Action on Energy Progress Update

Noted Scrutiny 2 papers

Strategy and Resources Scrutiny Committee noted this item on Monday 23 March 2015. Below is the council's own wording, with the papers it was decided on.

Item15/37/SnR

Resolved

Decision The Officer report advised that since being awarded Green Deal Communities funding in March 2014, the Action on Energy partnership had undertaken extensive engagement activity across Cambridgeshire and as a result have secured strong interest from local residents in insulation grants, including a particularly high response rate in Cambridge City. The decision is to note the progress made on Action on Energy. Decision of Executive Councillor for Finance and Resources N oted the progress and issues presented in the report. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Environmental Quality & Growth Manager. In response to Members’ questions the Environmental Quality & Growth Manager said the following: i. The Action on Energy partnership would continue even if grant funding ceased in future, it was a delivery vehicle that could use any funding stream. ii. A variety of means had been used to try and engage the private sector through incentives and marketing schemes. Good offers were available if the private sector wished to take them up. iii. A meeting between Department of Energy & Climate Change, the City Council and partners in April 2015 would look at how to better engage the private sector. iv. The size of properties in Cambridge affected the type of energy efficiency measures that could be used in them. Internal wall insulation take up was lower than external, although it was just as effective, because it reduced people’s living space. The thickness of insulation was unlikely to change in future, so people may wish to change how they used it. For example, mid terrace houses could have internal insulation at the front, and external at the rear (where it would not be seen). They would be insulated on the sides by neighbours. v. Energy efficiency work could be undertaken on rendered properties. Planning Officers had advised that like for like rendering (post energy efficiency work) could be undertaken without seeking planning permission, it would only be required if materials were changed. vi. All properties would get a full survey prior to work being undertaken by Green Deal accredited installers. Work was guaranteed for twenty five years. vii. A show home was available to visit at 155 Coleridge Road. viii. The Home Energy Officer undertook to provide committee members with original and updated figures for Green Deal Communities activity in relation to the report submitted to Strategy and Resources scrutiny committee of 23 March 2015. The Committee unanimously resolved to endorse the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Executive summary

1.1Since being awarded Green Deal Communities funding in March 2014, the Action on Energy partnership have undertaken extensive engagement activity across Cambridgeshire and as a result have secured strong interest from local residents in insulation grants, including a particularly high response rate in Cambridge City.

1.2However some elements of the project have been particularly challenging such as securing interest in the private rented sector.

1.3The partnership with a procured Green Deal Provider, Climate Energy, has provided additional resources that would not normally be available which has allowed successful targeted street by street engagement to take place. However there have also been issues such as poor customer management, length of customer journey, and installation capacity that has required active contract management by Council Officers to reduce the impact on residents and reduce reputational risk to the Council.

1.4Green Deal Communities funding has provided a very attractive offer to residents to install energy efficiency improvements and has provided the opportunity to develop support to the market through show homes, planning guidance, improved local resources and the opportunity to train local small and medium enterprises (SME’s) This Report Page No: 1 activity is now resulting in additional interest in the funding and jobs being completed.

1.5Funding was originally scheduled to end in March 2015, however it has been agreed by Amber Rudd, Parliamentary Under Secretary of State for energy and climate change that the time period for delivering the project should be extended until 30th September 2015. On this basis we are expected to deliver 400 sign-ups by households in Cambridgeshire by 31st March 2015, and a total of 1800 sign-ups by 30th September 2015. However while funding can be allocated up to 30th September 2015, any monies allocated at that point can be spent on installations up until 31st March 2016.

1.6We have been provided a variation of the Memorandum of Understanding to reflect these changes and the detail of this document is being agreed with the Department for Energy and Climate Change, with advice from Cambridge City Council Legal Department. Once finalised this is required to be signed by an appropriate senior council officer with authority to act on behalf of the Council.

Recommendations

The Executive Councillor is recommended:

To note the progress and issues presented in the report.

Background

3.1In January 2013 the Executive Councillor for Planning and Climate Change approved:

1) the establishment of a partnership of the Cambridgeshire Districts to deliver the Green Deal work proposal, subject to detailed approval of a Memorandum of Understanding between the Authorities involved at Public Service Board;

2) to conduct of a procurement exercise and award of contract(s) to one or more Green Deal commercial providers to be let on a County wide basis and in collaboration with Cambridgeshire Local Authorities.

3.2The six Cambridgeshire Local Authorities created a single Cambridgeshire brand called ‘Action on Energy’ (AoE) and, in the summer of 2013, procured a partnership with Climate Energy to deliver Green Deal, ECO and self-financed energy efficiency Report Page No: 2 measures across the county. The partnership launched in early November 2013, with a contract in place for three years, and an option to extend for every additional year up to 2019.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Action on Energy Appendix A: EqIA-Green Deal /37/SnRAppendix 104 KB Download
PDF
Action on Energy Progress UpdateReport 118 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
RR
Councillor Richard RobertsonChair, present
AS
Councillor Ann SinnottVice-Chair, present
DB
Councillor Dave BaigentCommittee Member, present
JB
Councillor Jeremy BensteadCommittee Member, present
TB
Councillor Tim Bick Lib Dem Spokes for Strategy, Transformation, Finance and ResourcesCommittee Member, present
RC
Councillor Rod CantrillCommittee Member, present
CS
Councillor Catherine SmartCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present
JS
Councillor Julie SmithReserve

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open