan for 2011/12 to 2016/17, will be presented to the special joint Housing Management Board and Community Services on 8 th February 2012, to include the impact of in year savings in capital budgets, re-allocation of budgets for decent homes works, rephrasing of existing projects and schemes and incorporation of capital bids (as detailed in Appendix O(b), page 177 of the BSR refers). j) Note the impact of revenue and capital budget approvals and approve the resulting level of reserves to be used to: (i) support the 2011/12 budget (ii) support the 2012/13 and future years budgets. (Appendix G(c), page 111 of the BSR refers) Recommendation k) - NEW : Approve contribution to Climate Change Fund in 2012/13 of £129,050. (This was previously included in page 109 of Appendix G(a)of the BSR under the line for “Use GF reserves above £5m”. Recommendation l) - NEW : To agree inclusion in the Capital & Revenue Projects Plan of new items identified below, to note additional funding for revised schemes approved by Executive Councillors namely: • PR018 - Bus Shelters • SC517 - Fuel Tanks Relining • SC518 - Corn Exchange Lighting Improvement • SC519 - Wulfstan Way Art Project • SC520 - Community Olympic Public Art Commission Also attached are updated tables [Page 51 of the BSR refers] and Appendix Q [page183 of the BSR] in the BSR reflecting the above changes (see Link 2 above). Housing Revenue Account [Part 5, page 41 of the BSR refers] • Whilst there are no changes at this stage, Council will consider the recommendations of the special Housing Management Board and Community Services Scrutiny Committee regarding Housing Self Financing at the meeting on 23rd February 2012. Reasons for the Decision : As set out in the officer’s report Any alternative options considered and rejected: N/A Scrutiny Considerations The committee received a report from the Director of Resources who highlighted the amendments as circulated. The Scrutiny Committee considered and approved the recommendations by 4 votes to 0. The Executive Councillor for Strategy & Climate Change approved the recommendations.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Strategy & Resources Scrutiny Committee 16 January 2012 (and The Executive 19 January 2012)

Amendment to Agenda Item 18: Budget-Setting Report (BSR) - Revenue and Capital Budgets 2011/12 (Revised), 2012/13 (Budget) and 2013/14 (Forecast).

This amendment consolidates changes that are being presented to individual Scrutiny Committees in this January cycle and other significant changes where they refer to the BSR and recommendations made in the original report to Strategy & Resources Scrutiny Committee.

Please note that all page references refer to the page numbering in the Budget Setting Report. All the changes outlined below will be incorporated in version 4 which will be presented to Council on 23 February 2012.

These amendments relate to:

• An additional External Funded Bid (X2995 – Community Development posts funded from Developers Contributions) [Appendix H at page 113] • An adjustment to a capital bid (C2982 – Cancellation of Solar PV Panel Installation) [Appendix Appendix O (a) at page 175 and Appendix R at page 185] • An adjustment for the Climate Change Fund Contribution [Appendix G(a) at page 109] • Corrections to wording and cross-referencing Appendix D at page 79 (various) Appendix H at page 172 - Item C2740 • Equalities Impact Assessment, Appendix W and updated Contents Page

Budget 2011/12:

Recommendation a):

• Approve, with any amendments, the revised budget items shown in Appendix D (page 75) - as amended for the attached replacement page 79 in Appendix D.

Budget 2012/13:

Recommendation c) (first bullet point):

Agree any recommendations for submission to the Executive in respect of:

• Bids to be funded from External or Earmarked Funds [Appendix H, page 112, refers] - as amended for the attached replacement page 113 in Appendix H.

Capital:

Recommendation h): • Agree any recommendations to the Executive in respect of the bids outlined in Appendix O(a) (page 159) - as amended for the attached Recommendation k) - NEW: Approve contribution to Climate Change Fund in 2012/13 of £129,050. (This was previously included in page 109 of Appendix G(a) under the line for “Use GF reserves above £5m”.

Recommendation l) - NEW: To agree inclusion in the Capital & Revenue Projects Plan of new items identified below, to note additional funding for revised schemes approved by Executive Councillors namely:

• PR018 - Bus Shelters • SC517 - Fuel Tanks Relining • SC518 - Corn Exchange Lighting Improvement • SC519 - Wulfstan Way Art Project • SC520 - Community Olympic Public Art Commission

Also attached are updated tables [Page 51 refers] and Appendix Q [page 183] in the BSR reflecting the above changes.

Housing Revenue Account [Part 5, page 41 refers]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Amendment to Item 18: BSR: Revenue and Capital Budgets 2011/12 (Revised), 2012/13 (Budget) and 2013/14 (Forecast). /18/SRReport 560 KB DownloadRead as text
PDF
BSR Version Ver 1.1 21 Dec 2011_1 /18/SRReport 3.9 MB Download
PDF
Budget-Setting Report (BSR): Revenue and Capital BudgetsReport 54 KB Download

At this meeting

Whole meeting

Who was there

9 of 11 attended
MB
Councillor Max BoyceChair, present
CR
Councillor Colin RosenstielVice-Chair, present
SA
Councillor Salah Al BanderCommittee Member, apologies, sent representative
MA
Councillor Mark AshtonCommittee Member, present
JB
Councillor Jeremy Benstead Labour Spokes for Customer Services and ResourcesCommittee Member, present
SB
Councillor Sarah BrownCommittee Member, present
LH
Councillor Lewis Herbert Labour Spokes for Strategy and Climate ChangeCommittee Member, present
IN
Councillor Ian Nimmo-SmithCommittee Member, present
AP
Councillor Adam Pogonowski Green SpokesCommittee Member, apologies
PS
Councillor Paul SaundersReserve, present as substitute
MW
Councillor Margaret WrightReserve, apologies

On this subject at Cambridge

Search all
  1. Budget-Setting Report (BSR) - Revenue and Capital BudgetsThis decision
  2. Budget Setting Report and Medium Term Financial Strategy 2026-27Agreed
  3. Cabinet: Update on Budget Setting Consultation 2025-26Noted
  4. Budget Setting Context 2026-27Agreed
  5. HRA Budget-Setting Report (BSR) 2025/26Agreed
  6. General Fund Budget Setting Report 2025/26 to 2029/30Approved

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies