E-Mail, File and Storage System and Server Upgrades

Approved Scrutiny 1 paper

Strategy and Resources Scrutiny Committee approved this item on Monday 14 October 2013. Below is the council's own wording, with the papers it was decided on.

Item13/70/SR

Resolved

Decision of the Executive Councillor for Customer Services and Resources Resolved to: Financial recommendations i. Approve the commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan (PR020). - The total cost of the project is £333,930, funded from the IT Infrastructure repairs and renewals fund and the Technology Investment Fund. - There are no ongoing revenue cost implications arising from the project. Procurement recommendations ii. Approve the carrying out and completion of the procurement of hardware, software and labour to support the upgrades. Subject to: - The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract. - The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Reasons for the Decision As set out in the Officer’s report Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The committee received a report from the Head of ICT regarding email, file and storage system and server upgrades. Councillor Herbert welcomed the work done by officers on this project. It was hoped that an improvement to the system would enable all Councillors to use a generic email address and lead to enhanced calendar functionality. Councillor Rosenstiel supported these comments and felt that it would be beneficial for the public if all Councillors used their generic email addresses. The Committee resolved unanimously to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) Not applicable.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Recommendations

Financial recommendations – • The Executive Councillor is asked to approve the commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan (PR020). • The total cost of the project is £333,930, funded from the IT Infrastructure repairs and renewals fund and the Technology Investment Fund. • There are no ongoing revenue cost implications arising from the project. Procurement recommendations: • The Executive Councillor is asked to approve the carrying out and completion of the procurement of hardware, software and labour to support the upgrades. • Subject to: - The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract. - The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%.

Project Name: E-mail, file storage system and server upgrades

1 Summary 1.1 The project

To change the Council’s e-mail system from Northgate GroupWise to Microsoft Exchange / Outlook, replace current file storage software with Microsoft products and upgrade supporting hardware.

Target Dates: by end March 2014. Start of procurement Arrangements already in place Award of Contract Arrangements already in place Start of project delivery February 2014 Completion of project April 2014 Date that project output is expected to become operational (if not same as above)

1.2Anticipated Cost Total Project Cost £333,930 Cost Funded from:

Funding: Amount: Details:

Reserves £0 IT Infrastructure R&R fund Repairs & Renewals £226,930 (cost centre 27742) Developer £0 Contributions Climate Change £0 Fund Technology Investment Other £107,000 Fund (cost centre 24613)

1.3Procurement process Procurement is required for ICT hardware and software. Both will be procured under government framework contracts via Northgate Information Solutions.

2 Project Appraisal & Procurement Report

2.1Project Background The Council has been using Novell’s GroupWise for e-mail and collaboration for some time, and at the time of initial procurement this was fairly common software in local government. Most organisations are now using Exchange and Outlook, together with Microsoft file storage software, and we are now increasingly finding problems of integration, as well as being reliant on specialist support.

2.2Aims & objectives

Objectives To upgrade core office systems by the end of March 2014, specifically:  Move from GroupWise to Exchange and Outlook  Move from Novell file storage to Microsoft.  Move from Novell system access management systems to Microsoft (eDirectory to Active Directory).  Upgrade related servers and storage, and complete the upgrade of the virtual server environment to a later version.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
E-Mail, File and Storage System and Server UpgradesReport 56 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
MP
Councillor Mike PittChair, present
RC
Councillor Rod CantrillVice-Chair, present
MA
Councillor Mark AshtonCommittee Member, present
JB
Councillor Jeremy Benstead Labour Spokes for Customer Services and ResourcesCommittee Member, present
MB
Councillor Max BoyceCommittee Member, present
LH
Councillor Lewis Herbert Labour Spokes for Strategy and Climate ChangeCommittee Member, present
CO
Councillor Carina O'ReillyCommittee Member, present
CR
Councillor Colin RosenstielCommittee Member, present

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies