Strategy and Transformation Portfolio Revenue and Capital Budgets
NotedScrutiny1 paper
Strategy and Resources Scrutiny Committee noted this item on Monday 18 January 2016. Below is the council's own wording, with the papers it was decided on.
Decision of the Leader Review of Charges i. Noted that none required formal approval within this portfolio (so no Appendix A). Revenue ii. Considered the revenue budget proposals shown in Appendix B. Capital iii. Considered the capital budget proposals shown in Appendix C. iv. Adjusted the capital funding for 2c (iii above). Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Finance. The Committee resolved by 7 votes to 0 to endorse the recommendations. The Leader approved the recommendations. Conflicts of Interest Declared by the Leader (and any Dispensations Granted): Not applicable.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
Executive summary
Revenue and Capital Budgets
1.1The following report details the budget proposals relating to this portfolio that are included in the Budget-Setting Report (BSR) 2016/17 which will be considered at the following meetings:
Date Committee Comments 18 January Strategy & Consider proposals / recommendations 2016 Resources from all Scrutiny Committees in relation to their portfolios 21 January The Executive Budget amendment may be presented 2016 8 February Strategy & Consider any further amendments including 2016 Resources opposition proposals 25 February Council Approves General Fund Budget and sets 2016 Council Tax
Recommendations
The Executive Councillor is recommended to:
Review of Charges:
a) There are none requiring formal approval within this Portfolio (so no Appendix A).
Report Page No: 1 Revenue:
b) Consider the revenue budget proposals as shown in Appendix B.
Capital:
c) Consider the capital budget proposals as shown in Appendix C. d) Adjust capital funding for item 2 (c).
Background
3.1At its meeting on 22 October 2015, Council gave initial consideration to the budget prospects for the General Fund for 2016/17 and future years in the Mid-year Financial Review (MFR) 2015.
3.2The overall BSR to Strategy & Resources Scrutiny Committee on 18 January 2016 will include a review of all the factors relating to the overall financial strategy that were included in the MFR.
3.3The report to The Executive on 21 January 2016 may include details of the Government’s Final Settlement for 2016/17. The announcement is likely to be made shortly after the conclusion of the consultation period, which ends on 15 January 2016.
3.4Further work may be required on detailed budgets, so delegation to the Head of Finance will be sought from Council for authority to finalise changes relating, for example, to the reallocation of departmental administration, support service and central costs, in accordance with the CIPFA Service Reporting Code of Practice for Local Authorities (SeRCOP).
Budget 2016/17 - Overall Revenue Budget Position
3.5The budget proposals for this portfolio, as summarised in table 1, will be considered by the Executive at its meeting on 21 January 2016.
Report Page No: 2 Table 1: Overall Revenue Proposals (see Appendix B)
2015/16 2016/17 2017/18 Savings and Bids Budget Budget Forecast £ £ £ Savings: Increased Income - - - Savings - (94,500) (94,500) Total - (94,500) (94,500)
Bids: Unavoidable Revenue Pressures - - - Reduced Income - - - Bids - 55,500 52,500 Total - - -
Net (savings)/bids - (39,000) (42,000)
External Bids - - -
Non-Cash Limit Items 408,000 230,000 81,000
Capital
3.6The review of the capital plan and capital approval processes, first proposed in the MFR 2014, is now complete. The review addressed a number of concerns, as listed below:
Capacity to deliver projects to time, cost and quality; Dependency on revenue funding; and Inclusion of items, such as unallocated funds, projects at an early stage of development, and items more properly treated as small enhancements or maintenance spend.
3.7Phase 1 sought to remove projects from the plan that were not fully specified and/or not deliverable. Phase 2 proposed and implemented new processes and procedures, including a Capital Programme Board to review and approve the planning and deliverability of schemes prior to funding approval. The operation of the board and the new processes will be kept under review to ensure effectiveness.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.