Environment Scrutiny Committee, Tuesday 8 July 2014 at 5.00pm

A14 Cambridge to Huntingdon Improvement Scheme - Public Consultation Response

Agreed Scrutiny 3 papers

Environment Scrutiny Committee agreed this item on Tuesday 8 July 2014. Below is the council's own wording, with the papers it was decided on.

Item14/52/Env

Resolved

Decision As part of the proposals to improve the A14 between Cambridge and Huntingdon, the Highways Agency has recently undertaken preapplication consultation on the proposed improvement scheme. Consultation started on 7 April and ended on 15 June 2014. Due to the timescales of the consultation and gaps in some of the key information necessary to consider the Council’s position on this scheme, the City Council has agreed with the Highways Agency that its response will be submitted as soon as practical after the close of consultation. The Officer’s report set out the background to the A14 improvements and outlined the details of the proposed scheme. Decision of Executive Councillor for Planning Policy and Transport i. Agreed the Council’s interim response to the Highways Agency consultation as set out in Appendix B of the Officer’s report. ii. Agreed the Council’s final response be submitted by the Head of Planning Services in consultation with the Executive Councillor and Chair and Spokes of Environment Scrutiny Committee. iii. Agreed that, in the interests of expediency, delegated authority be given to the Head of Planning Services to prepare and submit reports, proofs of evidence, technical papers, statements of common ground and other such documents, undertake appropriate negotiations and make further minor additions to the councils case at the examination of the A14 scheme if in the opinion of the Head of Planning Services it is appropriate and necessary to do so and to take such other necessary steps as are conducive or incidental to the presentation of the councils case at that examination. The exercise of this delegation to be reported back to Development Plan Scrutiny Sub-Committee at the end of the examination process. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Planning Services. She referred to paragraph 3.11 (P157) and said that a response was still pending from the Highways Agency. The Committee made the following comments in response to the report: i. Councillors were unable to comment on the proposal without data from the Highways Agency. Suggested Officers seek this prior to drafting a response for consideration by Councillors. ii. Agreed the Council’s final response should be submitted by the Head of Planning Services in consultation with the Executive Councillor and Chair and Spokes of Environment Scrutiny Committee (as per the recommendation). Later report text only referred to consultation with the Chair and Executive Councillor. iii. The location of the crematorium was close to the highway, appropriate access and noise mitigation measures were required. iv. The A14 would benefit from investment/improvement. In response to Members’ request the WSP Consultant outlined the following summary of the A14 improvement scheme: i. It was hard to quantify the impact of the scheme on the city due to a lack of information from the Highways Agency. ii. Without information on the Highways Agency transport model it was difficult to evaluate: · Accuracy of the model. · The impact on some areas if others are congested. · Noise impact on the crematorium. iii. The current crematorium access from the A14 was not ideal. iv. Welcomed the new cycle scheme. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor ( and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Safe roads, reliable journeys, informed travellers

Cambridge to Huntingdon improvement scheme A14 Scheme objectives Scheme objectives The section of the A14 trunk road between Cambridge and Huntingdon is well known for congestion and delays. Built more than 30 years ago, the road cannot cope with the current daily volume of traffic and is in need of improvement.

In June 2013, Government announced its commitment to the A14 Cambridge to Huntingdon improvement scheme by approving investment of up to £1.5billion. The scheme seeks to:

n Combat congestion

n Unlock growth

n Connect people

n Improve safety and

n Create a positive legacy for the area

An executive agency of the Department for Transport Highways Agency media services Bedford S130710 Safe roads, reliable journeys, informed travellers

Cambridge to Huntingdon improvement scheme A14 How you can be involved A scheme of this size is considered to be a Nationally Significant Infrastructure Project (NSIP) as defined by the Planning Act 2008 and this requires the Highways Agency to submit a Development Consent Order (DCO) application for approval to construct the scheme. We plan to submit an application in autumn 2014. The application and approval process follows five steps as set out below:

The five steps How you can be involved  View our proposals Pre-application  Attend our consultation events

 Provide your comments by 23:59 on Sunday 15 June 2014

 The Planning Inspectorate has 28 days to decide whether the application Acceptance meets the required standards to proceed, including whether our consultation has been adequate

 You can register with the Planning Inspectorate as an interested party Pre-examination so as to be kept informed of progress and opportunities to be involved. The Planning Inspectorate will set timescales

 The Planning Inspectorate has six months to carry out the examination  Registered parties can send written comments to the Planning Inspectorate Examination  They can ask to speak at a public hearing

 The Planning Inspectorate will make a recommendation to the Decision Secretary of State within three months. The Secretary of State then has a further three months to issue a decision

During the pre-application phase we are holding a formal consultation with the community and other stakeholder groups to receive views on our proposals.

An executive agency of the Department for Transport Highways Agency media services Bedford S130710 Safe roads, reliable journeys, informed travellers

Cambridge to Huntingdon improvement scheme A14 Why we are consulting We want to understand what is important for commuters, businesses, freight operators, non-motorised road users, developers and for the many people who live along the A14 corridor in this area – so that we can build this into the scheme design.

2011/12 Development of options

July 2012 Government confirms A14 Cambridge to Huntingdon improvement scheme will be tolled

September - October 2013 Public consultation on scheme options Pre-application

December 2013 Decision made not to toll the A14

January - April 2014 Further examination of non-tolled options

April - June 2014 Formal consultation on proposed scheme

Autumn 2014 Application Development Consent Order application

Development Consent Order application accepted by the Acceptance Planning Inspectorate

Register as an interested party Pre-examination Submit representations

Spring/Summer 2015 Examination Development Consent Order examination starts

Autumn 2015 Recommendation Report to the Secretary of State

Early 2016 Decision Secretary of State decision

By end of 2016 Start of works

Consultation has already been undertaken to help us develop options and we now seek your views on our proposed scheme. Consultation on land requirements needed for the construction of the scheme is also an important part of the DCO application process and we ask for your comments on these.

Your views and comments will help us to develop the most appropriate design to meet community and business needs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A14: Ap 1 /52/EnvReport 8.6 MB DownloadRead as text
PDF
A14: Ap 2 /52/EnvReport 1.7 MB Download
PDF
A14 Cambridge to Huntingdon Improvement Scheme: Public Consultation ResponseReport 153 KB Withheld: personal details

At this meeting

Whole meeting

Who was there

9 of 9 attended
NG
Councillor Nigel GawthropeChair, present
CP
Councillor Charlotte PerryVice-Chair, present
TM
Councillor Tim MooreCommittee Member, present
MP
Councillor Mike Pitt Lib Dem Spokes for Environment, Waste and Public HealthCommittee Member, apologies, sent representative
DR
Councillor Dan RatcliffeCommittee Member, present
RR
Councillor Richard RobertsonCommittee Member, present
CS
Councillor Catherine Smart Lib Dem Spokes for Planning Policy and TransportCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present
DT
Councillor Damien TunnacliffeCommittee Member, present as substitute

On this subject at Cambridge

Search all
  1. A14 Cambridge to Huntingdon Improvement Scheme - Public Consultation ResponseThis decision
  2. S/1355/17/FL - Land Immediately West Of The Electricity Pylon And Foul Pump Station Histon Road Impington, 07/0003/NMA2 - Land Between Huntingdon Road And Histon Road Cambridge Cambridgeshire CB3 0LE, S/0001/07/NMA1 - Land Immediately WestDecided
  3. 18/0355/FUL - Darwin Green One, Land Between Huntingdon Road and Histon Road CambridgeDecided
  4. 16/1973/ADV: North West Cambridge Development Site, Madingley Road and Huntingdon RoadApproved
  5. 16/1242/ADV - North West Cambridge Development Site, Madingley Road and Huntingdon Road.Refused
  6. 15/1670/REM Darwin Green One, Land Between Huntingdon Road And Histon Road CambridgeDecided

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies