Resolved (by 7 votes to 1) to grant the application for planning permission in accordance with the officer recommendation, for the reasons set out in the officer report, and subject to the conditions recommended by the officers plus an additional condition requiring a high level window to be incorporated into the bedroom of unit 8. 21 Prior to the commencement of above ground works a plan shall be submitted for written agreement by the Local Planning Authority for the inclusion of a high level or roof window to serve the bedroom of plot 8. Works shall thereafter be in accordance with the approved details. Reason: To ensure that plot 8 would provide a high quality living environment for future occupiers (Cambridge Local Plan policies 3/7 and 3/10).
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Application 18/0190/FUL Agenda Number Item Date Received 8th February 2018 Officer Mairead O'Sullivan Target Date 5th April 2018 Ward Romsey Site 307 Mill Road Cambridge CB1 3DF Proposal Demolition of former retail unit, associated workshop, storage and office and erection of 9 flats. Applicant [name removed] c/o Agent
SUMMARY The development accords with the Development Plan for the following reasons:
- The revised proposal is considered to preserve and enhance the character and appearance of the Conservation Area
- The revised proposal is considered to provide a high quality living environment for future occupiers.
RECOMMENDATI APPROVAL ON
1.0SITE DESCRIPTION/AREA CONTEXT
1.1The site lies on the north western end of Mill Road. The area is currently subject to much redevelopment. The site to the west, 305 Mill Road is also currently being developed under permission ref 16/1213/FUL. The site to the east is being redeveloped as the Mill Road Mosque; works have also commenced on site here. The application site has an extant consent to redevelop the site. Some conditions have been discharged and development has commenced on site. 1.2 The site is located within the Mill Road Conservation Area but the buildings on the site are not identified as of any merit. To the west of the site and in front of the allocated site is a grass verge which contains three protected (Tree Preservation Order) Birch trees with shrub planting.
2.0THE PROPOSAL
2.1The application seeks full planning permission for the demolition of the former retail unit, workshop, storage and office on site and construction of 9 flats.
2.2The application has been amended since submission to overcome concerns regarding the impact of the building on the Conservation Area and amenity for future occupiers of the flats
2.3The application follows on from a previously approved scheme on site. The revised plans are similar in design and scale to the previous approval. The nature of the units has changed. The previous consent was for 7 flats (3 x 1 bed & 4 x 2 Bed). The current application is for 9 flats (3 x 1 bed 1 person, 3 x 1 bed 2 person and 3 x 2 bed 3 person dwelling).
3.0SITE HISTORY
Reference Description Outcome 18/0032/S73 S73 to vary conditions 3 and 4 of Permitted ref: 15/1859/FUL (Demolition of an existing retail unit, associated workshop, storage and office and erection of 7 flats, together with associated access, landscaping, drainage and infrastructure works) to change the trigger for submission of details to allow demolition to begin before details of the preliminary contamination assessment, site investigation report and remediation strategy are required to be submitted. 15/1859/FU Demolition of an existing retail Permitted L unit, associated workshop, storage and office and erection of 7 flats, together with associated access, landscaping, drainage and infrastructure works
4.0PUBLICITY
4.1Advertisement: Yes Adjoining Owners: Yes Site Notice Displayed: Yes
5.0POLICY
5.1See Appendix 1 for full details of Central Government Guidance, Cambridge Local Plan 2006 policies, Supplementary Planning Documents and Material Considerations.
5.2Relevant Development Plan policies
PLAN POLICY NUMBER
Cambridge Local 3/1 3/4 3/7 3/11 3/12 Plan 2006 4/11
5/1
8/2 8/6 8/10 10/1
5.3Relevant Central Government Guidance, Supplementary Planning Documents and Material Considerations
Central National Planning Policy Framework Government March 2012 Guidance National Planning Policy Framework – Planning Practice Guidance March 2014 Circular 11/95 (Annex A)
Technical housing standards – nationally described space standard – published by Department of Communities and Local Government March 2015 (material consideration)
Supplementary Sustainable Design and Construction (May Planning 2007) Guidance Cambridgeshire and Peterborough Waste Partnership (RECAP): Waste Management Design Guide Supplementary Planning Document (February 2012)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.