Resolved (by 4 votes to 4 with 2 abstentions and on the Chair’s casting vote ) to grant the application for planning permission in accordance with the officer recommendation, for the reasons set out in the officer report, and subject to the conditions recommended by the officers.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Application 18/0758/FUL Agenda Number Item Date Received 18th May 2018 Officer Lewis Tomlinson Target Date 13th July 2018 Ward Queen Ediths Site 57 Hartington Grove Proposal Conversion of existing first floor and ground floor HMO (7 occupants) into 5 self-contained bedsits, a two storey rear extension and a side dormer. Applicant [name removed] c/o agent
SUMMARY The development accords with the Development Plan for the following reasons:
The design and scale of the development would not have an adverse impact upon the surrounding area.
The proposed development would not have any adverse impact on the residential amenity of adjoining neighbours and would provide acceptable living conditions for the future occupiers.
RECOMMENDATION APPROVAL
1.0SITE DESCRIPTION/AREA CONTEXT
1.1No.57 Hartington Grove is on the northern side of Hartington Grove and is a detached two storey dwelling. There is a right of way to west of the property to provide access to a garage for a neighbouring property. To the east of the property is the access gate to the rear garden of No.57. The surrounding area is predominantly residential and characterised by two storey properties of different design and built form. The site falls within the controlled parking zone. 1.2 The existing building comprises of two HMO’s: Ground floor: 4 bed HMO First Floor: 3 bed HMO
2.0THE PROPOSAL
2.1The proposal is for a change of use of the two existing HMO’s to five 1 bed studio flats, a two storey rear extension and a side dormer. The proposal would retain the existing 3 car parking spaces and provide 6 cycle parking spaces.
2.2A similar scheme was refused under planning application 14/0848/FUL and dismissed at appeal under reference (APP/Q0505/W/16/3150434). This application is a re- submission following the appeal decision. The appeal was dismissed for the following reasons: Storage of cycles/bin to the front of the property caused harm to the character and appearance of the area Impact upon privacy/outlook of unit 3 as all windows face west onto the right of way Sense of enclosure to unit 2 due to the hedge being less than 2m in depth
2.3The application is accompanied by the following supporting information: Planning Statement Drawings
2.4Amended plans have been received which show the following revisions: Bin storage moved from access way to the rear garden Gate to the rear garden widened from 0.8m to 1m Proposed dormer serving unit 4 obscure glazed Reduction from six to five units, to increase the internal size of the two first floor units. Guttering has been amended to be within the boundary of the site
3.0SITE HISTORY
Reference Description Outcome 13/1255/FUL Conversion of existing Refused property into 9 self-contained bedsits 14/0848/FUL Conversion of existing first Refused/Appeal floor and ground floor HMO (7 dismissed occupants) into 6 self- contained bedsits
4.0PUBLICITY
4.1Advertisement: No Adjoining Owners: Yes Site Notice Displayed: No
5.0POLICY
5.1Relevant Development Plan policies
PLAN POLICY NUMBER
Cambridge Local 3/1 3/4 3/6 3/7 3/8 3/11 3/14 Plan 2006 5/1
8/2 8/3 8/4 8/5 8/6 8/10
Cambridge Local 35, 50, 55, 56, 58, 82 Plan 2014: Proposed Submission, July 2013 (submitted March 2014), (as amended by the Inspectors' Main Modifications). Hereafter referred to as Cambridge Local Plan (2014).
5.2Relevant Central Government Guidance, Supplementary Planning Documents and Material Considerations
Central National Planning Policy Framework 2018 Government Guidance National Planning Policy Framework – Planning Practice Guidance March 2014 Circular 11/95 (Annex A)
Technical housing standards – nationally described space standard – published by Department of Communities and Local Government March 2015 (material consideration)
Supplementary Sustainable Design and Construction (May Planning 2007) Guidance Cambridgeshire and Peterborough Waste Partnership (RECAP): Waste Management Design Guide Supplementary Planning Document (February 2012)
Planning Obligation Strategy (March 2010)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.