Strategy and Resources Scrutiny Committee refused this item on Tuesday 9 April 2013. Below is the council's own wording, with the papers it was decided on.
To consider the disposal of land at Clay Farm. Decision of the Executive Councillor for Customer Services and Resources: The Executive Councillor resolved to: i. Confirm the award of a contract to a developer partner selected through a procurement process to develop the City Council’s land at Clay Farm Reasons for the Decision : As set out in the officer’s report Any alternative options considered and rejected: As set out in the officer’s report Scrutiny Considerations: The committee resolved to exclude the press and public by virtue of paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972 during the consideration of appendix 2. The committee made no comments on the public element of the report. The committee debated the appendix in closed session. The Scrutiny Committee considered the recommendation and endorsed it by 4 votes to 0. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted): Not applicable.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
Executive summary
At the Strategy and Resources Committee on the 4 July 2011 the Executive Councillor for Customer Services and Resources approved that the Council proceed with a project to dispose of the Council’s land at Clay Farm.
Delegated authority was given to the Director of Resources and the Head of Legal Services to agree a procurement process to select a preferred partner to dispose of the land following consultation with the Leader; relevant Executive Councillors; and Opposition Spokespersons and that a report be brought back to the Committee to authorise that a contract be entered into with the preferred partner.
The procurement process has now concluded and this report requests authority to enter into the contract.
Appendix 2, which is confidential, summarises the results of the evaluation of the successful tender.
Recommendations
The Executive Councillor is recommended:
To confirm the award of a contract to a developer partner selected through a procurement process to develop the City Council’s land at Clay Farm.
3. Background Report Page No: 1 Cambridge City Council owns the freehold of approximately 6.75 acres of land at the centre of the Clay Farm development area on the Southern Fringe of the city. Appendix 1 shows the location of the land (shaded green) adjacent to the new Community Centre and Square (shaded blue).
This land will provide up to 209 dwellings and up to 540 square metres of retail space.
Members have clearly expressed their expectations that ownership of the land presents the opportunity to deliver;
- a development of quality design - that sets exemplar sustainability standards - with 50% of the housing as Affordable Housing - that generates a capital receipt for the Council - with risk to the Council kept to a minimum
At the Strategy and Resources Committee on the 4 July 2011 the Executive Councillor for Customer Services and Resources approved that the Council proceed with a project to dispose of the site to achieve these objectives. Delegated authority was given to the Director of Resources and the Head of Legal Services to agree a procurement process to select a preferred partner to dispose of the land following consultation with the Leader; relevant Executive Councillors; and Opposition Spokespersons and that a report be brought back to the Committee to authorise that a contract be entered into with the preferred partner.
Also at the Customer and Community Services meeting in June 2012 it was approved in principle that the Council should retain the Affordable Housing on the Council’s site. This principle was subsequently agreed at Strategy and Resources Committee in July 2012 and at the Strategy and Resources Committee in January 2013 it was approved that the Council should retain the ownership of up to 450 square metres of commercial units on the site.
As further context, in 2006 the Council approved that a Collaboration Agreement (CA) be negotiated with Countryside Properties Limited (CPL) the developer of the remainder of the Clay Farm site to facilitate the development of the Council’s land. The CA has now been signed.
The main provisions of the CA are;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.