CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cambridge City Council
Strategy and Resources Scrutiny Committee, Monday 14 July 2014 at 5.00pm

Shared Services

Agreed Scrutiny 1 paper

Strategy and Resources Scrutiny Committee agreed this item on Monday 14 July 2014. Below is the council's own wording, with the papers it was decided on.

Item14/61/SR

Resolved

The report provided members with an update on the Council’s current shared service arrangements and the potential for the further sharing of services going forward. It also suggested an approach to governance around this subject. Decision of the Leader The Leader resolved: i. To endorse the proposed outcomes for shared working in Section 4.1 of the officer’s report as the basis for shaping future shared service work for the Council. ii. That a joint project governance structure be set up with a Member Steering Group overseeing the process supported by a shared service project board as described in Section 7 of the officer’s report. iii. That the Council Leaders be appointed to that Steering Group with the power to co-opt individual relevant portfolio holders as required. iv. That an ‘in principle’ agreement be given to a shared services between South Cambridgeshire District Council (SCDC) and Huntingdon District Council (HDC) for ICT and Legal as set out in the report and that the project board be tasked with agreeing outline business cases by September 2014. Reasons for the Decision : As set out in the officer’s report Any alternative options considered and rejected: As set out in the officer’s report Scrutiny Considerations: The committee received a report from the Director of Business Transformation. In response to member’s questions the Director of Business Transformation said the following: i. The initial work would provide a ‘road map’ highlighting potential opportunities for shared services ii. Improved ICT may open up opportunities for shared services elsewhere – i.e back office functions. The Scrutiny Committee considered the recommendations and endorsed them unanimously. The Leader approved the recommendations. Conflicts of Interest Declared by the Leader (and any Dispensations Granted): Not applicable.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Executive summary

This report provides members with an update on the Council’s current shared service arrangements and the potential for the further sharing of services going forward. It also suggests an approach to governance around this subject.

Recommendations

The Executive Councillor is recommended:

2.1That Members endorse the proposed outcomes for shared working in Section 4.1 as the basis for shaping future shared service work for the Council.

2.2That a joint project governance structure be set up with a Member Steering Group overseeing the process supported by a shared service project board as described in Section 7 below.

2.3That the Council Leaders be appointed to that Steering Group with the power to co-opt individual relevant portfolio holders as required.

2.4That an ‘in principle’ agreement be given to a shared services between South Cambridgeshire District Council (SCDC) and Huntingdon District Council (HDC) for ICT and Legal as set out in the

Report Page No: 1 report and that project board be tasked with agreeing outline business cases by September 2014.

Background

3.1The impact of cuts in public spending has meant that all public agencies have had to find more efficient ways of delivering services. One of the ways we have sought to deliver those efficiencies is to deliver services in shared arrangements with other local authorities.

3.1.2 To date we are sharing:

Home Improvement Agency - Cambridge City Council (CCC), (SCDC) and (HDC)

Internal Audit - CCC, SCDC and Peterborough City Council

Support to Joint Development Control Committee - provided by CCC

Payroll - CCC and SCDC

CCTV - CCC and HDC

Interim S151 Officer - provided to CCC by SCDC

3.1.3 We have also agreed a City Deal with government which would ultimately see the Council setting up a combined authority with SCDC and the County Council to deliver strategic planning and transport.

3.1.4 The original approach was to seek opportunities to develop shared services as they emerged. Last November we agreed a list of back- office services to explore particularly with SCDC as the geography of the two councils and the nature of the City Deal made them a natural first point of contact. However, this has not been an exclusive partnership and we have also been discussing with HDC the opportunity for sharing services where we have a more similar service offering.

3.1.5 This report seeks to update members on where discussions currently are and to propose a formal structure going forward to explore the opportunities for shared services with both SCDC and HDC where appropriate.

Report Page No: 2 4. Outcomes for Shared Working

4.1The Council recognises that it will be smaller going forward and one of the ways to develop local public services is to work in shared service arrangements in order to help protect key services and to ensure resilience whilst retaining local control and sovereignty.

4.2CCC, SCDC and HDC have different ways of providing some services and different levels of discretionary services. They also have very different geographies with one being urban, one being rural and one a mix of the two. This means that it may make sense to combine some services together across all three councils, but more pragmatically some services may make sense in different combinations of the two authorities.

4.3In working together, in whatever permutation, all three Councils will seek to deliver seamless services to internal service users and the public and to deliver the following outcomes:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Shared ServicesReport 103 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
RR
Councillor Richard RobertsonChair, present
AS
Councillor Ann SinnottVice-Chair, present
DB
Councillor Dave BaigentCommittee Member, present
JB
Councillor Jeremy BensteadCommittee Member, present
TB
Councillor Tim Bick Lib Dem Spokes for Strategy, Transformation and FinanceCommittee Member, apologies, sent representative
RC
Councillor Rod CantrillCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present
JS
Councillor Julie Smith Lib Dem Spokes for ResourcesCommittee Member, present
CS
Councillor Catherine SmartReserve, present as substitute

On this subject at Cambridge

Search all
  1. Shared ServicesThis decision
  2. 4 Day Week - Shared Services South Cambridgeshire District CouncilApproved
  3. Shared Services Partnership AgreementApproved
  4. Update on the Shared Services Partnership AgreementAgreed
  5. 3Cs Legal and ICT Services and Greater Cambridge - Internal Audit Shared Service - 2020/21 Annual ReportsNoted
  6. 3Cs Legal and ICT Services and Greater Cambridge - Internal Audit Shared Service - 2019/20 Annual Reports and Partnership Agreement ReviewNoted

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies