Resolved (by 19 votes to 0) to: Housing Capital i. Approve the capital bids, including resource to re-roof HRA commercial property in Campkin Road and funding to meet the relocation costs of existing residents in housing in Water Lane and Aylesborough Close (subject to approval that the schemes proceed, as shown in Appendix H of the HRA Budget Setting Report.) ii. Approve re-phasing of both the expenditure, and external funding, in respect of the new build affordable housing programme, in line with scheme specific approvals and anticipated cash flows. iii. Approve the virement of £40,000 of resource from the communal area uplift allocation, where work is still being done to produce full stock condition data, to the budget for work to HRA commercial property, to facilitate the conversion of ECCHO House to a two-bedroom dwelling for social housing purposes at a total cost of £95,000, as detailed in the project appraisal at Appendix P, and the Housing Capital Investment Plan at Appendix N of the HRA Budget Setting Report. iv. Approve a reduction of £80,000 in each of the Disabled Facilities Grant and Private Sector Housing Grants and Loans budgets in 2012/13 due to a combination of reduced demand, coupled with a temporary reduction in activity by the new Shared Home Improvement Agency whilst the service was set up. Permission is sought to re-profile this resource to 2017/18, the end of the current funding period, from which point future funding for this area of investment is at risk. v. Approve the revised Housing Capital Investment Plan as shown in Appendix N of the HRA Budget Setting Report. vi. Approve a provisional addition to the Housing Capital Allowance of £25,358,000 in respect of anticipated qualifying expenditure in 2013/14.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1At this stage in the 2013/14 budget process the range of assumptions on which the HRA Business Plan Mid-Year Update was based need to be reviewed, in light of the latest information available, to determine whether any aspects of the strategy need to be revised. This will then provide the basis for the finalisation of the 2012/13 revised and 2013/14 budgets.
1.2The HRA Budget-Setting Report, which is attached, provides an overview of the review of the key assumptions. It sets out the key parameters for the detailed recommendations and final budget proposals.
1.3The recommendations that follow refer to the strategy outlined in the HRA Budget Setting Report.
1.4The HRA BSR confirms that the key parameters agreed as part of the HRA Business Plan of February 2012, and subsequent update of October 2012, can be achieved in setting the 2013/14 HRA Budget.
1.5Housing Management Board, on 8th January 2013, considered and supported the proposed review of rents and service charges and the revenue bids and savings, which form part of the HRA budget, both revised for 2012/13 and for 2013/14 and beyond.
1.6The Executive Councillor for Housing will take final decisions in respect of the items in 1.5 above (recommendations a to m) at a meeting of Strategy & Resources in February 2013.
Report Page No: 1 1.7 This report also recommends, following consideration at this meeting of Community Services, the approval of the Housing Capital Investment Plan, including capital bids and associated funding proposals (recommendations n to s), for final decision at Council on 21st February 2013.
Recommendations
The Executive Councillor, is recommended, following scrutiny and debate at Housing Management Board, to:
Review of Rents and Charges
a) Approve the proposed charges for Housing Revenue Account services and facilities, as shown in Appendix B of the attached HRA Budget Setting Report.
b) Approve that council dwellings rents be increased in line with rent restructuring guidelines to seek to achieve convergence with formula rent by 2015/16, with a maximum in individual increases of inflation (RPI at September 2012 of 2.6%) plus half percent (0.5%) plus £2.00 per week with effect from 1 April 2013, in accordance with the latest government guidelines.
c) Approve inflationary increases of 2.4% in garage rents for 2013/14, in line with the base rate of inflation for the year assumed in the HRA Budget Setting Report, pending future recommendations in respect of garage pricing structures following the findings of the Garage Working Group.
d) Approve that service charges for gas maintenance, door entry systems, lifts and electrical and mechanical maintenance are increased by a maximum of inflation at 2.6% plus 0.5%, if required, to continue to recover full estimated costs as detailed in Appendix B of the attached HRA Budget Setting Report.
e) Approve that caretaking, communal cleaning, estate services, grounds maintenance, window cleaning, temporary housing premises and utilities, sheltered scheme premises, utilities, digital television aerial and catering charges continue to be recovered at full cost, as detailed in Appendix B of the attached HRA Budget Setting Report.
f) Approve revised leasehold administration charges for 2013/14 as detailed in Appendix B of the attached HRA Budget Setting Report.
Report Page No: 2 g) Approve the revised Rent Write Off Policy, as detailed in Appendix A(1) of the HRA Budget Setting Report.
h) Approve the revised Rent Policy, as detailed in Appendix A(2) of the HRA Budget Setting Report.
Revenue – HRA
Revised Budget 2012/13:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.