13/0409/FUL - EF Language School, 221 Hills Road

Approved Committee 7 papers

South Area Committee approved this item on Thursday 9 May 2013. Below is the council's own wording, with the papers it was decided on.

Item13/28/SAC

Resolved

Resolved (unanimously) to accept the officer recommendation to GRANT DELEGATED AUTHORITY to officers to approve the application subject to: · the conditions listed below · the Nature Conservation Officer and the Planning Case Officer being satisfied that the necessary additional bat emergence surveys have taken place and that any proposed mitigating measures are acceptable; and · officers drafting and attaching to the permission any additional conditions which, in the officers’ opinion, are necessary to address the protection of bats including to secure any required mitigating measures. (ii) If Officers are not satisfied that the additional bat emergence surveys have taken place, or they are not satisfied that the proposed mitigating measures are acceptable, the application is to be brought back to the next meeting of South Area Committee. Conditions and reasons for approval: 1. The development hereby permitted shall be begun before the expiration of three years from the date of this permission. Reason: In accordance with the requirements of section 51 of the Planning and Compulsory Purchase Act 2004. 2. No development shall take place until samples of the materials to be used in the construction of the external surfaces of the development hereby permitted have been submitted to and approved in writing by the local planning authority. Development shall be carried out in accordance with the approved details. Reason: To ensure that the appearance of the external surfaces is appropriate. (Cambridge Local Plan 2006 policies 3/4, 3/12 and 3/14) 3. Before starting any brick or stone work, a sample panel of the facing materials to be used shall be erected on site to establish the detail of bonding, coursing and colour and type of jointing and shall be agreed in writing with the local planning authority. The quality of finish and materials incorporated in any approved sample panel(s), which shall not be demolished prior to completion of development, shall be maintained throughout the development. Reason: In the interests of visual amenity and to ensure that the quality and colour of the detailing of the brickwork/stonework and jointing is acceptable and maintained throughout the development. (Cambridge Local Plan 2006 policies 3/4 and 3/12) 4. No development, other than demolition, shall commence until full details of the following architectural features have been submitted to, and approved in writing by the local planning authority. This may require drawings at 1:20. Development shall proceed only in accordance with the agreed details. main entrance roof ridges and eaves recessed masonry panels door and window joinery junctions with the original building metal shutters fire escape stairs Reason: To ensure the building responds appropriately to its context. (Cambridge Local Plan 2006 policies 3/4 and 3/12) 5. Except with the prior written agreement of the local planning authority no construction work or demolition shall be carried out or plant operated other than between the following hours: 0800 hours to 1800 hours Monday to Friday, 0800 hours to 1300 hours on Saturday and at no time on Sundays, Bank or Public Holidays. Reason: To protect the amenity of the adjoining properties. (Cambridge Local Plan 2006 policy 4/13) 6. Prior to the commencement of the development hereby approved (including any pre-construction, demolition, enabling works or piling), the applicant shall submit a report in writing, regarding the demolition / construction noise and vibration impact associated with this development, for approval by the local authority. The report shall be in accordance with the provisions of BS 5228:2009 Code of Practice for noise and vibration control on construction and open sites and include full details of any piling and mitigation measures to be taken to protect local residents from noise and or vibration. Development shall be carried out in accordance with the approved details. Due to the proximity of this site to existing residential premises and other noise sensitive premises, impact pile driving is not recommended. Reason: To protect the amenity of neighbouring occupiers. (Cambridge Local Plan 2006 policies 3/4 and 4/13) 7. Except with the prior written agreement of the local planning authority, there should be no collection or deliveries to the site during the demolition and construction stages outside the hours of 0700 hrs and 1900 hrs on Monday - Saturday and there should be no collections or deliveries on Sundays or Bank and public holidays. Reason: Due to the proximity of residential properties to this premises and that extensive refurbishment will be required, the above conditions are recommended to protect the amenity of these residential properties throughout the redevelopment in accordance with policies 4/13 and 6/10 of the Cambridge Local Plan (2006) 8. No development shall commence until a programme of measures to minimise the spread of airborne dust from the site during the demolition / construction period has been submitted to and approved in writing by the Local Planning Authority. The development shall be implemented in accordance with the approved scheme. Reason: To protect the amenity of neighbouring occupiers and highway users (Cambridge Local Plan 2006 policy 3/4) 9. No development shall take place until a site visit has taken place involving the retained arboriculturalist , the developer and the City Council Tree Officer to agree tree works and the location and specification of tree protection barriers and temporary ground protection. Development shall proceed thereafter only in accordance with the agreed details. Reason: To protect trees of amenity value. (Cambridge Local Plan 2006 policy 4/4) 10. The agreed means of tree protection shall be retained on site until all equipment, and surplus materials have been removed from the site. Nothing shall be stored or placed in any area protected in accordance with this condition, and the ground levels within those areas shall not be altered nor shall any excavation be made without the prior written approval of the local planning authority. Reason: To protect trees of amenity value. (Cambridge Local Plan 2006 policy 4/4) 11. No development other than demolition shall take place until full details of both hard and soft landscape works have been submitted to and approved in writing by the local planning authority and these works shall be carried out as approved. These details shall include proposed finished levels, demonstration that no excavation will be carried out within Root Protection Areas; means of enclosure; car parking layouts, other vehicle and pedestrian access and circulation areas; hard surfacing materials; minor artefacts and structures including cycle hoops, picnic tables and railings; services above and below ground including drainage, power, and communications cables. Soft Landscape works shall include planting plans; written specifications (including cultivation and other operations associated with plant and grass establishment); schedules of plants, noting species, plant sizes and proposed numbers/densities where appropriate and an implementation programme. Reason: In the interests of visual amenity and to ensure that suitable hard and soft landscape is provided as part of the development. (Cambridge Local Plan 2006 policies 3/4, 3/11 and 3/12) 12. No development shall take place until full details of surface water attenuation have been submitted to, and approved in writing by, the local planning authority. Reason: To avoid the risk of flooding. (Cambridge Local Plan policy 4/16) 13. Prior to the commencement of development/construction, a noise insulation scheme detailing the acoustic noise insulation performance specification of the external building envelope and including plant (having regard to the building fabric, glazing and ventilation) shall be submitted to and approved in writing by the local planning authority. The scheme shall achieve the internal noise levels recommended in British Standard 8233:1999 "Sound Insulation and noise reduction for buildings-Code of Practice". The approved scheme shall be fully implemented and a completion report submitted prior to the occupation of the noise sensitive development. The approved scheme shall remain unaltered in accordance with the approved details. Reason: To protect the amenity of future occupiers from noise. (Cambridge Local Plan 2006 policies 3/4 and 4/16) 14. No development other than demolition shall take place until full details of the provision for the storage of waste and recycling have been submitted to, and approved in writing by, the local planning authority. Reason: To ensure satisfactory waste storage (Cambridge Local Plan policy 3/12) 15. Before the development/use hereby permitted is commenced, details of equipment for the purpose of extraction and/or filtration of fumes and or odours shall be submitted to and approved in writing by the local planning authority. The approved extraction/filtration scheme shall be installed before the use hereby permitted is commenced. Reason: To protect the amenity of nearby properties. (Cambridge Local Plan 2006 policy 4/13) 16. No unbound material shall be used on the surface of the vehicle access within 6m of the boundary of the public highway. Reason: To prevent the spread of debris onto the highway. (Cambridge Local Plan 2006 policy 8/2) 17. No development shall take place within the site until the applicant, or their agent or successors in title, has secured the implementation of a programme of archaeological work in accordance with a written scheme of investigation which has been submitted by the applicant and approved in writing by the local planning authority. Reason: To ensure that an appropriate archaeological investigation of the site has been implemented before development commences. (Cambridge Local Plan 2006 policy 4/9) 18. No development shall commence until details of facilities for the covered, secured parking of bicycles for use in connection with the development hereby permitted shall be submitted to and approved by the local planning authority in writing. The approved facilities shall be provided in accordance with the approved details before use of the development commences. Reason: To ensure appropriate provision for the secure storage of bicycles. (Cambridge Local Plan 2006 policy 8/6) INFORMATIVE: To satisfy the condition requiring the submission of a program of measures to control airborne dust above, the applicant should have regard to: Cambridge City Council's Supplementary Planning Document 'Sustainable Design and Construction 2007': http://www.cambridge.gov.uk/public/docs/sustainable-designand construction-spd.pdf Control of dust and emissions from construction and demolition - Best Practice Guidance produced by the London Councils: http://www.london.gov.uk/thelondonplan/guides/bpg/bpg_04.jsp INFORMATIVE: To satisfy the standard condition on noise insulation, the noise level from all plant and equipment, vents etc (collectively) associated with this application should not raise the existing background level (L90) by more than 3 dB(A) (i.e. the rating level of the plant needs to match the existing background level). This requirement applies both during the day (0700 to 2300 hrs over any one hour period) and night time (2300 to 0700 hrs over any one 5 minute period), at the boundary of the premises subject to this application and having regard to noise sensitive premises. Tonal/impulsive noise frequencies should be eliminated or at least considered in any assessment and should carry an additional 5 dB(A) correction. This is to guard against any creeping background noise in the area and prevent unreasonable noise disturbance to other premises. It is recommended that the agent/applicant submits a noise prediction survey/report in accordance with the principles of BS4142: 1997 "Method for rating industrial noise affecting mixed residential and industrial areas" or similar. Noise levels shall be predicted at the boundary having regard to neighbouring premises. Such a survey / report should include: a large scale plan of the site in relation to neighbouring premises; noise sources and measurement / prediction points marked on plan; a list of noise sources; details of proposed noise sources / type of plant such as: number, location, sound power levels, noise frequency spectrums, noise directionality of plant, noise levels from duct intake or discharge points; details of noise mitigation measures (attenuation details of any intended enclosures, silencers or barriers); description of full noise calculation procedures; noise levels at a representative sample of noise sensitive locations and hours of operation. Any report shall include raw measurement data so that conclusions may be thoroughly evaluated and calculations checked. INFORMATIVE: The applicant is advised that the accessibility of the building for people with disabilities would be significantly improved if the following enhancements were incorporated: entrance door wider and power assisted and preferably automatic avoidance of dog-leg turn in entrance lobby foyer double doors asymmetric, power assisted and preferably automatic dropped height section and hearing loop in reception hearing loops in classrooms fire alarm provision for those with hearing impairments. good colour contrast within the building to aid visually impaired users to wayfind . Reasons for Approval 1. This development has been approved, conditionally, because subject to those requirements it is considered to conform to the Development Plan as a whole, particularly the following policies: Cambridge Local Plan (2006): policies 3/1, 3/4, 3/7, 3/12, 4/4, 4/13, 4/16, 7/11, 8/2 2. The decision has been made having had regard to all other material planning considerations, none of which was considered to have been of such significance as to justify doing other than grant planning permission. 3. In reaching this decision the local planning authority has acted on guidance provided by the National Planning Policy Framework, specifically paragraphs 186 and 187. The local planning authority has worked proactively with the applicant to bring forward a high quality development that will improve the economic, social and environmental conditions of the area. These reasons for approval can be a summary of the reasons for grant of planning permission only. For further details on the decision please see the officer report online at www.cambridge.gov.uk/planningpublicaccess or visit our Customer Service Centre, Mandela House, 4 Regent Street, Cambridge, CB2 1BY between Mon 8am - 5:15pm, Tues, Thurs & Fri 9am - 5:15pm, Weds 9am - 6pm
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to South Area Committee

SOUTH AREA COMMITTEE 9th May 2013

Application 13/0409/FUL Agenda Number Item Date Received 22nd March 2013 Officer [name removed] Date 17th May 2013 Ward Queen Ediths Site EF Language School 221 Hills Road Cambridge Cambridgeshire CB2 8RW Proposal Partial demolition of an existing language school and replacement with a new side extension with increased social space. The amount of teaching space and Use Class (D1 - Non-residential Education and Training Centres) remains the same. Applicant [name removed] E F Language Schools Ltd 221 Hills Road Cambridge CB2 8RN

SUMMARY The development accords with the Development Plan for the following reasons:

The contemporary design of the extension responds well to the original 19th century building, and would enhance the character of this part of Hills Road

The extension would not result in significant harm to the residential amenity of neighbours

The proposal involves the improvement of language school facilities, but no increase in teaching space.

RECOMMENDATION APPROVAL

1.0SITE DESCRIPTION/AREA CONTEXT

1.1The application site is located on the north-east corner of Hills Road and Cavendish Avenue, on the eastern side of Hills Road. The site presently accommodates a two and half storey property, with modern two storey extensions, which accommodate an established Language School.

1.2The original 2½ storey building mainly occupies the north east corner of the site with the modern two storey form extending southwards, along the eastern boundary. The original property is constructed from gault brick and is believed to have been designed by Richard Reynolds Rowe and is a fine example of a Victorian Villa, with an articulated roof consisting of gable ends and traditional dormer windows.

1.3The site is largely screened from Hills Road and Cavendish Avenue by mature trees that form a protected tree belt around the west and southern boundaries of the site.

1.4To the north of the site is St John’s Church, a two storey building with steeply pitched roof, finished in red brick, that sits back on its site to provide landscaping as a buffer between the building and Hills Road. The Church sits behind the established building line that is created by residential properties to the north and south.

1.5To the east and south of the site and to a wider degree, this eastern side of Hills Road, it is residential in appearance. Properties take the form of a domestic scale, mainly 2 to 2 ½ storeys in height with amenity space surrounding the building.

1.6On the western site of Hills Road, nearly opposite the application site is Homerton College. This is a large landscaped site with collegiate type buildings accommodated on the site. Further to the north is the Hills Road/Cherry Hinton junction, which is an urban environment, which is undergoing re-development with large residential and leisure buildings being constructed. To the south of this junction the area quickly descents into a suburban appearance.

1.7Hills Road is a busy arterial road, which carries vehicular traffic to Addenbrookes Hospital and south towards Haverhill and Linton. The site is not located in a Conservation Area, nor are there any listed buildings or Buildings of Local Interest in close proximity to the site. The site is within Character Area 3 of the Hills Road Suburbs and Approaches Study (2012). 2.0 THE PROPOSAL

2.1The application proposes the total demolition of the 1980’s extension to the south and east of the original Victorian house, and its replacement by a new two-storey building wrapping round the south and east sides of the building and covering the footprint of the demolished building and the courtyard between it and the original house.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
13/0409/FUL: EF Language School, 221 Hills RoadReport 129 KB DownloadRead as text
PDF
Drg 1: floorplan /28/SACReport 78 KB Download
PDF
Drg 2: west(front) elevation /28/SACReport 37 KB Download
PDF
Drg 3: East (rear) elevation /28/SACReport 38 KB Download
PDF
Drg 4: photo montage /28/SACReport 48 KB Download
PDF
Drg 5 /28/SACReport 34 KB Download
PDF
Location PLan /28/SACPlan 143 KB Download

At this meeting

Whole meeting

Who was there

11 of 12 attended
RD
Councillor Robert DrydenChair, present
SM
Councillor Shapour MeftahVice-Chair, present
MA
Councillor Mark AshtonCommittee Member, present
AB
Councillor Andy Blackhurst Liberal Democrat SpokesCommittee Member, present
SB
Councillor Sue BirtlesCommittee Member, present
RM
Councillor Russ McPhersonCommittee Member, present
GP
Councillor George PippasCommittee Member, present
SS
Councillor Sheila StuartCommittee Member, present
JS
Councillor Jean SwansonCommittee Member, present
BA
Councillor Barbara AshwoodCommittee Member, present
SC
Councillor Sandra CrawfordCommittee Member, apologies
AT
Councillor Amanda TaylorCommittee Member, present

More from Cambridge South Area Committee

All decisions
MeetingDecisionOutcome
30 Nov 2020 Food Hubs - Coronavirus Community ResponseAgreed that although it is difficult to mention everyone involved, many individuals and organisations deserved thanks. Agreed Open
7 Sep 2020 Election of Chair and Vice Chair - SACResolved (by 4 votes to 4 and flip of a coin by Committee Manager) that Councillor McPherson be Chair for the ensuing... Decided Open
22 Jul 2019 Election of Chair and Vice Chair - SACResolved (by 6 votes to 5) that Councillor McGerty be Chair for the ensuing year. Councillor McGerty proposed, and Co... Decided Open
10 Sep 2018 Updates on Cambridge Biomedical Campus Transport Study and Related ProjectsAgreed it was better to get things (like lighting) designed in than trying to retrofit. ii. Agreed that more stops ne... Agreed Open
4 Jun 2018 Election of Chair and Vice Chair - SACResolved (by 4 votes to 4 and toss of a coin) that Councillor McPherson be Chair for the ensuing year. County Council... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies