Lion Yard Public Toilet Refurbishment - Project Update
ApprovedCommittee1 paper
Public Toilets (Lion Yard) Working Party approved this item on Monday 19 March 2012. Below is the council's own wording, with the papers it was decided on.
Resolved by 5 votes to 0 to: (i) Note progress with the project (ii) Approve the proposed stages for project delivery [nb. Cllr Swanson did not vote because of her position as the Executive Councillor being advised by the Working Party on the matter which is one of its Terms of Reference]
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Public Toilets (Lion Yard) Working Party
Recommendations
The Working Party is recommended to:
i) note progress with the project. ii) approve the proposed stages for project delivery.
Background
• A £300,000 capital bid to extend the existing Public Conveniences Capital Programme was approved at Council on 23rd February, as part of the Budget Setting Report for 2012/13. • This funding was approved on the basis it would provide an initial £300,000 budget for the refurbishment of the public toilets in Fisher Square. • This is a preliminary budget until the outcome of a structural investigation. Significant structural issues could lead to a further bid to increase the project budget in order to make the project deliverable. • The structural report is expected to be available around the time of this meeting and a summary will be provided verbally if possible. • The delivery of this project is indirectly linked to the proposed redevelopment of the Lion Yard Shopping Centre by Aberdeen Asset Management.
Report Page No: 1 • Current proposals to close the entrance to the Lion Yard Shopping Centre in Fisher Square as part of this redevelopment would have to be taken into account in the refurbishment of the public toilets. • There are some significant issues surrounding this proposed closure that must be fully resolved before any further work can be carried out on this toilet refurbishment project.
4. Outline Project Plan
• Once the redevelopment proposals have been resolved, the toilet refurbishment project can begin. • For the purposes of the project plan outlined below, a ‘virtual’ start date of October 2012 has been used.
Concept Preparation of outline architect October 2012 STAGE 1
Design designs, specifications and to preliminary costs. January 2013
Consultation City wide public consultation on February 2013 STAGE 2
concept proposals and options, to giving the public the ability to April 2013 directly input into the design process.
Preliminary Further development of the design May 2013 STAGE 3
Design and specifications based on the to results of the public consultation. July 2013
Approvals Submission of a project appraisal July 2013 for review by the City Councils’ STAGE 4
Asset Management Group and approval by the Executive Councillor for Environmental and Waste Services at Environment Scrutiny Committee. Detailed Preparation of detailed technical August 2013 STAGE 5
Design designs and specifications and to preparation of information to enable September 2013 procurement of building services.
Report Page No: 2 Procurement OJEU Tender process. August 2013 Preparation of OJEU advert. to Review of expressions of interest. January 2014 STAGE 6
Release tender documents to shortlisted Contractors. Assess tender returns. Award Contract for Building Services.
Construction Mobilisation of Contractor. February 2014 STAGE 7
Contract administration. to Completion of Refurbishment. May 2014
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Public Toilets (Lion Yard) Working Party at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Public Toilets (Lion Yard) Working GroupResolved unanimously to: i. Agree to disband as its business as described in the terms of reference set by the Leader...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.