Development Plan Scrutiny Sub-Committee, Wednesday 22 March 2017 at 4.30pm

Housing White Paper - Consultation Response to Government

Agreed Scrutiny 3 papers

Development Plan Scrutiny Sub-Committee agreed this item on Wednesday 22 March 2017. Below is the council's own wording, with the papers it was decided on.

Item16/84/DPSSC

Resolved

Decision of Executive Councillor for Planning Policy and Transport · To agree the comments set out in the consultation response attached to the officer report and that these are submitted to the Government as Cambridge City and South Cambridgeshire District Councils’ formal response to the consultation. · To agree that any subsequent changes to the consultation response as a result of the South Cambridgeshire District Planning Portfolio Holder meeting be agreed with the Executive Councillor for Planning Policy and Transport, Chair and Spokes prior to submission. Reasons for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Planning Policy and Economic Development Officer. The Committee made the following comments in response to the report: i. Highlighted that the demand for new housing was only met when local authorities were building them. Without the ability for local authorities to borrow and utilise receipts then it would be difficult to achieve the uplift in housing construction required in Cambridge to meet demand. ii. Drew attention to the implication that within the White Paper that Planning Authorities were responsible for the current status of the housing market when government policies such as Right to Buy and developers purchasing land but delaying development, a practice known as ‘land-banking’ had a far greater impact upon the housing market. iii. Clarified paragraph 3.3, bullet points 1 and 4 of the officer report, questioning whether the agreement of all local authorities was required in respect of the allocation of strategic sites and the level of residential allocations in local plans. iv. Questioned the amount of time and resources had been used in compiling the consultation response. The Planning Policy and Economic Development Officer said the following in response to Members questions: i. Confirmed that the Department for Communities and Local Government (DCLG) confirmed, following the publication of the report that bullet point 4 of the report referred to residential allocations and that DCLG had not clarified bullet point 1. ii. Explained that in compiling the consultation response, 15 officers across 2 Councils had input which took considerable time in reading the consultation and formulating responses. The Committee resolved 4 in favour, 0 against, with 2 abstentions to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Development Plan Scrutiny Sub-Committee

Appendix A

Appendix A: Draft Consultation Response to the Government’s Housing White Paper

1. Do you agree with the proposals to:

a) Make clear in the National Planning Policy Framework that the key strategic policies that each local planning authority should maintain are those set out currently at paragraph 156 of the Framework, with an additional requirement to plan for the allocations needed to deliver the area’s housing requirement?

The strategic priorities set out in paragraph 156 of the Framework require policies to provide:  the homes and jobs needed in the area;  the provision of retail, leisure and other commercial development;  the provision of infrastructure for transport, telecommunications, waste management, water supply, wastewater, flood risk and coastal change management, and the provision of minerals and energy (including heat);  the provision of health, security, community and cultural infrastructure and other local facilities; and  climate change mitigation and adaptation, conservation and enhancement of the natural and historic environment, including landscape.

As ‘lower tier’ authorities, a number of the strategic priorities listed are beyond the remit of the Councils’ areas of control, being the responsibility of the County Council (transport, minerals and waste). In addition, many organisations which are not local planning authorities have significant responsibilities in relation to these matters including public institutions, not-for-profit charities and privately owned companies working within a regulated market. The policy guidance in paragraph 156 can only be understood fully by reference to the definition of local planning authority in the glossary which clarifies that these strategic priorities will vary depending on the extent of their responsibilities. Given the increasing incidence of combined authorities and devolution deals, this definition may need further refinement.

Given that many of these organisations are not public bodies (NPPF paragraph 178), Cambridge City Council and South Cambridgeshire District Council would be supportive of requirements being applicable to all organisations responsible for the strategic oversight and provision of these strategic priorities to ensure their co-operation in a timely and constructive manner regarding their respective area of responsibility to support growth and the needs of local communities.

1 Appendix A

A proviso requiring full and timely responses to strategic matters would be welcomed by Cambridge City Council and South Cambridgeshire District Council. This condition should require any objections or serious concerns from a statutory consultee or an organisation with statutory responsibilities regarding any planning proposals during a consultation (external or internal) to be provided in a clear and timely manner; thereby allowing for the issue to be resolved or a strategy to be developed to overcome the concerns raised at an early stage of the planning process. Delays resulting from partial cooperation or late responses from statutory bodies can increase the cost of the plan-making process hindering the development of key policy areas.

b) Use regulations to allow Spatial Development Strategies to allocate strategic sites, where these strategies require unanimous agreement of the members of the combined authority?

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Response to the Housing White Paper Consultation DPSSC /84/DPSSCAppendix A 362 KB DownloadRead as text
PDF
Housing White Paper /84/DPSSCAppendix B 3.4 MB Download
PDF
Housing White Paper: Consultation Response to GovernmentReport 206 KB Withheld: personal details

At this meeting

Whole meeting

Who was there

6 of 7 attended
PS
Councillor Peter SarrisChair, present
NG
Councillor Nigel GawthropeVice-Chair, present
NA
Councillor Nicholas AveryCommittee Member, present
DB
Councillor Dave BaigentCommittee Member, apologies
TB
Councillor Tim Bick Lib Dem Spokes for Planning Policy & TransportCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present
MS
Councillor Mike SargeantReserve, present

More from Cambridge Development Plan Scrutiny Sub-Committee

All decisions
MeetingDecisionOutcome
13 Feb 2018 Grafton Area of Major Change – Masterplan and Framework Supplementary Planning DocumentDecision The draft Cambridge Local Plan 2014: Proposed Submission (as amended) designates the area around Fitzroy Str... Approved Open
13 Feb 2018 Land North of Cherry Hinton Supplementary Planning DocumentDecision The draft Cambridge Local Plan 2014: Proposed Submission (as amended) allocates Land North of Cherry Hinton ... Approved Open
5 Dec 2017 Annual Monitoring Report 2017Decision The Council is required to produce an Annual Monitoring Report (AMR) on at least a yearly basis. The draft A... Agreed Open
12 Sep 2017 Draft Grafton Area of Major Change – Masterplan and Framework Supplementary Planning DocumentDecision The draft Cambridge Local Plan 2014: Proposed Submission (as amended) designated the area around Fitzroy Str... Agreed Open
27 Jul 2017 Draft Land North of Cherry Hinton Supplementary Planning DocumentDecision The draft Cambridge Local Plan 2014: Proposed Submission (as amended) allocated Land North of Cherry Hinton ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies