Environment Scrutiny Committee, Tuesday 22 January 2013 at 5.30pm

Cambridgeshire Green Deal

Approved Scrutiny 7 papers

Environment Scrutiny Committee approved this item on Tuesday 22 January 2013. Below is the council's own wording, with the papers it was decided on.

Item13/15/ENV

Resolved

Green Deal is the Governments new energy efficiency policy, launched in October 2012. It is a fully accredited route for householders and property owners to have their properties and energy use behaviour assessed and for key measures to improve energy efficiency to be identified, financed and installed. The legislation stipulates that key players, involved at all relevant stages will be rigorously assessed and certified by appropriate bodies to provide maximum confidence in the process. The Executive Councillor is asked to approve the establishment of a partnership of the Cambridgeshire Districts to deliver the Green Deal work proposal, subject to detailed approval of a Memorandum of Understanding between the Authorities involved at Public Service Board. Decision of Executive Councillor for Planning and Climate Change The Executive Councillor resolved to: i. To approve the establishment of a partnership of the Cambridgeshire Districts and Cambridgeshire County Council to deliver the Green Deal work proposal, subject to detailed approval of a Memorandum of Understanding between the Authorities involved at Public Service Board; ii. To approve the conduct of a procurement exercise and award of contract(s) to one or more Green Deal commercial providers to be let on a County wide basis and in collaboration with Cambridgeshire Local Authorities. Reason for the As set out in the Officer’s report. Any Alternative Options Considered and Rejected: Not applicable. Scrutiny Considerations: The Committee received a report from the Environmental Quality and Growth Manager regarding the Green Deal. The Officer made the following points in response to members’ questions. i. The potential that up front fees would put off potential customers had been considered. The Partnership would consider a variety of models offered by providers and take up the most attractive based on a number of considerations. The onus would be on the providers to find a solution for up front costs. ii. Training community groups to carry out the initial assessment might offer a solution. iii. The Partnership would take into account the opportunities for the City of Cambridge to include a non-domestic properties. This is something that will be considered, however, the current guidance concentrated on domestic properties. iv. Green Deal will be attractive to landlords, as costs would be recovered from the tenant via energy costs. v. The Green Deal potential locally is not as strong as some parts of the country and there will be a need to promote what the council could offer in order to attract providers and to promote competition. If no provider could be found there would be little ‘ECO’ money for Cambridge. Members were concerned that recent press report suggested that to-date the scheme had achieved very little nationally. It was suggested that marketing the Green Deal would be key. The Environmental Quality and Growth Manager reminded members of a recent successful DECC bid for a pilot project. This would deliver over 200 home assessments over Cambridgeshire and form the evidence base to produce some locally focussed promotional materials. This activity would help to raise public awareness. Concerns were raised that the scheme would be overly complicated. The Officer agreed that it was complicated. Members discussed the staffing implications and were assured that while an initial additional half time post was needed to establish the scheme, it was not envisaged that this need would continue once the scheme was up and running. Councillor Saunders proposed an amendment to the second recommendation to add clarity. Additional wording in bold: To approve the establishment of a partnership of the Cambridgeshire Districts and Cambridgeshire County Council to deliver the Green Deal work proposal, subject to detailed approval of a Memorandum of Understanding between the Authorities involved at Public Service Board; The Committee resolved unanimously to endorse the amended recommendations. The Executive Councillor approved the recommendation. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) Not applicable .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Executive summary

1.1Green Deal is the Governments new energy efficiency policy, launched in October 2012. It is a fully accredited route for householders and property owners to have their properties and energy use behaviour assessed and for key measures to improve energy efficiency to be identified, financed and installed. The legislation stipulates that key players, involved at all relevant stages will be rigorously assessed and certified by appropriate bodies to provide maximum confidence in the process.

1.2Green Deal replaces currently available government grant funding for domestic and community based energy efficiency grant schemes.

1.3Funding will be made available to end users either through a Green Deal finance package or the Energy Company Obligation (ECO) grant depending on financial circumstances, tenure and property type. However, it is also open for other forms of finance to be used if they are the most appropriate. Local Authorities have a statutory duty under the updated Home Energy Conservation Act (HECA) to promote and report on Green Deal activity in their area on an annual basis.

1.4The District and County Councils in Cambridgeshire have established that there is both a significant advantage and a desire to work in partnership to ensure that the Green Deal is a success and that uptake of energy efficiency measures in buildings is maximised thus reducing carbon emissions.

1.5There are also potential consequences of not engaging positively with Green Deal including: Much reduced energy efficiency investment;

Report Page No: 1 Lack of ECO support for vulnerable households; and censure from the Secretary of State for Energy.

1.6A series of consultation workshops, research, consultancy work and interviews with potential Green Deal providers has identified that the likely most effective and financially efficient way of delivering Green Deal across the County is to procure a partnership relationship with a suitable registered Green Deal Provider.

1.7The chosen Green Deal Provider will benefit from the support of a common brand across the county and access to promotional support, networks and information held by each district. In return they will provide a clear and trusted route for residents and property managers in the district to get energy efficiency work done to their properties.

1.8Partnering a Green Deal provider will mean that residents and businesses in the district have good access to quality assessments, finance options and accredited installers. The local authority will benefit from, an active partner to:-

• help engage with local residents; • to maximise lead potential; • provide a secure and accountable referral network.

This will be provided at minimal cost to the authority in the long term following early implementation of the proposal.

1.9In addition the districts will through the procurement process ensure that local benefits are maximised both economically and for reducing carbon emissions.

1.10This report details the legislative context, results of consultation and research, and an outline business plan for the establishment of a countywide Green Deal partnership.

Report Page No: 2 2. Recommendations

2.1The Executive Councillor for Planning and Climate Change is recommended:

1) To approve the establishment of a partnership of the Cambridgeshire Districts to deliver the Green Deal work proposal, subject to detailed approval of a Memorandum of Understanding between the Authorities involved at Public Service Board;

2) To approve the conduct of a procurement exercise and award of contract(s) to one or more Green Deal commercial providers to be let on a County wide basis and in collaboration with Cambridgeshire Local Authorities.

Background

3.1What is Green Deal & ECO (Energy Company Obligation)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Terms of reference Green Deal Steering Group /15/ENVAppendix a 69 KB Download
PDF
Schematic of Green Deal progress /15/ENVAppendix b 415 KB Download
PDF
VERCO GD Executive Summary FINAL 070912 /15/ENVAppendix c 114 KB Download
PDF
Related policies and initiatives /15/ENVAppendix d 58 KB Download
PDF
Green Deal Risk Review Speadsheet /15/ENVAppendix e 64 KB Download
PDF
EqIA-Green Deal /15/ENVAppendix f 130 KB Download
PDF
Cambridgeshire Green DealReport 1.4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
SK
Councillor Simon KightleyChair, apologies, sent representative
PS
Councillor Paul SaundersVice-Chair, present
RJ
Councillor Richard JohnsonCommittee Member, present
GM
Councillor Gail Marchant-Daisley Labour Spokes for Planning and Climate ChangeCommittee Member, present
GO
Councillor George Owers Labour Spokes for Environmental and Waste ServicesCommittee Member, present
SR
Councillor Sian ReidCommittee Member, present
AR
Councillor Andrea ReinerCommittee Member, present
SB
Councillor Simon BrierleyCommittee Member, present
LH
Councillor Lewis HerbertCommittee Member, present
D
DepositPublic, expected

On this subject at Cambridge

Search all
  1. Cambridgeshire Green DealThis decision
  2. 15/1829/REM - Land South of Secondary School Playing Fields and North of Addenbrookes Busway Spur Within Clay Farm Green Corridor, Clay Farm, Cambridge, CambridgeshireDecided
  3. Green Infrastructure Strategy for CambridgeshireRefused

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies