Development Plan Scrutiny Sub-Committee, Tuesday 6 December 2016 at 4.30pm

Annual Monitoring Report 2016

Agreed Scrutiny 2 papers

Development Plan Scrutiny Sub-Committee agreed this item on Tuesday 6 December 2016. Below is the council's own wording, with the papers it was decided on.

Item16/71/DPSSC

Resolved

Decision of Executive Councillor i . To agree the content of the Annual Monitoring Report (AMR) (Appendix A to the officer’s report); ii. To agree that if any amendments are necessary, these should be agreed by the Executive Councillor for Planning Policy and Transport in consultation with Chair and Spokes of Development Plan Scrutiny Sub Committee. Reason for Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the The Planning Policy Manager, Principal Planning Policy Officer, and the Planning Policy Officer. The Committee welcomed the report and made the following comments in response: i. Questioned how the impact of large multi-national companies moving to the area, such as AstraZeneca, were managed. ii. Questioned the impact of devolution on the Local Plan. iii. Highlighted “land-banking” by developers as a risk to housing supply in the area and requested that an analysis be undertaken that identified where the development of sites had been delayed by developers. iv. Sought an update regarding the NIAB site that had been delayed considerably and whether the planned bus service for the site had been delayed. v. Questioned the use of policies from the emerging Local Plan and their reporting within the Annual Monitoring Report. vi. Questioned whether a financial viability check was undertaken on developers. vii. Asked whether the Design and Conservation Panel still operated and clarification of its role within the planning process. viii. Sought clarity regarding paragraph 7.14 of the Annual Monitoring Report. ix. Clarified what constituted the use of a planning policy and asked whether there was software available that could capture when specific planning policies were applied. The Planning Policy Manager, Principal Planning Policy Officer, and the Planning Policy Officer said the following in response to Members questions: i. Explained that although AstraZeneca moving to the area was unusual, it has contributed towards meeting the jobs growth forecast set out in the emerging Local Plan.it ii. Explained that the impact of devolution needed to be scoped and the next Local Plan would be prepared to be consistent with the aims of devolution. iii. Agreed to provide an analysis to Members that identified the length of time between a site being released for development and the development taking place that included commentary on why development had been delayed on specific sites. iv. Officers explained that the development proposals first came forward on the NIAB site in around 2007 just before the recession that greatly affected the construction industry. It has a large consortium of landowners, which also makes it more complicated to deliver development. Recently, the developer was affected financially by Brexit, and is now looking to other developers to bring forward the NIAB scheme. The Council’s New Neighbourhoods team is working with the developer and representatives of the consortium of landowners to deliver the site. A deed of variation to the existing Section 106 agreement is likely to be presented at Joint Development Control Committee early in 2017. This will address timing of delivery of some of the site’s infrastructure. The developer is still legally committed to providing the site-wide infrastructure. The intention is to start these works in May 2017. A written response to Member concerns regarding the planned bus route would be circulated to Members in due course. v. Explained that the 2006 Local Plan was the current plan and the emerging Local Plan would not be reported on through the Annual Monitoring Report until it was adopted. vi. Explained that a high level viability assessment was undertaken to inform the development of policies in the Local Plan and the Community Infrastructure Levy requirements. There was no requirement on the Council to undertake a detailed viability assessment of individual developers’ proposals at the plan-making stage. vii. Confirmed that the Design and Conservation panel was still in operation and met on a monthly basis, providing a forum for presentation of, briefing for, and expert advice on, major or otherwise significant development proposals (both at pre-application and application stages). The advice of the Panel forms part of reports on planning applications.; viii. Agreed to investigate and provide further information regarding paragraph 7.14 of the Annual Monitoring Report.. ix. Explained that all planning application reports were reviewed to identify the policies that were used. Work was ongoing regarding software that could capture the data more easily. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Development Plan Scrutiny Sub-Committee

Appendix A

Cambridge City Council Annual Monitoring Report 2016

December 2016 Appendix A List of Abbreviations

List of Abbreviations

Definition AAP Area Action Plan AMR Annual Monitoring Report ASHE Annual Survey of Hours and Earnings BfL Building for Life BfL12 Building for Life 12 BREEAM Building Research Establishment Environmental Assessment Method CATS Cambridge Area Transport Strategy CCC Cambridge City Council CHP Combined Heat & Power CIL Community Infrastructure Levy CiWs City Wildlife Site CLG Department for Communities and Local Government CPERC Cambridgeshire and Peterborough Environmental Records Centre CSR Cambridge Sub-Region DPD Development Plan Document dph Dwellings Per Hectare DPSSC Development Plan Sub Scrutiny Committee DWP Department of Work and Pensions EEDA East of England Development Agency EERA East of England Regional Assembly ELR Employment Land Review EU European Union GC3 Greater Cambridge Cycle City Project GCP Greater Cambridge Partnership GO-EAST The Government Office for the East of England Grade I Listed Buildings of exceptional interest, sometimes considered to be internationally important. Grade II Listing Buildings that are nationally important and are of special interest. Grade II* Listed Buildings that are particularly important and of more than special interest. ha Hectares HESA Higher Education Statistics Agency HMO Housing in Multiple Occupation HRA Habitats Regulation Assessment HSSA Housing Strategy Statistical Appendix IMD Index of Multiple Deprivation IPPG Informal Planning Policy Guidance JDCC Joint Development Control Committee JSGIC Joint Strategic Growth Implementation Committee JTF Joint Transport Forum LDF Local Development Framework LDS Local Development Scheme

