Decision To consider the requests to carry forward funding arising from certain budget underspends into 2017/18 were identified. Decision of Executive Councillor for Environmental Services and City Centre Resolved to request that the Executive Councillor for Finance and Resources approved the following at the Strategy and Resources Scrutiny Committee on 3 July 2017. To carry forward requests of £394k capital resources from 2016/17 to 2017/18 to fund re-phased net capital spending, as detailed in Appendix D of the Officer’s report. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Principal Accountant (Services) The Officer’s report presented a summary of the 2016/17outturn position (actual income and expenditure) for services within the Environmental Services and City Centre portfolio, compared to the final budget for the year. The position for revenue and capital was reported and variances from budgets were highlighted, together with explanations. Requests to carry forward funding arising from certain budget underspends into 2017/18 were identified The Chair thanked the Officer for a comprehensive report. There were no further comments. The Committee resolved (unanimously) to endorse the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1This report presents, for the Environmental Services & City Centre Portfolio :
a) A summary of actual income and expenditure compared to the final budget for 2016/17 (outturn position)
b) Revenue and capital budget variances with explanations
c) Specific requests to carry forward funding available from budget underspends into 2017/18.
Recommendations
The Executive Councillor is recommended to request that the Executive Councillor for Finance and Resources, at the Strategy and Resources Scrutiny Committee on 3 July 2017, approves the following:
a) Carry forward requests of £394k capital resources from 2016/17 to 2017/18 to fund rephased net capital spending, as detailed in Appendix D.
Report Page No: 1 3. Background
Revenue Outturn
3.1The overall revenue budget outturn position for the Environment & Waste Portfolio is given in the table below. Detail, by service grouping, is presented in Appendix A.
2015/16 Environmental Services & City Centre 2016/17 % Final £’000 Portfolio £’000 Budget Revenue Summary
7,823 Original Budget 4,249 97.9
96 Adjustment – Prior Year Carry Forwards 0 -
(7) Adjustment – Service Restructure Costs (20) (0.4)
0 Adjustment – Earmarked Reserves 0 -
5 Adjustment – Capital Charges 110 2.5
45 Adjustment – Central & Support 0 - reallocations
0 Other Adjustments 0 -
7,962 Final Budget 4,339 100.0
7,728 Outturn 4,511 103.9
(234) (Under) / Overspend for the year 172 3.9
0 Carry Forward Requests 0 0
(234) Resulting Variance 172 3.9
3.2Appendix A shows original and final budgets for the year (with the movements summarised in the above table) and compares the final budget with the outturn position for this Portfolio for 2016/17. The original revenue budget for 2016/17 was approved by the Executive Councillor for Environmental Services & City Centre (formerly Environment & Waste) on 12 January 2016.
3.3Appendix B provides explanations of the main variances.
3.4Appendix C lists revenue carry forward requests for which there are none for this portfolio.
Report Page No: 2 Capital Outturn
3.5The overall capital budget outturn position for the Environmental Services & City Centre Portfolio is given in the table below. Appendix D shows the outturn position by scheme and programme with explanations of variances.
2015/16 Environmental Services & City Centre 2016/17 % Final £’000 Portfolio £’000 Budget Capital Summary
1,566 Final Budget 1,140 100.0
1,186 Outturn 739 64.8
(380) Variation - (Under)/Overspend for the (401) (35.2) year
418 Rephasing Requests 394 34.6
38 Variance (7) (1.8)
4. Implications
4.1The net variance from the final budget (see above), would result in an increased use of General Fund reserves of £172k.
4.2A decision not to approve a carry forward request may impact on officers’ ability to deliver the service or scheme in question and this could have staffing, equality and poverty, environmental, procurement, consultation and communication and/or community safety implications.
Background papers
Closedown Working Files 2016/17 Directors’ Variance Explanations – March 2017 Capital Monitoring Reports – March 2017 Budgetary Control Reports to 31 March 2017
6. Inspection of papers
To inspect the background papers or if you have a query on the report please contact:
Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.