Housing Management Board, Tuesday 1 October 2013 at 5.30pm

Outcome of the Repairs Improvement Plan

Approved Committee 1 paper

Housing Management Board approved this item on Tuesday 1 October 2013. Below is the council's own wording, with the papers it was decided on.

Item13/34/HMB

Resolved

Decision The decision to implement a 2 year improvement plan for the responsive repairs and voids service was approved at the meeting of Housing Management Board on 28 September 2010. The Executive Councillor subsequently agreed to extend the period by a further 1 year to enable further investigation into the procurement of alternative I.T. solutions and to implement the most appropriate option. The 3 year period has now concluded, and the report presented the outcomes of the improvement plan, which would enable the Executive Councillor to consider retaining the service provision in-house. Decision of Executive Councillor for Housing i. Noted the progress and improvements made in service delivery over the past 3 years. ii. Agreed to retain the service delivery in house subject to the following requirements: - That a report be presented to Housing Management Board in June 2014 detailing the performance of the service following the introduction of mobile working. - That an annual review takes place which establishes whether performance is being maintained and the decision to retain the service in house is still valid. iii. Approved that the contract review date for all products supplied by Orchard Information Systems and their operational partners, is timetabled to be 5 years from the point of implementation of the Direct Works and SVS applications, to ensure that any anticipated cost savings are achieved and that the housing service is able to maintain rational service delivery across all aspects of the service. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Property Services Officer. The Committee made the following comments in response to the report: (i) Welcomed the progress and improvements highlighted in the report and congratulated the entire workforce and Officers involved. (ii) Made reference to the Responsive Repair Service Delivery table that figures should be produced to show what the percentage figures are a total of. (iii) Questioned why the “5 point promise” needed to be reviewed again. (iv) Expressed disappointment that the data regarding the Completed Repair’s did not separate information to show communal areas. (v) Noted that that cross departmental working would continue to be embedded within the repairs and maintenance service. (vi) Disappointed to note that an annual review would take place to establish whether performance was being maintained and the decision to retain the service in house was still valid. The Committee : Terry Sweeny (Tenant Representative) proposed the following amendment to recommendation 2.1 of the Officer’s report (replacement underlined and original struck through ): · To note welcome the progress and improvements made in service delivery over the past 3 years. Resolved unanimously to agree this amendment. Terry Sweeny (Tenant Representative) then requested the inclusion of an additional recommendation to 2.2 of the Officer’s report. · C. If the annual report to the Housing Management Board continue to show that services are improved consideration be given to retention of the service ‘in house’ on a more permanent and business like basis. Resolved unanimously to agree to this additional recommendation. The Committee resolved unanimously to endorse the amendment and additional recommendation. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Management Board

Recommendations

The Executive Councillor is recommended:

2.1To note the progress and improvements made in service delivery over the past 3 years. 2.2 To agree to retain the service delivery in house subject to the following requirements: A. That a report is presented to Housing Management Board in June 2014 detailing the performance of the service following the introduction of mobile working. B. That an annual review takes place which establishes whether performance is being maintained and the decision to retain the service in house is still valid. 2.3 To approve that the contract review date for all products supplied by Orchard Information Systems and their operational partners, is timetabled to be 5 years from the point of implementation of the Direct Works and SVS applications, to ensure that any anticipated cost

Report Page No: 1 savings are achieved and that the housing service is able to maintain rational service delivery across all aspects of the service.

3. Improvement Plan Outcomes

3.1The improvement plan contained six key service objectives. The three main objectives were:  Improve service delivery  Improve value for money and the overall cost of the service.  Increase resident involvement

The main objectives were supported by three further objectives that contribute to the overall improvement of the service. The contributory objectives were:  Improve communication within the Estates and Facilities team  Improve technology and innovation  Improve inter-departmental working practises

Appendix A details the changes made to the service that have resulted in the improvements achieved. Appendix B sets out the programme for the remaining tasks required to implement new IT and enable a “go-live” date of 6 January 2014.

3.2Improve Service Delivery

3.2.1 The key performance indicators that monitor this aspect of the improvement plan show improvements have been achieved in all areas of the responsive repairs service since 2010/11. This is summarised in the table below. Please note that the information for 2013/14 relates to the first third of the current financial year (April – July 2013.)

Responsive Repairs Service Delivery 2010/11 2013/14 Emergency jobs completed in target 96.4% 99.0% Urgent jobs completed in target 82.4% 97.4% Routine jobs completed within target 86.5% 97.9% All jobs completed within target 86.5% 98.04% Appointments made* 49.0% 54.6% Appointments kept (information collected from 94% 99.4% resident satisfaction survey cards) Number of late afternoon appointments made 47 99 Resident satisfaction with the completed 9.3 9.9 repair (score out of 10) Percentage of jobs where the target date is 10.5% 4.9% extended

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Outcome of the Repairs Improvement PlanReport 462 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 14 attended
AB
Councillor Andy BlackhurstVice-Chair, present
GB
Councillor Gerri BirdCommittee Member, present
KB
Councillor Kevin BlencoweCommittee Member, present
SB
Councillor Simon BrierleyCommittee Member, present
RJ
Councillor Richard JohnsonCommittee Member, present
GP
Councillor George PippasCommittee Member, present
KP
Councillor Kevin Price Labour Spokes for HousingCommittee Member, present
CR
Councillor Colin RosenstielCommittee Member, present
DM
Diana Minns Tenant RepresentativeChair, present
DB
Diane Best Leaseholder RepresentativeCo-Optee, present
KH
Kay Harris Tenant RepresentativeCo-Optee, present
JM
John Marais Tenant RepresentativeCo-Optee, present

All 14 on the meeting page

More from Cambridge Housing Management Board

All decisions
MeetingDecisionOutcome
4 Mar 2014 Housing Portfolio Plan 2014/15Decision To note the draft , which had set out the strategic objectives for the portfolio for the year ahead, describ... Noted Open
4 Mar 2014 Progress Report From Residents' Housing Regulation PanelDecision of Executive Councillor for Housing i. Noted and welcomed the positive outcomes achieved by residents’ Housi... Noted Open
16 Jan 2014 Housing Revenue Account budget for 2014/15To consider the Revenue Account Budget 2014/115 for the Housing Portfolio. Decision of the Executive Council for Hous... Approved Open
7 Jan 2014 Shared Ownership ReviewDecision of Executive Councillor for Housing To note the report of the Housing Strategy Manager. Reason for the Decis... Noted Open
7 Jan 2014 Tenancy Policy 2014 -2016Decision of Executive Councillor for Housing i. Approved the Tenancy Policy. ii. Approved the use of fixed term tenan... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies