Budget Setting Report February 2015

Agreed Scrutiny 2 papers

Strategy and Resources Scrutiny Committee agreed this item on Monday 19 January 2015. Below is the council's own wording, with the papers it was decided on.

Item15/14/SR

Resolved

The Budget-Setting Report (BSR) provided an overview of the review of the key assumptions. It included the detailed revenue bids and savings and set out the key parameters for the detailed recommendations and budget finalisation to be considered at the meeting of The Executive on 22 January 2015. The Executive would make final budget recommendations to Council, for consideration at its meeting on 26 February 2015. Decision of the Executive Councillor for Finance and Resources The Executive Councillor resolved to: General Fund Revenue Budgets: [Section 5, page 28 of the BSR refers] i. Agree any recommendations for submission to the Executive in respect of: - Revenue Pressures shown in Appendix B(a) and Savings shown in Appendix B(b). - Priority Policy Fund (PPF) Bids as shown in Appendix B(c) of the BSR. - Bids to be funded from External or Earmarked Funds as shown in Appendix B(d) of the BSR. - Non Cash Limit items as shown in Appendix B(e) of the BSR ii Formally confirm delegation to the Chief Financial Officer (Head of Finance) of the calculation and determination of the Council Tax taxbase (including submission of the National Non-Domestic Rates Forecast Form, NNDR1, for each financial year) as set out in Appendix A(a) of the BSR. iii Recommend to Council the level of Council Tax for 2015/16 as set out in Section 4 [page 26 of the BSR refers]. Note that the Cambridgeshire Police and Crime Panel will meet on 28 January 2015 to consider the precept proposed by the Police and Crime Commissioner, Cambridgeshire & Peterborough Fire Authority will meet on 12 February 2015 and Cambridgeshire County Council will meet on 17 February 2015 to consider the amounts in precepts to be issued to the City Council for the year 2015/16. Treasury Management (see separate report). Other Revenue: ii Delegate to the Head of Finance authority to finalise changes relating to any corporate and/or departmental restructuring and any reallocation of support service and central costs, in accordance with the CIPFA Service Reporting Code of Practice for Local Authorities ( SeRCOP ). iii Approve an amendment to the remit for the “Sharing Prosperity Fund” so that the revised remit (changes are underlined) is Capital: [Section 7, page 35 of the BSR refers] Capital Plan: ii Agree any recommendations to the Executive in respect of the proposals outlined in Appendix D(a) of the BSR for approval to include in the Capital Plan, or put on the Projects Under Development or Hold Lists, including any additional use of revenue resources required. iii Agree the revised Capital Plan as set out in Appendix D(c) of the BSR, the Projects Under Development and Hold lists set out in Appendices D(d) and D(e) respectively and the Funding as set out in Section 7, page 41 of the BSR for the General Fund. General Fund Reserves: iiii Note the impact of revenue and capital budget approvals and approve the resulting level of reserves to be used to support the budget proposals as set out in the table [Section 6, report page 34 and Section 8, page 46 of the BSR refers]. Reasons for the Decision : As set out in the officer’s report Any alternative options considered and rejected: As set out in the officer’s report Scrutiny Considerations: The committee received a report from the Head of Finance. In response to member’s questions the Head of Finance said the following: ii. With regard to the process for non-vehicular repair and renewal (R&R) bids: - Revenue R&R would be funded from the Revenue Repairs Budget - Capital R&R would be funded via a capital bid through the budget setting process. It was noted that the current Capital process was very complex and officers were working to simplify and standardise it. iii. Commitments against the New Homes Bonus (NHB), as shown on page 31 of the BSR, are the same headings as in last year’s budget, and the priority order would be dependent on City Deal arrangements. It was unlikely, with current allocations, that homelessness prevention would be affected. iv. Car park income was very difficult to accurately estimate. Whilst the Council used consultants to help predict the income this was not an exact science and was affected by many variables. The Director of Environment added that, whilst there were many variables, there were also many constants i.e. growth of the City and surrounding areas which could help estimate car park income. It was confirmed that the Transport Strategy took account of the Park and Ride sites. iiv Budget Reference NCL3716 (New Homes Bonus - additional): This represented income being put into projections for future years. iv Budget Reference NCL3716 (New Homes Bonus - unallocated): This was the balance of unallocated income which would go into the NHB reserve fund. ivi Agreed to provide capital bid documentation prepared in line with existing procedures for new projects to Councillor Bick prior to the meeting of The Executive, if required. ivii A new prioritisation process was being developed by officers. Whilst the old style paperwork would still be used during this transition period officers were looking in more detail at projects during the prioritisation stage. The Executive Councillor for Finance and Resources added that, in the past many projects had been added with little or no business case and the new prioritisation process would address this. Park Street Car Park and the public convenience project were examples of this. iviii Options for Park Street Car Park had been consulted on but they had very different costings and timings. Until a preferred option had been agreed upon the project was therefore placed on the Projects Under Development (PUD) list. iix Whilst the Council needed to be aware of projects upcoming for the Capital Plan, there was no need to allocate the money before a Business case had been developed. The Executive Councillor for Finance and Resources added that more efficiency with the Capital Plan process was needed. Placing items on the Plan that had not been fully costed simply tied up money that could be used elsewhere. In response to member’s questions the Executive Councillor for Finance and Resources said the following: v. The funding for public conveniences would be released pending the outcome of the review of provision. The funding had therefore been placed on the Projects Under Development section (PUD) list. The Scrutiny Committee considered the recommendations and endorsed them by 5 votes to 0. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted): Not applicable.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Version 1 Strategy & Resources

Budget Setting Report 2015/16

February 2015 2015/16

Cambridge City Council Version Control Version Revised version / Content / Items for Consideration No. updates for:

Strategy & Resources Scrutiny Committee Initial budget overview and budget proposals Current

1 (19 January 2015)

The Executive Proposals of The Executive (22 January 2015)

Special Strategy & 2 Amendments to Executive proposals Resources Scrutiny Committee Opposition budget amendment proposals (13 February 2015)

Final Proposals to Council Incorporating updates relating to; Council 3 - Final Local Government Finance Settlement 2014/15 (26 February 2015) and grant determinations - Director of Resources final Section 25 report

Approved Budget Setting Report incorporating - Decisions of Council 4 Council (Final) - Appendix B Council Tax Setting following receipt of County Council, Police and Fire Authority precepts

Anticipated Precept Setting Dates

Cambridgeshire Police Cambridgeshire & Cambridgeshire County and Crime Peterborough Fire Authority Council Commissioner

28 January 2015 12 February 2015 17 February 2015 Contents Section No. Topic Page No.

Foreword by the Leader of the Council and the Executive Councillor for Finance and Resources

1 Introduction 1

2 Local and National Policy Context 3

3 Public Budget Consultation 9

4 General Fund Resources 13

5 General Fund Revenue Budgets 28

6 General Fund revenue and funding 2014/15 to 2019/20 34

7 Capital 35

8 Risks and general reserves 43

9 Future strategy and recommendations 47

10 Section 25 Report (Council version only) 50

Appendices Reference Topic Page No.

A(a) Council Tax base 2015/16 51

A(b) Council Tax setting 2015/16 52

B(a) Detailed revenue proposals - pressures 54

B(b) Detailed revenue proposals - savings 58

B(c) Detailed revenue proposals – PPF bids 70

B(d) Detailed revenue proposals – external / earmarked bids 72

B(e) Detailed revenue proposals – non-cash limit items 75 Reference Topic Page No.

C Sensitivity analysis 78

D(a) Capital plan – proposals 81

D(b) Capital proposals requiring funding from revenue resources 89

D(c) Capital plan 92

D(d) Capital plan – Projects under Development (PUD) list 96

D(e) Capital plan – Hold list 98

E Earmarked funds 99

F Equality Impact Assessment 102

G Significant events 118

Contacts 119 Foreword by the Leader of the Council and the Executive Councillor for Finance and Resources

This budget heralds a major shake-up of the way this council manages its finances. It aims to utilise the extensive resources that we possess to much better effect, in order to put the council on a sound financial footing in the years to come. It meets the annual savings target, while also making a very substantial contribution to finding the necessary savings for the next two years, without compromising our frontline services. It manages to do this while also freeing up resources to invest in our strategy to make Cambridge a fairer and more equal place, as well as improved transport and infrastructure. It does this by accelerating our business transformation strategy while carefully investing in the city’s future, utilising funds freed up from our earmarked reserves and our capital programme in order to convert them to revenue streams.

The financial context is well-known, but it bears repeating. There appears to be no end to the national austerity agenda, and cuts to our Revenue Support Grant are projected to continue at a rate of roughly 13% per annum. This has resulted in the substantial savings target of £1.225m in 2015/16, and £6m over five years, targets which are effectively increased by a wide-range of unavoidable revenue pressures that have emerged in the course of the budget process. This presents a formidable financial challenge.

Our strategy for meeting this challenge has been partially focussed on earmarked reserves and the capital plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BSR: Doc /14/SRReport 1.6 MB DownloadRead as text
PDF
Budget Setting Report February 2015Report 221 KB Download

At this meeting

Whole meeting

Who was there

8 of 9 attended
RR
Councillor Richard RobertsonChair, present
AS
Councillor Ann SinnottVice-Chair, present
DB
Councillor Dave BaigentCommittee Member, present
JB
Councillor Jeremy BensteadCommittee Member, present
TB
Councillor Tim Bick Lib Dem Spokes for Strategy, Transformation, Finance and ResourcesCommittee Member, present
RC
Councillor Rod CantrillCommittee Member, present
CS
Councillor Catherine SmartCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present
JS
Councillor Julie SmithReserve

On this subject at Cambridge

Search all
  1. Budget Setting Report February 2015This decision
  2. Budget Setting Report and Medium Term Financial Strategy 2026-27Agreed
  3. Cabinet: Update on Budget Setting Consultation 2025-26Noted
  4. Budget Setting Context 2026-27Agreed
  5. HRA Budget-Setting Report (BSR) 2025/26Agreed
  6. General Fund Budget Setting Report 2025/26 to 2029/30Approved

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies