Decision Report on the progress of the Council’s Affordable Housing Development Programme providing an up-date with a particular emphasis on the re-housing of existing residents. Decision of Executive Councillor for Housing Noted progress with the delivery of the Council’s Affordable Housing Development Programme. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Strategic Housing. In response to Members’ questions the Head of Strategic Housing confirmed the following: (i) Water Lane was one of the last schemes approved and was therefore marginally behind the others. (ii) Tenants moved from an under-occupied property would be offered the option of a ‘like for like’ property. (iii) The Latimer Close scheme had received planning permission and a final design was being worked on. The scheme may however be delayed slightly by highway related issues. (iv) Negotiations were going well regarding the Stanesfield Road Scout Hut. (v) Water Lane and Aylesborough Close had been delayed for 3 months and this did hold up some rehousing work but it was not yet at a critical point. (vi) Officers would be happy to answer any further questions on specific schemes outside of the meeting. The Committee resolved unanimously to endorse the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor .
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Housing Management Board has requested a report on the progress of the Council’s Affordable Housing Development Programme. This report provides an up-date with a particular emphasis on the re-housing of existing residents.
Recommendations
The Executive Councillor is recommended:
To note progress with the delivery of the Council’s Affordable Housing Development Programme.
Background
“Maximise the delivery of new sustainable housing in a range of sizes, types and tenures - at least maintaining current standards and driving energy efficient homes for residents” is a Strategic Objective in the Housing Portfolio Plan.
Over the last twenty years most new Affordable Housing has been delivered by Registered Providers (RPs) working with house- builders and developers through the planning system. The Homes and Communities Agency (HCA) introduced a significantly different way of allocating grant to RPs in 2011. RPs were invited to bid for grant in a single bid round to allocate all available grant to the end of March 2015. In the new context of ‘self financing’, local authorities were able to bid for grant too and the Council took the opportunity to establish its own new Council House building programme.
Three Year Rolling Programme
A new approach to the review of the use of housing land in the Council’s ownership was introduced in July 2008 following Committee scrutiny. It was agreed by the Executive Councillor that a three year rolling programme of sites be brought forward each year for consideration for development, redevelopment or disposal. The annual review keeps members appraised of progress with sites and offers the opportunity to introduce new sites for investigation. Sit.es have been selected from the Council’s Three Year Rolling Programme to include in the new Council House building programme. A cross-party Member Group has been established to steer and monitor the Council’s Affordable Housing Development Programme
New Council House Programme
Eight new Council homes have now been completed since 2010 in Harris Road, Cockerall Road, Teversham Drift and Church End. The scheme to redevelop Seymour Court is due to complete in October 2013. This will provide 18 two bedroom and 2 one bedroom flats for older people. Two of the two bedroom flats will be fully wheelchair accessible.
Based on the three year rolling programme grant has been secured from the HCA through the bid round mentioned above to provide a further 126 (146 including Seymour Court) new Council homes by the end March 2015. To facilitate this officers have completed a procurement process to set up an Affordable Housing Development partnership (AHDp) with a house-builder/developer and four Registered Providers. Keepmoat has been selected as our house-bulider partner.
Appendix 1 is a Workbook of Scheme Audit Checklists summarising progress on the individual schemes in the Council’s Affordable Housing Development Programme. Progress with Re-housing Residents
The following table summarises the current position with the re- housing of tenants;
Scheme Number Number Remaining Tenants moved or number to re- accepted house offers Latimer Close 16 16 0 Barnwell Road 23 23 0 Campkin Road 40 36 4 Colville Road 17 16 1 Aylesborough 20 8 12 Close Water Lane 23 6 17 Total 139 105 34
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.