Strategy and Resources Scrutiny Committee approved this item on Monday 21 January 2013. Below is the council's own wording, with the papers it was decided on.
As part of the new Cambridge Science Park Station access is required over City Council land in several areas, key being a small strip of land at the end of Cowley Road without which the station will not proceed. There will be significant economic, social and environmental benefit from the station. Given these benefits and the uplift in value of the Council’s neighbouring land from the station, it is considered that rights of access for the station should be granted at nominal value. Access for other development will be by negotiation at a later date. Decision of the Executive Councillor: The Executive Councillor resolved to: i. Approve the grant of a right of way to Network Rail across Cowley Road on the terms as outlined in paragraph 3.9 of the officer’s report. Reasons for the Decision : As set out in the officer’s report Any alternative options considered and rejected: As set out in the officer’s report. Scrutiny Considerations: The committee received a report from the Head of Property Services. Councillor Rosenstiel confirmed that this was an important step by the City Council in helping to facilitate the new station. The Scrutiny Committee considered and approved the recommendations unanimously. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted): Not applicable.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
Executive summary
1.1Cambridgeshire County Council is securing funding and approval for the new Cambridge Science Park Station. This is an important part of their transport plans for the region and it meets many requirements relating to viability and cost benefit analyses.
1.2Timescales are tight as the new station delivery has to link with the grant of new franchises. A planning application will probably be submitted in late 2012/early 2013 with opening aimed for late 2015. The station will be a relatively simple one with station building, new platforms, car and cycle parking and a link with the guided busway.
1.3The station will be on Network Rail land at Chesterton Sidings with public access primarily over Cowley Road. Network Rail owns more land than required for the station, much of the land will continue to be used for freight and aggregate operations with the remainder being freed up for possible commercial development.
1.4Access is required over City Council land in several areas, key being a small strip of land at the end of Cowley Road without which the station will not proceed. This land has potentially high value for the City Council as it enables Network Rail to develop its land for the station and for wider commercial opportunities.
1.5The City Council’s land or the necessary access rights could be acquired under compulsory purchase powers but the delay would mean key deadlines would be missed and it would be unlikely that the station would be delivered in the near future.
Report Page No: 1 1.6 There will be significant economic, social and environmental benefit from the station. Given these benefits and the uplift in value of the Council’s neighbouring land from the station, it is considered that rights of access for the station should be granted at nominal value. Access for other development will be by negotiation at a later date.
Recommendations
The Executive Councillor is recommended:
2.1To approve the grant of a right of way to Network Rail across Cowley Road on the terms as outlined in paragraph 3.9.
Background
3.1This report deals with access issues over Cowley Road serving the proposed new railway station and potential future development land owned by Network Rail.
Cambridge Science Park Station.
3.2Cambridgeshire County Council is acting as enabler and funder to develop Cambridge Science Park Station. It will design and develop all or part of the station in conjunction with Network Rail. The cost, exclusive of finance, is estimated at £28m and the County Council will receive payments over the loan period to cover its costs only. The County Council has been trying to provide a station at this location since 2006 but funding and priority changes have prevented this to date.
3.3The initial proposals for the station are for a 450 sq m station building/ticket hall, new platforms, parking for 450 cars and 1000 cycles and a link with the guided busway. Work is proceeding with more detailed design with submission of a planning application in early 2013. The target date for opening the new station is late 2015. An indicative layout is shown at Appendix A.
3.4The station will be on Network Rail’s land and it will be handed over to them upon completion. They in turn will grant a long lease of the station to one of the franchisees who will operate the station on their behalf
City Council and Network Rail land ownership.
3.5Cambridge City Council owns a small strip of land (“retained strip”) at the end of Cowley Road, access over which will be required for public Report Page No: 2 access to the new station. Network Rail has rights of access over Cowley Road to service its operational rail network and freight rail depot at Chesterton Sidings but not for other purposes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.