Swimming Pool Investment Strategy

Approved Scrutiny 2 papers

Environment and Community Scrutiny Committee approved this item on Thursday 28 June 2018. Below is the council's own wording, with the papers it was decided on.

Item18/16/E&C

Resolved

Decision To adopt the proposed swimming pool investment strategy to allow for the use and allocation of collected Developer S106 Contributions specifically for swimming to be assigned to projects to improve access and upgrade swimming facilities around the city. To approve the release of feasibility funds to be able to do investigatory and feasibility works to look at a range of investment options to improve access and facilities at Jesus Green Lido. Decision of Executive Councillor for Communities i. Adopted the proposed Swimming Investment Strategy in Appendix 1 to be able to allocate existing and future S106 developer contributions for swimming for the improvement of swimming opportunities across the City. ii. Approved the use of up to £45,000 from the feasibility fund to do more detailed survey works and options appraisals for the development of Jesus Green Lido. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Community, Sport & Recreation Manager. The Committee made the following comments in response to the report: i. Queried if it were practicable and reasonable to heat an outdoor lido. ii. Queried how pool opening hours could be extended. iii. Queried if there were sufficient numbers of pools to meet demand; and if those in place were of sufficient length ie was a 50m pool required? The Community, Sport & Recreation Manager said the following in response to Members’ questions: i. The feasibility strategy would look at options to extend opening hours including those at Jesus Green Lido. ii. Operational details about swimming pools could be given to committee post meeting and offered to take councillors on a tour of pools such as the lido where queries could be answered eg practicalities of heating the lido. The Executive Councillor added there were other heated lidos in the country. iii. The City Council had a contract with GLL which set swimming pool opening hours. iv. City Council Officers were in regular contact with the Friends of Jesus Green Lido about the pool. The Executive Councillor added the Friends of Jesus Green could comment on pool matters during the feasibility study consultation period. v. Future swimming pool demand models took into account: · Public and private pools. · Walk/cycle/drive transport links to them, and their anticipated impact was modelled. · A 50m pool was not necessarily required. vi. Swimming pools in the City were reaching (user) capacity. Officers were looking to see if the university pool proposal could be opened up to the public or club use in future to free up capacity in other city council managed ones. vii. There were designated parts of the River Cam that can be used for swimming (by confident swimmers) and other water based activities. The City Council generally discourages people from swimming in the Cam for various safety reasons. viii. The Appendix in the Officer’s report showed how s106 funding could be spent and some projects could be delivered before the first deadline in 2023. The Committee resolved by 9 votes to 0 to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment and Community Scrutiny Committee

Item : SWIMMING INVESTMENT STRATEGY

To: Councillor Richard Johnson, Executive Councillor for Communities Environment & Community Scrutiny Committee 28/06/2018 Report by: Ian Ross, Tel: 01223 - 457000 Email: [email protected] Wards affected: All wards

Not a Key Decision

1. Executive Summary 1.1 To adopt the proposed swimming pool investment strategy to allow for the use and allocation of collected Developer S106 Contributions specifically for swimming to be assigned to projects to improve access and upgrade swimming facilities around the city. 1.2 To approve the release of feasibility funds to be able to do investigatory and feasibility works to look at a range of investment options to improve access and facilities at Jesus Green Lido.

2. Recommendations The Executive Councillor is recommended to: 2.1 Adopt the proposed Swimming Investment Strategy in Appendix 1 to be able to allocate existing and future S106 developer contributions for swimming for the improvement of swimming opportunities across the City. 2.2 Approve the use of up to £45,000 from the feasibility fund to do more detailed survey works and options appraisals for the development of Jesus Green Lido.

Report page no. 1 Agenda page no. 3. Background 3.1 The City has been collecting S106 Developer Contributions specifically for swimming from the major growth sites for many years. This “pool” of money now equates to agreed contributions of around £910,000 with a further sum of around £145,000 yet to be agreed for Land North of Cherry Hinton. This could provide a fund of around £1,055,000 specifically for investment in swimming around the city. 3.2 Of this funding the City Council has already been paid over £517,000 with the outstanding balances due in from major growth areas totaling in excess of £390,000 to be paid over the coming 5 years. 3.3 The City Council along with South Cambridgeshire District commissioned joint authority strategies for Playing Pitches and Indoor Sports facilities both of which were completed and adopted in June 2016. 3.4 This strategic work was led by Leisure Consultants and Recreation and Planning officers from both Councils. The work was also informed by local representatives of National Governing bodies, and Sport England officers, along with comprehensive independent site visits and assessments of all pitches and leisure facilities in both Councils districts whether council owned and run, or privately owned and run. 3.5 The Sport England Facilities Planning model was used to assess current demand and future needs accounting for growth and new populations with the City, fringe sites and beyond for swimming and sports hall provision. 3.6 The modelling for swimming pools across the districts identified 11 swimming facilities of which only 4 are available for public pay and play usage. (Abbey and Parkside Pools, in the City and Impington and, Melbourne College Pools in South Cambs). 3.7 Whilst there are other pools available they are either too small (under 20m in length – Kings Hedges), a non-standard pool length (Chesterton Sports Centre pool), or only open on a seasonal basis (Jesus Green Lido), they are therefore not included in the Sport England facility modelling for assessing water space. 3.8 Usage analysis also showed that Parkside Pools was operating at 98% capacity with Abbey at 62% capacity. Sport England comfort levels are anything below 70%, anything above this is considered to be overcrowded and has a detrimental swimming experience for the user.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pools Strategy /16/E&CAppendix 1 307 KB Download
PDF
Swimming Pool Investment StrategyReport 313 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 13 attended
MS
Councillor Martin SmartChair, present
GB
Councillor Gerri BirdVice-Chair, present
SB
Councillor Sophie BarnettCommittee Member, present
OG
Councillor Oscar Gillespie Independent / Green spokes for Communities, Environmental Services, Streets and Open SpacesCommittee Member, present
AM
Councillor Anthony Martinelli Lib Dem Spokes for Environmental Services and City CentreCommittee Member, present
NM
Councillor Nicky MasseyCommittee Member, present
CM
Councillor Colin McGerty Lib Dem Spokes for Streets and Open SpacesCommittee Member, present
ZO
Councillor Zoe O'Connell Lib Dem Spokes for CommunitiesCommittee Member, present
PS
Councillor Patrick SheilCommittee Member, present
BT
Councillor Baiju ThittalaCommittee Member, present
RJ
Councillor Richard JohnsonExecutive Councillor, present
RM
Councillor Rosy MooreExecutive Councillor, present

All 13 on the meeting page

More from Cambridge Environment and Community Scrutiny Committee

All decisions
MeetingDecisionOutcome
20 Mar 2025 Folk FestivalDecision The Officer’s report was presented following a request for a special meeting of Environment and Community Sc... Noted Open
20 Mar 2025 Market Traders Terms and ConditionsDecision The Officer’s report provided details of the proposed changes to Cambridge General Market (General Market) T... Approved Open
20 Mar 2025 Weekly Food Waste CollectionsDecision The Environment Act 2021 required all councils to align their household waste and recycling services with ne... Approved Open
20 Mar 2025 Leisure Management Contract 2026Decision This report was being presented to update Members and conclude the on ongoing work to review the Council’s l... Agreed Open
20 Mar 2025 Equalities Objectives for 2025/26Decision The Officer’s report sought approval of new equalities objectives applicable from 1 April 2025 to 31 March 2... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies