Cambridge 20mph Project

Agreed Scrutiny 3 papers

Environment Scrutiny Committee agreed this item on Tuesday 15 January 2013. Below is the council's own wording, with the papers it was decided on.

Item13/8/ENV

Resolved

The Executive Councillor was asked to agree the project scope, initiation, and programme. Also for spending to be authorised on initial project costs. Decision of Executive Councillor for Planning and Climate Change : The Executive Councillor resolved to: i. Approve initiation of the project and initial project costs in accordance with the project documentation referenced in the Officer’s report, with implementation subject to further scrutiny, and approval of project appraisals. ii. Approve the Programme as detailed in Appendix A of the Officer’s report. iii. Approve the Governance/Decision making process as set out in section 4 of the Officer’s report. iv. Approve the Board terms of reference as detailed in Appendix B of the Officer’s report. v. Approve the phasing as detailed in Appendix C of the Officer’s report. vi. Approve the Engagement/Consultation to commence for the first phase as detailed in Appendix D of the Officer’s report. Approve the following estimated initial project spending: vii. Automatic Traffic Counts (ATCs) for project baseline data collection – < £12,000 viii. Project wide Engagement/Consultation Activities – < £50,000 Reason for the As set out in the Officer’s report. Any Alternative Options Considered and Rejected: Not applicable. Scrutiny Considerations: The Committee received a report from the Officer regarding the Cambridge 20mph project. The Committee made the following comments in response to the report. i. The Police needed to be fully consulted at an early stage of the project. ii. Could short-term street closures of some streets be considered for community events and play days? iii. As there has been no public consultation to-date can members be assured that the questions are open and neutral? iv. A skewed consultation would not result in public buy in and the project would fail. v. Members did not feel that a PR firm could add value to the project. However, a pro-active approach to the local paper would be welcomed. vi. The Committee suggested that there were omissions to the consultee list. The final consultee list would be agreed by the Project Board. In response to members’ questions the Officers present confirmed the following: i. The consultation process would be phased along area committee lines. However, no individual area committee could opt out. ii. If the consultation demonstrates a lack of public support, the project would not go ahead. iii. If the public had strong views that a particular A or B road be included in the project, the County Council would be consulted. iv. The County Council was contributing officer time and equipment but was not contributing financially. v. The Police had agreed to enforce the limit once adequate signage was in place. vi. The Project Board would have the role of project management. They would not be empowered to make decision. vii. Area Committee Chairs would be members of the Project Management in rotation. The Committee resolved unanimously to endorse the recommendations. The Executive Councillor approved the recommendation. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) Not applicable .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Executive summary

This report seeks to agree the project scope, initiation, and programme. Also for spending to be authorised on initial project costs.

Recommendations

The Executive Councillor is recommended: i. to approve initiation of the project and initial project costs in accordance with the project documentation referenced in this report, with implementation subject to further scrutiny, and approval of project appraisals.

Specific approval is sought for the project: • Programme (see Appendix A provided as separate PDF file) • Governance/Decision making process as set out in section 4 below • Board terms of reference (see Appendix B) • Phasing (see Appendix C) • Engagement/Consultation to commence for the first phase (See Appendix D)

BISHO1B Page 1 14/12/2012 20mph Project Scrutiny Committee Report Final

Approval is also sought for the following estimated intial project spending: • Automatic Traffic Counts (ATCs) for project baseline data collection – < £12,000 • Phase 1 Engagement/Consultation Activities – < £50,000

Background

3.1In July 2011, a motion to Council was agreed that requested the Executive Councillor for Planning and Climate Change (Cllr Tim Ward) to evaluate existing 20mph schemes in Cambridge and where appropriate, consult on expansion of schemes. Support and commitment from Cambridgeshire County Council was secured, and potential project scope and resourcing were investigated, which culminated in Council Budget funding bids for ‘the Cambridge City 20mph Zones Project’. A capital bid for £400,000 to cover works was agreed in February 2012. A further revenue Priority Policy Fund bid for £59,800 to cover staffing was also approved.

3.2Both funding bids stipulate that the project should have a citywide approach. As such the project will consider all appropriate roads within the Cambridge City Boundary where it is appropriate/feasible to introduce a self enforcing 20mph limit. Works will be subject to agreement with the Highway Authority (Cambridgeshire County Council).

3.3Due to the size of the project, it is intended that it be divided over four separate phases, roughly reflecting existing area committee boundaries (for further details see Project Phase Identification and Phase Prioritisation Report at Appendix C). It is intended that each phase be progressed separately and brought to the relevant area committee and adjacent area committees as necessary for recommendation (for further details see the Project Engagement/Consultation/ Marketing Plan at Appendix D)

3.4The project aims to:

• provide conditions that are conducive to an increase in active travel modes such as walking and cycling and encourage a modal shift towards these modes

BISHO1B Page 2 14/12/2012 20mph Project Scrutiny Committee Report Final

• reduce the severity of personal injury accidents (PIAs) that occur on the city’s road network • reduce noise and air pollution levels

3.5The project is reflected in the City’s current policy context including strategic objective PST4.4 in the Planning and Sustainable Transport Portfolio Plan 2012-13. The extension of 20mph zones is also included within the Council’s Annual Statement 2012-13 and contributes to the ‘Vision for the City’. The project will help to achieve objectives set out in the council’s Medium Term Strategy, which includes an action to ‘Improve facilities for pedestrians, cyclists and public transport users, including consideration of extending areas with a 20mph limit’. In addition forthcoming Climate Change Strategy 2012-2016 includes an action to ‘Identify opportunities in the development of the Cambridge Local Plan to minimise traffic generation and promote public transport, cycling and walking’.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20mph Project Programme /8/ENVAppendix A 170 KB Download
PDF
20mph Project Brief Report Final /8/ENVAppendix G 1.3 MB Download
PDF
Cambridge 20mph ProjectReport 1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
SK
Councillor Simon KightleyChair, present
PS
Councillor Paul SaundersVice-Chair, present
RJ
Councillor Richard JohnsonCommittee Member, present
GM
Councillor Gail Marchant-Daisley Labour Spokes for Planning and Climate ChangeCommittee Member, present
GO
Councillor George Owers Labour Spokes for Environmental and Waste ServicesCommittee Member, present
SR
Councillor Sian ReidCommittee Member, present
AR
Councillor Andrea ReinerCommittee Member, present
LH
Councillor Lewis HerbertCommittee Member, expected

On this subject at Cambridge

Search all
  1. Cambridge 20mph ProjectThis decision
  2. Cambridge 20 mph Project - East Phase & Victoria RoadApproved
  3. Cambridge Citywide 20mph Project - Phase 2Noted
  4. Cambridge 20mph Project – Phase 2, East Area ConsultationAgreed
  5. Cambridge 20mph Project – Phase 1 Consultation ReportApproved
  6. Cambridge 20mph Project - Phase 1 Consultation ReportNoted

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies