2014/15 Revenue and Capital Outturn, Carry Forwards and Significant Variances - Environment and Waste Health Portfolio

Agreed Scrutiny 1 paper

Environment Scrutiny Committee agreed this item on Tuesday 7 July 2015. Below is the council's own wording, with the papers it was decided on.

Item15/28/Env

Resolved

Decision The Officer’s report presented a summary of the 2014/15 outturn position (actual income and expenditure) for services within the Environment and Waste portfolio, compared to the final budget for the year. The position for revenue and capital was reported and variances from budgets were highlighted, together with explanations. Requests to carry forward funding arising from certain budget underspends into 2015/16 were identified. Decision of Executive Councillor for Environment and Waste i. Agreed the carry forward requests totalling £96,400 as detailed in Appendix C of the Officer’s report, to be recommended to Council for approval. ii. Agreed to seek approval from Council to carry forward capital resources to fund rephrased net capital spending of £537,000 from 2014/15 into 2015/16, as detailed in Appendix D of the Officer’s report. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Finance which noted that the outturn reports presented to the Committee cycle reflected the reporting structures in place prior to the recent changes in Executive portfolios. In light of these changes (together with the requirement to report outturn on the basis of portfolios in place during 2014/15) members of this committee were asked to consider the proposals to carry forward budgets and make their views known to the Executive Councillor for Finance and Resources, for consideration at Strategy & Resources Scrutiny Committee prior to the recommendations to Council. In response to the Committee’s comments Officers and the Director of Environment and the Executive Councillor for Environment and Waste made the following statements: i. Following a change in the process the previous year the recharges were now allocated slightly differently. ii. Although it appeared there were differences line by line between original budgets and final budgets, the total budget had not changed, only the way in which the overhead costs had been allocated across budget lines. The restructuring of overhead costs was deemed to be a technical adjustment. iii. The carry forward request of £50,000 for the new post of Contracts Manager was for a fixed twelve month contract pending further review. The recruitment process had been followed but the Director of Environment would confirm to the Committee the basis on which the decision had been made. iv. Confirmed that few adjustments had gone through the Mid year Financial Review v. Although the overall capital for streets and open spaces had not changed significantly compared to previous years, there had been an increase in monies spent which had focused on public priorities, such as the recruitment of a dog warden, additional money on posters, bins and enforcement. vi. Officers were working to improve the accounting reporting process for scrutiny. vii. The bulk of the underspend related to the purchase of new vehicles which had been ordered in the second half of the previous year but the monies had been spent in the first quarter of this financial year. The Committee resolved (6 votes to 0) to endorse the recommendations. The Executive Councillor approved the recommendations.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Executive summary

1.1This report presents a summary of the 2014/15 outturn position (actual income and expenditure) for services within the Environment and Waste Portfolio, compared to the final budget for the year. The position for revenue and capital is reported and variances from budgets are highlighted, together with explanations. Requests to carry forward funding arising from certain budget underspends into 2015/16 are identified.

1.2It should be noted that outturn reports being presented in this Committee cycle reflect the reporting structures in place prior to the recent changes in Executive portfolios. In light of those changes (together with the requirement to report outturn on the basis of portfolios in place during 2014/15) members of this committee are asked to consider the proposals to carry forward budgets and make their views known to The Executive Councillor for Finance and Resources, for consideration at Strategy & Resources Scrutiny Committee prior to his recommendations to Council.

Recommendations

Members of the Scrutiny Committee are asked to consider and make known their views on the following proposals:

a) To agree the carry forward requests totalling £96,400 as detailed in Appendix C, to be recommended to Council for approval.

b) To seek approval from Council to carry forward capital resources to fund rephased net capital spending of £537,000 from 2014/15 into 2015/16, as detailed in Appendix D. 3. Background

Revenue Outturn

3.1The outturn position for the Environment and Waste Portfolio, compared to final revenue budget, is presented in detail in Appendix A.

3.2Appendix B to this report provides explanations of the main variances.

3.3Appendix C sets out the final list of items, for this portfolio, for which approval is sought to carry forward unspent budget from 2014/15 to the next financial year, 2015/16.

3.4The overall revenue budget outturn position for the Environment and Waste Portfolio is set out in the table below:

Environment and Waste Portfolio £ 2014/15 Revenue Summary

Final Budget 8,073,310

Outturn 7,776,373

Variation – (Under)/Overspend for the year (296,937)

Carry Forward Requests: 96,400

Net Variance (200,537)

The net variance represents 2.48% of the overall portfolio budget for 2014/15.

Capital Outturn

3.5Appendix D shows the outturn position for schemes and programmes within the Environment and Waste Portfolio, with explanations of variances.

3.6An overall net underspend of £537,000 has arisen which is due to slippage. Rephasing of items in the Capital Plan is required to transfer the budget into 2015/16.

4. Implications

4.1The net variance from the final budget, after approvals to carry forward budget of £96,400 from 2014/15 to the next financial year, 2015/16, would result in a decreased use of General Fund reserves of £200,537.

4.2In relation to anticipated requests to carry forward revenue budgets into 2015/16 the decisions made may have a number of implications. A decision not to approve a carry forward request will impact on officers’ ability to deliver the service or scheme in question and this could have staffing, equality and poverty, environmental, procurement, consultation and communication and/or community safety implications.

Background papers

These background papers were used in the preparation of this report:

 Closedown Working Files 2014/15  Directors Variance Explanations - March 2015  Capital Monitoring Reports - March 2015  Budgetary Control Reports to 31 March 2015

Appendices

 Appendix A - Revenue Budget 2014/15 - Outturn  Appendix B - Revenue Budget 2014/15 - Major Variances from Final Revenue Budgets  Appendix C - Revenue Budget 2014/15 - Carry Forward Requests  Appendix D - Capital Budget 2014/15 - Outturn

7. Inspection of papers

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2014/15 Revenue and Capital Outturn, Carry Forwards and Significant Variances: Environment and Waste Health PortfolioReport 206 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
NG
Councillor Nigel GawthropeChair, present
CP
Councillor Charlotte PerryVice-Chair, present
DB
Councillor Dave BaigentCommittee Member, present
MG
Councillor Markus GehringCommittee Member, present
OG
Councillor Oscar Gillespie Minorities Spokesperson for Environment and Waste plus Planning Policy and TransportCommittee Member, present
MP
Councillor Mike Pitt Lib Dem Spokes for Environment and WasteCommittee Member, present
DR
Councillor Dan RatcliffeCommittee Member, present
RR
Councillor Richard RobertsonCommittee Member, present
CS
Councillor Catherine Smart Lib Dem Spokes for Planning Policy and TransportCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present

On this subject at Cambridge

Search all
  1. 2014/15 Revenue and Capital Outturn, Carry Forwards and Significant Variances - Environment and Waste Health PortfolioThis decision
  2. 2023/24 General Fund Revenue and Capital Outturn, Carry Forwards and Significant Variances (Executive Councillor for Finance and Resources)Approved
  3. 2023/24 General Fund Revenue and Capital Outturn, Carry Forwards and Significant VariancesApproved
  4. 2022/23 General Fund Revenue and Capital Outturn, Carry Forwards and Significant VariancesApproved
  5. General Fund Revenue and Capital Outturn, Carry Forwards and Significant Variances Report (Executive Councillor for Finance, Resources and Transformation)Approved
  6. 2020/21 Revenue and Capital Outturn, Carry Forwards and Significant Variances – Housing Revenue Account (Executive Councillor for Strategy and External Partnerships)Approved

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open