12/1139/FUL - 2 Tenison Road

Approved Committee 2 papers

East Area Committee approved this item on Tuesday 26 March 2013. Below is the council's own wording, with the papers it was decided on.

Item13/27/EACc

Resolved

Resolved (by 6 votes to 2) to accept the officer recommendation to approve planning permission as per the agenda, subject to the following amendments to conditions. (Reasons for conditions to remain as published in all cases.) Within three months of this decision, a management, travel and community liaison plan for the use of the application premises shall be submitted to the local planning authority for approval. Activities within 2 Tenison Road shall take place thereafter only in accordance with the approved plan. Reason: To ensure that the use hereby permitted does not have an unacceptable impact on the residential amenity of neighbours or on the highway network. (Cambridge Local Plan (2006) policies 3/4 and 8/2). Condition 1: Delete ‘01 January 2017’; insert ’01 January 2015’. Condition 3: Delete ‘In the event that’; insert ‘Before any’. Condition 5: Delete all and replace with this text. The use of the ground floor of this site as an assembly area for prayers hereby permitted shall take place only on Fridays between 1200 and 1500, except during Ramadan, when the use is permitted on any day between 1130 and 1430 and between 1630 and half an hour after sunset. The precise dates for the period of Ramadan shall be submitted to the local planning authority at least one calendar month before Ramadan begins in each year. Condition 6: Delete all and replace with this text. Within three months of this decision, a framework document explaining the educational activities to be undertaken on the ground floor of the application site, which includes details of the activities, the number of people taking part, and the times involved shall be submitted to the local planning authority for approval. Educational activities during the times for prayer hereby permitted shall take place only in accordance with the approved framework document. Educational activities shall not take place on the application site outside the times for prayer hereby permitted. Add new Condition 7: Within three months of this decision, a management, travel and community liaison plan for the use of the application premises shall be submitted to the local planning authority for approval. Activities within 2 Tenison Road shall take place thereafter only in accordance with the approved plan. Reason: To ensure that the use hereby permitted does not have an unacceptable impact on the residential amenity of neighbours or on the highway network. (Cambridge Local Plan (2006) policies 3/4 and 8/2) Reasons for Approval 1. This development has been approved, conditionally, because subject to those requirements it is considered to conform to the Development Plan as a whole, particularly the following policies: Cambridge Local Plan (2006): policies 3/4, 3/7, 4/13, 5/12, 8/2, 8/6 and 8/10. 2. The decision has been made having had regard to all other material planning considerations, none of which was considered to have been of such significance as to justify doing other than grant planning permission. 3. In reaching this decision the local planning authority has acted on guidance provided by the National Planning Policy Framework, specifically paragraphs 186 and 187. The local planning authority has worked proactively with the applicant to bring forward a high quality development that will improve the economic, social and environmental conditions of the area. These reasons for approval can be a summary of the reasons for grant of planning permission only. For further details on the decision please see the officer report online at www.cambridge.gov.uk/planningpublicaccess or visit our Customer Service Centre, Mandela House, 4 Regent Street, Cambridge, CB2 1BY between 8am to 6pm Monday to Friday.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to East Area Committee

EAST AREA COMMITTEE Date: 26th March 2013

Application 12/1139/FUL Agenda Number Item Date Received 4th September 2012 Officer [name removed] Date 30th October 2012 Ward Petersfield Site 2 Tenison Road Cambridge Cambridgeshire CB1 2DW Proposal Retrospective application for temporary continuation of use for additional assembly area for worship on Fridays (12.30pm to 2.30pm) and during Ramadan (midday to 2pm and 5pm to sunset). Applicant [name removed] 1 Mawson Road Cambridge CB1 2DZ

1.0SITE DESCRIPTION/AREA CONTEXT

1.1The application site lies between Tenison Road and Mawson Road, close to the point at which these two streets meet Mill Road. It adjoins at its western end, and is connected via internal doors to, the Islamic Centre premises at 1 Mawson Road. Tenison Road and Mawson Road are both predominantly residential, with a mixture of family houses and buildings which are in use as HMO’s, or subdivided into flats. There are commercial premises on the opposite side of Tenison Road. The building on the application site is the northernmost of a terrace of houses on the west side of Tenison Road.

1.2A narrow alleyway runs along the whole length of the northern boundary of the application site, and continues along the northern boundary of 1 Mawson Road, forming a link between Tenison Road and Mawson Road. This alley provides rear access to some of the retail premises along Mill Road and to flats which occupy the upper floors of most of these premises. Several of the flats have first floor rear terraces. There are emergency exits from both the application site and 1 Mawson Road into the alleyway, which is obstructed in several places by large waste bins. 1.3 The Islamic Centre at 1 Mawson Road is used for a number of religious purposes, including Friday prayers. The ground floor of 2 Tenison Road is also used for prayers, but according to neighbour representations is also used extensively at other times for young people’s activities.

2.0THE PROPOSAL

2.1Following the expiry of the previous permission for the use of the ground floor of the building on this site as an assembly area for prayers (08/0568/FUL), this application retrospectively seeks permission for continued use for Friday prayers every week, and daily during Ramadan. These uses are sought for a further three-year period, pending the opening of the new Mill Road mosque.

3.0SITE HISTORY

3.1At 1 Mawson Road:

Reference Description Outcome 81/0483 Use of premises as Islamic Centre Approved with conditions 81/0703 Use of premises as non-residential Refused club 98/1013 Removal of flat roof and erection of Approved pitched roof over rear assembly with room conditions 00/1046 Extension to rear to form enlarged Approved assembly room with conditions

3.2At 2 Tenison Road:

Reference Description Outcome 98/0472 Conservatory Approved with conditions 02/1261 Change of use of ground floor to Approved assembly room for prayer with meetings conditions 08/0568/FUL Retrospective application for Approved temporary change of use to with additional assembly area for conditions worship.

3.3Subsequent to the consent for temporary use of the ground floor of this site for prayers (02/1261), a single-storey extension to the building with a glazed roof and high-level windows along the boundary wall with 4 Tenison Road was erected without planning permission or Building Regulations approval. This extension has now been demolished.

4.0PUBLICITY

4.1Advertisement: Yes Adjoining Owners: Yes Site Notice Displayed: Yes DC Forum (meeting of 16 January 2012): Yes

4.2The minutes of the Development Control Forum are attached to the report as Appendix 1.

5.0POLICY

5.1Central Government Advice

National Planning Policy Framework (March 2012)

The National Planning Policy Framework (NPPF) sets out the Government’s economic, environmental and social planning policies for England. These policies articulate the Government’s vision of sustainable development, which should be interpreted and applied locally to meet local aspirations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
12/1139/FUL: 2 Tenison RoadReport 78 KB DownloadRead as text
PDF
12/1139/FUL: Drawings /27/EACcReport 194 KB Download

At this meeting

Whole meeting

Who was there

11 of 15 attended
KB
Councillor Kevin BlencoweChair, present
GO
Councillor George OwersVice-Chair, present
JB
Councillor Jeremy BensteadCommittee Member, present
SB
Councillor Sarah BrownCommittee Member, present
CH
Councillor Caroline HartCommittee Member, apologies
LH
Councillor Lewis HerbertCommittee Member, apologies
RJ
Councillor Richard JohnsonCommittee Member, present
GM
Councillor Gail Marchant-DaisleyCommittee Member, present
ZM
Councillor Zoe MoghadasCommittee Member, present
PS
Councillor Paul SaundersCommittee Member, present
CS
Councillor Catherine SmartCommittee Member, present
KB
Councillor Kilian Bourke Cambridgeshire County Councillor for Romsey WardCommittee Member, present

All 15 on the meeting page

On this subject at Cambridge

Search all
  1. 12/1139/FUL - 2 Tenison RoadThis decision
  2. 14-1811-FUL:35 Tenison RoadDecided
  3. 14/0974/FUL - 27 Tenison AvenueRefused
  4. 12/1040/FUL - St Colettes Preparatory School, Tenison RoadRefused
  5. 10/0833/FUL Station Area Redevelopment - Junction of Station Road and Tenison RoadApproved

More from Cambridge East Area Committee

All decisions
MeetingDecisionOutcome
24 Jun 2021 Open ForumAgreed it was vital that residents understood the documentation and would be happy to arrange assistance when looking... Agreed Open
3 Dec 2020 Policing and Safer NeighbourhoodsRESOLVED unanimously to write to the Acting Police and Crime Commissioner highlighting the Committee’s concern regard... Decided Open
17 Sep 2020 Election of Chair and Vice Chair - EACResolved unanimously that Councillor Barnett be Chair for the ensuing year. Councillor Barnett assumed the chair from... Decided Open
17 Sep 2020 Policing and Safer NeighbourhoodsResolved unanimously to approve the following as local areas of concern: i. Anti-social driving ii. Cycle theft iii. ... Approved Open
17 Sep 2020 Outside Body Appointment: Cambridge Airport Consultative CommitteeResolved that Councillor Davey be the representative for the Cambridge Airport Consultative Committee for the ensuing... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies