2015/16 Revenue and Capital Outturn, Carry Forwards and Significant Variances - Environment & Waste Portfolio

Approved Scrutiny 1 paper

Environment Scrutiny Committee approved this item on Tuesday 28 June 2016. Below is the council's own wording, with the papers it was decided on.

Item16/16/Env

Resolved

Decision of Executive Councillor for Environment and Waste. Resolved to request that the Executive Councillor for Finance and Resources, at the Strategy and Resources Scrutiny Committee on 4 July 2016, approves the following: i. Carry forward requests of £418k capital resources from 2015/16 to 2016/17 to fund rephased net capital spending, as detailed in Appendix D of the Officer’s report . Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Principal Accountant (Services). The Interim Strategic Director stated the following in response to Members’ questions: i. The variance in the Food and Occupational Safety spend was explained as a short term issue relating to two vacant posts. ii. It was expected that the Shared Waste Service would result in long term savings. However, initial set up costs and delays in the project delivery had resulted in an overspen . iii. Street cleaning savings had been the result of increased efficiency. The Committee resolved by 5 votes to 1 to endorse the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Executive summary

1.1This report presents, for the Environment & Waste Portfolio :

a) A summary of actual income and expenditure compared to the final budget for 2015/16 (outturn position)

b) Revenue and capital budget variances with explanations

c) Specific requests to carry forward funding available from budget underspends into 2016/17.

Recommendations

The Executive Councillor is recommended to request that the Executive Councillor for Finance and Resources, at the Strategy and Resources Scrutiny Committee on 4 July 2016, approves the following:

a) Carry forward requests of £418k capital resources from 2015/16 to 2016/17 to fund rephased net capital spending, as detailed in Appendix D.

Report Page No: 1 3. Background

Revenue Outturn

3.1The overall revenue budget outturn position for the Environment & Waste Portfolio is given in the table below. Detail, by service grouping, is presented in Appendix A.

2014/15 Environment & Waste Portfolio 2015/16 % Final £’000 Revenue Summary £’000 Budget

8,447 Original Budget 7,823 98.2

- Adjustment – Prior Year Carry Forwards 96 1.2

- Adjustment – Service Restructure Costs (7) (0.1)

- Adjustment – Earmarked Reserves 0 0.0

- Adjustment – Capital Charges 5 0.1

- Adjustment – Central & Support 45 0.6 reallocations

(374) Other Adjustments 0 0.0

8,073 Final Budget 7,962 100.0

7,776 Outturn 7,728 97.1

(297) (Under) / Overspend for the year (234) (2.9)

96 Carry Forward Requests 0 0.0

(201) Resulting Variance (234) (2.9)

3.2Appendix A shows original and final budgets for the year (with the movements summarised in the above table) and compares the final budget with the outturn position for this Portfolio for 2015/16. The original revenue budget for 2015/16 was approved by the Executive Councillor for Environment & Waste on 13 January 2015.

3.3Appendix B provides explanations of the main variances.

3.4Appendix C lists revenue carry forward requests for which there are none for this portfolio.

Report Page No: 2 Capital Outturn

3.5The overall capital budget outturn position for the Environment & Waste Portfolio is given in the table below. Appendix D shows the outturn position by scheme and programme with explanations of variances.

2014/15 Environment & Waste Portfolio 2015/16 % Final £’000 Capital Summary £’000 Budget

1,411 Final Budget 1,566 100.0

874 Outturn 1,186 75.7

(537) Variation - (Under)/Overspend for the (380) (24.3) year

537 Rephasing Requests 418 26.7

0 Variance 38 2.4

4. Implications

4.1The net variance from the final budget (see above), would result in a decreased use of General Fund reserves of £234k.

4.2A decision not to approve a carry forward request may impact on officers’ ability to deliver the service or scheme in question and this could have staffing, equality and poverty, environmental, procurement, consultation and communication and/or community safety implications.

Background papers

 Closedown Working Files 2015/16  Directors’ Variance Explanations – March 2016  Capital Monitoring Reports – March 2016  Budgetary Control Reports to 31 March 2016

6. Inspection of papers

To inspect the background papers or if you have a query on the report please contact:

Authors’ Names: Karen Whyatt; Jackie Collinwood Authors’ Phone Numbers: 01223 - 458145; 01223 - 458241 [email protected] Authors’ Emails: [email protected]

O:\accounts\Committee Reports & Papers\Environment Scrutiny\2016 June\Final\Env & Waste (formerly Env Waste & Public Health)\Environment (E & W) Draft Outturn Report 2015-16.docx

Report Page No: 3 Appendix A

Environment & Waste Portfolio / Environment Scrutiny Committee

Revenue Budget 2015/16 - Outturn

Variation Carry Forward Increase / Requests - see Service Grouping Original Budget Final Budget Outturn (Decrease) Appendix C Net Variance £ £ £ £ £ £

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2015/16 Revenue and Capital Outturn, Carry Forwards and Significant Variances: Environment & Waste PortfolioReport 207 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 6 attended
CP
Councillor Charlotte PerryChair, present
NG
Councillor Nigel GawthropeVice-Chair, present
TB
Councillor Tim Bick Lib Dem Spokes for Planning Policy & TransportCommittee Member, present
MG
Councillor Markus Gehring Lib Dem Spokes for Environment and WasteCommittee Member, present
DR
Councillor Dan RatcliffeCommittee Member, present
MS
Councillor Mike SargeantCommittee Member, present

On this subject at Cambridge

Search all
  1. 2015/16 Revenue and Capital Outturn, Carry Forwards and Significant Variances - Environment & Waste PortfolioThis decision
  2. 2023/24 General Fund Revenue and Capital Outturn, Carry Forwards and Significant Variances (Executive Councillor for Finance and Resources)Approved
  3. 2023/24 General Fund Revenue and Capital Outturn, Carry Forwards and Significant VariancesApproved
  4. 2022/23 General Fund Revenue and Capital Outturn, Carry Forwards and Significant VariancesApproved
  5. General Fund Revenue and Capital Outturn, Carry Forwards and Significant Variances Report (Executive Councillor for Finance, Resources and Transformation)Approved
  6. 2020/21 Revenue and Capital Outturn, Carry Forwards and Significant Variances – Housing Revenue Account (Executive Councillor for Strategy and External Partnerships)Approved

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies