Strategy and Resources Scrutiny Committee agreed this item on Monday 22 January 2018. Below is the council's own wording, with the papers it was decided on.

Item18/12/SR

Resolved

Decision The report outlined that a decision was needed to allow the Cambridge Junction capital project to move to the next stage. A Joint Project Board had been formed between the Council and Cambridge Junction to facilitate agreement of project drivers and outcomes. The report considered a high level feasibility and detailed options assessment carried out by external consultants. As the Council owned the freehold of the site, officers also considered the wider property issues and opportunities provided by any redevelopment scheme. An arts and cultural infrastructure audit had been commissioned in order to provide an evidence base of existing and future needs for professional cultural infrastructure, and to provide underpinning evidence for an options assessment. The options assessment looked specifically at Cambridge Junction assessed a range of options from ‘do nothing’ through to ‘complete redevelopment of the site’. Decision of Executive Councillor for Strategy and Transformation: i. Noted the findings from the Arts and Cultural Infrastructure Audit. ii. Noted the findings of the options assessment work. iii. Approved progression to a detailed study on Option 3 – a partial redevelopment - as the preferred recommendation for redevelopment of Cambridge Junction. iv. The detailed study on option 3 would be considered within a framework of an outline site wide masterplan to ensure that: a) The full impacts of the phase 1 study on the wider freehold site were taken into account. b) Alternative options were considered at this stage should option 3 be undeliverable. c) The Council was able to ensure best value optimisation of its assets on the site. d) The work would support a potential first stage capital bid to Arts Council England including completion of more detailed work up to RIBA stage 1. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Culture and Community Manager. The Committee made the following comments in response to the report: i. Asked what financial consideration had been given to the Junction in terms of bridging the gap caused by redevelopment. ii. Welcomed the opportunity of redevelopment. Referred to section 3.6 of the report and asked if the audit had been subject to analysis. The Culture and Community Manager and Head of Property Services said the following in response to Members’ questions: i. Confirmed that the Junction had stable finances, they had been working closely with the Arts Council who were their biggest funder so they were confident that the redevelopment would make a positive and sustainable impact on their finances. ii. Stated that the proposal wasn’t just to increase performance capacity, there was high demand for rehearsal/education space and start up facilities. The Executive Councillor for Strategy and Transformation confirmed that discussions had been ongoing for 18 months; this was a positive opportunity which could lead to further development in Junction 1 in the future. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Item CAMBRIDGE JUNCTION CAPITAL PROJECT

To: Councillor Lewis Herbert, Leader and Executive Councillor for Strategy and Transformation Committee: 22 January 2018, Strategy and Resources Scrutiny Committee Report by: Jane Wilson Tel: 01223 - 457860 Email: [email protected] Wards affected: Abbey, Arbury, Castle, Cherry Hinton, Coleridge, East Chesterton, King's Hedges, Market, Newnham, Petersfield, Queen Edith's, Romsey, Trumpington, West Chesterton

NOT FOR PUBLICATION: The appendix relates to an item during which the public is likely to be excluded from the meeting by virtue of paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972.

Non Key Decision

1. Executive Summary 1.1 This decision is needed to allow the Cambridge Junction capital project to move to the next stage. 1.2 A Joint Project Board was formed between the Council and Cambridge Junction which facilitated agreement of project drivers and outcomes, and considered a high level feasibility and detailed options assessment carried out by external consultants. 1.3 As the Council is owner of the freehold of the site, officers have also considered the wider property issues and opportunities provided by any redevelopment scheme.

Report page no. 1 Agenda page no. 1.4 An arts and cultural infrastructure audit was commissioned in order to provide an evidence base of existing and future needs for professional cultural infrastructure, and to provide underpinning evidence for an options assessment. 1.5 An options assessment was carried out looking specifically at Cambridge Junction, which assessed a range of options from ‘do nothing’ through to ‘complete redevelopment of the site’.

2. Recommendations The Executive Councillor is recommended to: 2.1 Note the findings from the Arts and Cultural Infrastructure Audit. 2.2 Note the findings of the options assessment work. 2.3 Approve progression to a detailed study on Option 3 – a partial redevelopment - as the preferred recommendation for redevelopment of Cambridge Junction. 2.4 The detailed study on option 3 will be considered within a framework of an outline site wide masterplan options assessment to ensure that: a) The full impacts of the phase 1 study on the wider freehold site are taken into account. b) Outline alternative options are considered at this stage should option 3 be undeliverable. c) The Council is able to ensure best value optimization of its assets on the site. d) The work will support a potential first stage capital bid to Arts Council England and include completion of more detailed work up to RIBA stage 1.

3. Background 3.1 Cambridge Junction is a major arts and cultural venue located on the old Cattle market site in Cambridge. The original building, built by the Council and opened in 1990, consisted of an 850 capacity (standing) venue, used predominantly for music, comedy and clubs (known as J1). In 2005 the building was extended to include: one 220 capacity (seated) venue used for contemporary theatre (J2); one rehearsal/community space (J3); and office space. There are two separate entrances, one for

Report page no. 2 Agenda page no. J1 and one for J2/J3, and there is no public internal connection between J1 and J2/J3.

3.2The freehold of the building and the site are both owned by Cambridge City Council, with the venue operated by Junction CDC, a charity which has a lease until 2030, under a peppercorn rent arrangement (agreed as match funding for an earlier capital development).

3.3A joint project board was formed in January 2017 to examine the need and options for a major capital development.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cambridge Junction Capital ProjectReport 426 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
SB
Councillor Sophie BarnettChair, present
DB
Councillor Dave BaigentVice-Chair, present
TB
Councillor Tim Bick Lib Dem Spokes for Strategy & TransformationCommittee Member, present
RC
Councillor Rod Cantrill Lib Dem Spokes for Finance and ResourcesCommittee Member, present
PS
Councillor Peter SarrisCommittee Member, apologies, sent representative
AS
Councillor Ann SinnottCommittee Member, present
MA
Councillor Margery AbbottReserve, present as substitute

On this subject at Cambridge

Search all
  1. Cambridge Junction Capital ProjectThis decision
  2. S/0467/13/CM Chesterton Rail Freight Sidings, Chesterton Junction, Cowley Road, Cambridge, CB4 0DLDecided

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open