Annual Monitoring Report 2015 Page | i Appendix A List of Abbreviations

Definition LEP Local Enterprise Partnership LNR Local Nature Reserve Local Plan Review The process of the creation of the Local Plan 2014, which will replace the Cambridge Local Plan 2006, once adopted. LTB Local Transport Bodies MW Megawatt NHB New Homes Bonus NHS National Health Service NIAB National Institute of Agricultural Botany NPPF National Planning Policy Framework ODPM Office of the Deputy Prime Minister (succeeded by the CLG) ONS Office for National Statistics PDCS Preliminary Draft Charging Schedule PDL Previously Developed Land PPS Planning Policy Statement R&D Research and Development RDA Regional Development Agency RGF Regional Growth Fund RSS Regional Spatial Strategy (also known as the East of England Plan) S106 Section 106 S29 Section 29 Committee SA Sustainability Appraisal SCDC South Cambridgeshire District Council SFRA Strategic Flood Risk Assessment SHLAA Strategic Housing Land Availability Assessment SHMA Strategic Housing Market Assessment SPD Supplementary Planning Document SSSI Site of Special Scientific Interest SuDs Sustainable Drainage Systems TIF Transport Innovation Fund TSCSC Transport Strategy for Cambridge and South Cambridgeshire

Annual Monitoring Report 2015 Page | ii Appendix A Executive Summary

Executive Summary Important Note:

Cambridge’s planning policy framework is in a transitional phase, with the 2006 adopted local plan (plan period of 1999 - 2016) being replaced by a new local plan, to be adopted, hopefully, in 2017 (plan period of 2011 - 2031).

This Annual Monitoring Report (AMR) makes reference to both plans, adopted (2006) and emerging (2014).

Where the Local Plan 2014 is referred to, it should be noted that this plan has been submitted to the Secretary of State for examination and may be subject to change prior to adoption. However, the council believes it is appropriate, for the purposes of this AMR, to cautiously make reference to this emerging plan as part of this monitoring and reporting document.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
201516 AMR: FINAL /71/DPSSCReport 4.9 MB DownloadRead as text
PDF
Annual Monitoring Report 2016Report 208 KB Download

At this meeting

Whole meeting

Who was there

7 of 7 attended
PS
Councillor Peter SarrisChair, present
NG
Councillor Nigel GawthropeVice-Chair, present
NA
Councillor Nicholas AveryCommittee Member, present
DB
Councillor Dave BaigentCommittee Member, apologies, sent representative
TB
Councillor Tim BickCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present
MS
Councillor Mike SargeantReserve, present as substitute

On this subject at Cambridge

Search all
  1. Annual Monitoring Report 2016This decision
  2. Authority Monitoring Report 2023-24Agreed
  3. Greater Cambridge Authority Monitoring Report 2022-23Approved
  4. Authority Monitoring Report for Greater Cambridge 2021-2022Agreed
  5. Authority Monitoring Report 2020-21Agreed
  6. Cambridge City Council and South Cambridgeshire District Council - Authority Monitoring Report for Greater Cambridge 2019-2020Agreed

More from Cambridge Development Plan Scrutiny Sub-Committee

All decisions
MeetingDecisionOutcome
13 Feb 2018 Grafton Area of Major Change – Masterplan and Framework Supplementary Planning DocumentDecision The draft Cambridge Local Plan 2014: Proposed Submission (as amended) designates the area around Fitzroy Str... Approved Open
13 Feb 2018 Land North of Cherry Hinton Supplementary Planning DocumentDecision The draft Cambridge Local Plan 2014: Proposed Submission (as amended) allocates Land North of Cherry Hinton ... Approved Open
5 Dec 2017 Annual Monitoring Report 2017Decision The Council is required to produce an Annual Monitoring Report (AMR) on at least a yearly basis. The draft A... Agreed Open
12 Sep 2017 Draft Grafton Area of Major Change – Masterplan and Framework Supplementary Planning DocumentDecision The draft Cambridge Local Plan 2014: Proposed Submission (as amended) designated the area around Fitzroy Str... Agreed Open