Hobson’s Brook Corridor 10 Year Vision

Refused Scrutiny 2 papers

Community Services Scrutiny Committee refused this item on Thursday 15 March 2018. Below is the council's own wording, with the papers it was decided on.

Item18/16/Comm

Resolved

Decision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring at Nine Wells on Cambridge’s southern fringe and running northwards in to the city centre. (covering the period 2018 – 2028) describes the nature and character of the corridor, defines various pressures faced and outlines management and maintenance priorities over the next 10 years; based upon an assessment of historical records and more recent data gathered. It is intended to guide activities which focus on water quality improvements, ecological enhancements, maintenance and restoration work along with community engagement activities within the corridor. Decision of Executive Councillor for Streets and Open Spaces i. Endorsed the Hobson’s Brook Corridor 10 Year Vision as an evidence base to inform planning policy and decisions, and to influence management and maintenance priorities. ii. Supported the establishment of a delivery action plan setting out future investment priorities in order to assist obtaining funded as needed. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Sustainable Drainage Engineer . The Committee made the following comments in response to the report: i. There was a disappointing response rate to the Hobson Conduit public consultation. ii. Queried if land owners near the Conduit, particularly the University of Cambridge, were disengaged. If so, would this cause difficulties regarding consent and funding for future work? iii. Councillor O’Connell offered to help engage the University of Cambridge in the Hobson Conduit public consultation process in her capacity as Ward Councillor. iv. Historically the Market Square fountain was an important feature as the end of the Conduit and a source of drinking water. Requested this be brought back into the Vision document, possibly as a way to reduce the number of plastic drinking bottles in the city. v. Raised concern about the number of pollutants and chemicals that could affect the Conduit and local water supplies through surface run off from agricultural and industrial areas in/around/bordering the city. The Sustainable Drainage Engineer said the following in response to Members’ questions: i. The University of Cambridge were directly engaged through stakeholder consultation. Further engagement work would continue in future. ii. It was unclear if future problems would arise from stakeholder disengagement. iii. The Vision document was not a contentious document, which may explain the low consultation response rate. The Conduit was seen as an asset to the city. iv. The majority (70%) of consultees were involved in earlier stakeholder engagement work ie landowners along the Conduit corridor such as the University of Cambridge. v. There was greater public interest in the visible parts of the Conduit (eg the open brook) than underground sections. Both were equally important but the open sections had a higher profile as a public amenity. Funding would be easier to target for the open sections. vi. Various water quality tests were undertaken over time to ensure there were no adverse impacts from local farms or (new) developments. There were no issues to report at present eg floating pennywort or pesticide pollution. Part of the checks were to measure and collate what was occurring with the brook ie what was in/on it and whether this was good or bad. vii. Officers engaged with Pemberton Farms who were major land owners on the south of the city. Land use and ownership around the brook was changing over time. viii. Local wildlife charities were engaged in the consultation rather than national ones as they were seen as more appropriate. The Committee resolved by 6 votes to 0 to endorse the recommendations. Councillors Abbott and Barnett did not vote due to their declarations. The Executive Councillor approved the recommendations. She undertook to raise the suggestion of reconnecting the Market Square fountain to Hobson’s Conduit (as a potential drinking fountain) with the Planning Department and Executive Councillor for Environmental Services and City Centre. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Community Services Scrutiny Committee

APPENDIX A

Hobson’s Brook Corridor 10 Year Vision – Public Consultation Report

1. Purpose To outline the feedback from the consultation and analyse the responses giving an indication and recommendation of the amendments and or additions required for the Hobson’s Brook Corridor 10 Year Vision.

2. Consultation Method A number of media options were undertaken to encourage and ensure the general public were able to interact and give feedback on the ‘Vision’. Key stakeholders were kept up to date on the consultation. The consultation ran from Wednesday 22nd November until Tuesday 9th January 2018.

a) Electronic consultation leaflet made available on Cambridge City Council consultation webpage (01/11/17).

3. Responses

Wider Public Consultation, November/December 2017 From the various consultation media and response to the wider public consultation there were 20 responses received. All but two of these used the online consultation questions:

Question 1 responses To the question asking, ‘Are you responding as’ there were 18 responses received as below: - As a resident of Cambridge - 11 people or 61% of the respondents indicated they were a resident of Cambridge - As a local resident to Hobson’s Brook – 4 people or 22% of the respondents said they were a local resident to Hobson’s Brook. - Responding on behalf of an organisation – 3 person or 17% of the respondents said they were responding on behalf of an organisation - Organisations stated included - Highways Cambridgeshire County Council, Trumpington Residents' Association and Bentley and Newton Roads Residents Association (BENERA).

APPENDIX B - Proposed Modifications Table Are you responding as...? (Please select the option below that most closely represents you) 70.00% 60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00% As a resident of As a local resident Responding on Other Cambridge to Hobson's Brook behalf of an organisation

Question 2 responses To the question asking, ‘Please tell us whether the ‘Vision’ document was easy or difficult to understand.’ there were 16 responses received:

- 10 or 63% of respondents said the whole document was easy to understand - 5 or 31% of respondents said most of the document was easy to understand - 0 respondents said some of the document was easy to understand - 1 or 6% of respondents said the document was not at all easy to understand

Comments on this question when asked to, ‘tell us what, if anything, you didn’t understand in the ‘Vision’ document’ included,

1. some technical details in the tables The evasive recording of legal issues concerning ownership and responsibility The status of the Hobson Conduit Conservators, and their effectiveness, which is not transparent BENERA welcomes those aspects of the document which will serve to archive the current extremely fragile situation of the watercourse corridor. It is not easy to understand how the Vision will be adequately funded 2. What, and precisely where, is Addenbrookes Ditch? What is CamEO?

Appendix A – Hobson’s Brook Corridor 10 Year Vision – Public Consultation Report Please tell us whether the 'Vision' document was easy or difficult to understand. 70.00%

60.00%

50.00%

40.00%

30.00%

20.00%

10.00%

0.00% The whole document Most of the Some of the The document was was easy to document was easy document was easy not at all easy to understand to understand to understand understand

Question 3 responses To the question asking, ‘overall do you support the 10 year ‘Vision’ for Hobson’s Brook Corridor.’ there were 17 responses received:

- 11 or 65% of respondents said they strongly supported the ‘Vision’ - 6 or 35% of respondents said they tended to support the ‘Vision’ - No respondents said they tended not to support the ‘Vision’ - No respondents said they strongly do not to support the ‘Vision’

Overall do you support the 10 year 'Vision' for Hobson's Brook Corridor? 70.00%

60.00%

50.00%

40.00%

30.00%

20.00%

10.00%

0.00% Strongly support Tend to support Tend not to support Strongly do not support

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
10 Year Vision Committee Report Appendices /16/CommReport 966 KB DownloadRead as text
PDF
Hobson’s Brook Corridor 10 Year VisionReport 313 KB Download

At this meeting

Whole meeting

Who was there

8 of 9 attended
DR
Councillor Dan RatcliffeChair, present
AS
Councillor Ann SinnottVice-Chair, present
MA
Councillor Margery AbbottCommittee Member, present
YA
Councillor Ysanne Austin Lib Dem Spokes for Streets and Open SpacesCommittee Member, present
SB
Councillor Sophie BarnettCommittee Member, present
GB
Councillor Gerri BirdCommittee Member, present
OG
Councillor Oscar Gillespie Independent/Green Spokes for Streets and Open Spaces / CommunitiesCommittee Member, present
ZO
Councillor Zoe O'Connell Lib Dem Spokes for CommunitiesCommittee Member, present
AM
Alistair McCluskeyOfficer, expected

On this subject at Cambridge

Search all
  1. Hobson’s Brook Corridor 10 Year VisionThis decision
  2. Footbridge across Hobson's BrookDecided

More from Cambridge Community Services Scrutiny Committee

All decisions
MeetingDecisionOutcome
15 Mar 2018 Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover... Approved Open
15 Mar 2018 Annual Update on the Work of our Strategic Partnerships - Communities PortfolioDecision The Officer’s report provides an update on the work of the Health and Wellbeing Board and Children’s Trust a... Agreed Open
18 Jan 2018 Policy for Use of Events on Parks and Open SpaceDecision The hosting of events on city parks and open spaces had become increasingly popular with both local and nati... Approved Open
18 Jan 2018 S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ... Noted Open
18 Jan 2018 Streets and Open Spaces Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision The report detailed the budget proposals relating to the Streets and Opens Spaces portfolio that are include... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies