Council Newbuild Redevelopment - 9-10A Ventress Close Scheme Approval

Approved Scrutiny 3 papers

Housing Scrutiny Committee approved this item on Tuesday 7 March 2017. Below is the council's own wording, with the papers it was decided on.

Item17/18/HSC

Resolved

Decision i. The report provided details of the proposal to redevelop the existing flats at 9-10a Ventress Close to provide up to 19 new homes. ii. The proposed redevelopment had indicative plans to deliver up to 19 No. new homes on the existing site, providing 1 and 2 bedroom apartments and 3 bedroom houses. iii. The report requested approval to a capital budget for the scheme based on the outlined appraisal assuming the mix stated above. iv. The appraisal suggests that all of the new properties can be delivered as part of the Council’s social rent programme. Decision of Executive Councillor for Housing i. Noted the indicative mix of the proposed scheme. ii. Approved the scheme capital budget of £4,153,000 detailed in the report to cover the construction cost of the scheme and professional fees and other costs. iii. Approved the commencement of Compulsory Purchase Order (CPO) proceedings on the remaining 2 Leaseholders at 9 and 9a Ventress Close should they be required. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Housing Development Officer. The Committee made the following comments in response to the report: i. Expressed concern regarding a potential compulsory purchase and hoped that this could be resolved amicably. ii. Noted that here were a number of infill projects appearing around Cambridge. iii. Such development inevitably changed neighbourhoods and the committee hoped that neighbours were being treated sympathetically. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Executive summary

This report provides details of the proposal to redevelop the existing flats at 9-10a Ventress Close to provide up to 19 new homes. The area currently consists of 4 No. 2 bedroom maisonettes and associated garden land to the rear. The initial proposal also includes some garden land from properties located on Godwin Way. Of the existing 4 No. maisonettes, two are occupied by Cambridge City Council tenants and two are leasehold, both currently vacant. Both leaseholders have been consulted on the council’s wish to purchase their properties and negotiations are ongoing at this time.

The proposed redevelopment has indicative plans to deliver up to 19 No. new homes on the existing site, providing 1 and 2 bedroom apartments and 3 bedroom houses.

The report requests approval to a capital budget for the scheme based on the outlined appraisal assuming the mix stated above.

The appraisal suggests that all of the new properties can be delivered as part of the Council’s social rent programme.

Report Page No: 1 2. Recommendations

The Executive Councillor is recommended to:

 Note the indicative mix of the proposed scheme.  Approve the scheme capital budget of £4,153,000 detailed in the report to cover the construction cost of the scheme and professional fees and other costs.  To commence Compulsory Purchase Order (CPO) proceedings on the remaining 2 Leaseholders at 9 and 9a Ventress Close should they be required

Background

The opportunity to redevelop the site was first reported to committee in June 2012 as part of the three year rolling programme. The redevelopment area currently consists of 4 maisonettes including associated garden land. It is proposed to include part of the rear gardens of properties on Godwin Way, subject to further discussion and negotiation.

The potential to redevelop this site was first highlighted in 2012 due to the condition of the properties and large garden areas to the rear that were over grown and under used at the time.

Ventress Close residents were first contacted in July 2012 and made aware that the Council was investigating the possibility of redevelopment. Residents have received frequent updates, the most recent being June 2016.

Appendix 1 shows the indicative layout of the scheme.

4. Implications

(a) Financial Implications

The capital budget required for the scheme is £4,153,000.

The scheme can be funded by

RTB Receipts £ 1,132,990 Devolution Grant £ 2,643,642 Reserves for reprovision of existing units £ 376,368 Report Page No: 2 The financial appraisal shows a pay-back period of 7 years (the benchmark is for schemes to pay-back up to 35 year).

The rents used in the financial appraisal are;

1 bed @ LHA £126.05 2 bed @ LHA £144.96 3 bed @ LHA £168.45

The total capital budget includes funding to acquire the leasehold properties and costs associated with supporting residents to find alternative accommodation.

As the scheme is still at the outline stage and will be subject to planning, the costs are indicative and presented as a maximum budget required to deliver the scheme. These costs have been calculated using recent build costs on similarly sized developments locally. Should fewer units be accommodated on the site due to planning guidance, the costs for delivery will be reduced accordingly.

The Housing Revenue Account (HRA) Business Plan already allows for the spending of Right to Buy Receipts and Devolution monies on the net gain in units, therefore this scheme can be funded despite the current major national housing policy and legislative and changes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Council Newbuild Redevelopment: 9-10A Ventress Close Scheme ApprovalReport 149 KB DownloadRead as text
PDF
Project Appraisal Jan 2017 /18/HSCReport 524 KB Download
PDF
Ventress Close Option 2.0 Jan 17 /18/HSCReport 267 KB Download

At this meeting

Whole meeting

Who was there

8 of 14 attended
MT
Councillor Mike Todd-JonesChair, present
GB
Councillor Gerri BirdVice-Chair, present
NA
Councillor Nicholas Avery Lib Dem SpokesCommittee Member, present
NG
Councillor Nigel GawthropeCommittee Member, present
MH
Councillor Marie-Louise Holland Independent/Green Group SpokesCommittee Member, present
RM
Councillor Rosy MooreCommittee Member, present
JP
Councillor Jennifer Page-CroftCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present
LA
Lulu Agate Tenant RepresentativeCo-Optee, expected
DB
Diane Best Leaseholder RepresentativeCo-Optee, expected
KH
Kay Harris Tenant RepresentativeCo-Optee, expected
JM
John Marais Tenant RepresentativeCo-Optee, expected

All 14 on the meeting page

On this subject at Cambridge

Search all
  1. Council Newbuild Redevelopment - 9-10A Ventress Close Scheme ApprovalThis decision
  2. Council Newbuild Redevelopment - 9-28 Anstey Way Scheme ApprovalApproved

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies