CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cambridge City Council
Planning and Transport Scrutiny Committee, Tuesday 25 June 2019 at 5.30pm

2019 S106 Priority-Setting (Play Areas and Open Spaces)

Approved Planning 2 papers

Planning and Transport Scrutiny Committee approved this item on Tuesday 25 June 2019. Below is the council's own wording, with the papers it was decided on.

Item19/25/PnT

Resolved

i. to allocate S106 funding to the following projects, subject to business case approval (see Section 4 and Appendix A of the Officers report for project details). S106 funding types Project Play provision Informal open space N01 Logan’s Meadow: provide more benches and bins - £7.5k N02 Bramblefields local nature reserve: more planting - £7.5k N05 Arbury Court play area improvements (landscaping & equipment) £15k £15k N07 Jubilee Gardens: improved access, landscaping, planting and seating - £40k N08 Chestnut Grove Play Area: benches and bins - £7.5k E07 Robert May Close play area: new play equipment and the replacement of two park benches £5k £35k S01 Cherry Hinton Hall play area improvements: including accessible play equipment, plus landscaping £90k £60k S02 Holbrook Road play area improvements (additional equipment and extra bench) £46k £1k S03 Nightingale Avenue Rec Ground: new all-weather footpath between car park and community garden - £15k S05 Consort Way play area (Trumpington Meadows): boundary fencing - £30k WC1 Jesus Green ditch: landscaping and biodiversity improvements - £53k WC2 Jesus Green: new wildflower meadow - £18k WC3 Jesus Green: ecological/ educational space - £7k WC4 Jesus Green barbecue area (and associated signage) plus drinking water fountain - £12.5k WC5 Midsummer Common Community Orchard: drinking water fountain - £2.5k WC6 Sheep’s Green local nature reserve: biodiversity bank improvements at Mill Pond - £22k X01 Biodiversity enhancements (e.g. ‘Bee banks’) at parks in in East Chesterton, Coleridge, Trumpington & Market - £5k E01 Thorpe Way Rec Ground: new footpath £15k S04 Nightingale Avenue Rec community garden: accessible polytunnel £1.5k Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Development Manager . The Development Manager said the following in response to Members’ questions: i. The needs of elderly residents would be considered when benches were installed in Logan’s Meadow and other sites and benches with arms would be used where possible. ii. Wheelchair user’s needs would be taken into account when drinking water facilities were installed. iii. The budget allocation for the water fountain included wider costs such as officer time and any consultation work needed. iv. Confirmed that lighting costs had been removed from a number of projects as S106 funding could only be used for capital cost and not on-going maintenance or utilities charges. This could be reconsidered at a later date for other funding sources. v. Requests for litter bins that had been unsuccessful could be directed to alternative funding streams such as the next round of Environmental Improvement Projects. vi. Confirmed that the definition of Informal Open Spaces for S106 purposes related to soft landscaping. Public Realm funding might be available for hard surfaces areas. vii. Confirmed that the S106 pot was diminishing and that officers were endeavouring to make the most positive contribution with the reduced funds. Members were disappointed that the £50,000 Informal Open Spaces funding for Chesterton Recreation Ground was being withdrawn. Officer’s confirmed that the funding for this project was not time sensitive and suggested deleting this recommendation to allow further consultation work to be completed. The Committee unanimously resolved to delete recommendation ( i ) De-allocate £50,000 of informal open space S106 funding for previously prioritised project for a skate park at Chesterton Recreation Ground (see paragraph 3.9); The Committee unanimously resolved to endorse the recommendation (ii): to allocate S106 funding to the following projects, subject to business case approval (see Section 4 and Appendix A of the Officers report for project details). The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Planning and Transport Scrutiny Committee

Executive summary

1.1The Council uses S106 contributions paid by developers to mitigate the impact of developments on facilities and amenities in Cambridge. In line with the arrangements agreed by the Executive Councillor in March 2019, the Council has invited proposals for improving play areas and open spaces within the city as part of its 2019 S106 funding round. Thirty applications have been received and assessed against the S106 selection criteria. This report summarises those applications and assessments and makes 17 recommendations for S106 funding.

2. Recommendations The Executive Councillor is recommended to:

Report page no. 1 Agenda page no. i. De-allocate £50,000 of informal open space S106 funding for previously prioritised project for a skate park at Chesterton Recreation Ground (see paragraph 3.9); ii. Allocate S106 funding to the following projects, subject to business case approval (see Section 4 and Appendix A for project details).

S106 funding types Play Informal Project provision open space Logan’s Meadow: provide more N01 - £7.5k benches and bins Bramblefields local nature reserve: N02 - £7.5k more planting Arbury Court play area improvements N05 £15k £15k (landscaping & equipment) Jubilee Gardens: improved access, N07 - £40k landscaping, planting and seating Chestnut Grove Play Area: benches N08 - £7.5k and bins Robert May Close play area: new E07 play equipment and the replacement £5k £35k of two park benches Cherry Hinton Hall play area S01 improvements: including accessible £90k £60k play equipment, plus landscaping Holbrook Road play area S02 improvements (additional equipment £46k £1k and extra bench) Nightingale Avenue Rec Ground: new S03 all-weather footpath between car park - £15k and community garden Consort Way play area (Trumpington S05 - £30k Meadows): boundary fencing Jesus Green ditch: landscaping and WC1 - £53k biodiversity improvements WC2 Jesus Green: new wildflower meadow - £18k

Report page no. 2 Agenda page no. S106 funding types Play Informal Project provision open space Jesus Green: ecological/ educational WC3 - £7k space Jesus Green barbecue area (and WC4 associated signage) plus drinking - £12.5k water fountain Midsummer Common Community WC5 Orchard: drinking water fountain - £2.5k

Sheep’s Green local nature reserve: WC6 biodiversity bank improvements at - £22k Mill Pond Biodiversity enhancements (e.g. ‘Bee banks’) at parks in in East X01 - £5k Chesterton, Coleridge, Trumpington & Market

3. S106 Funding Context

3.1The Council has secured generic, off-site S106 funding from developers, under a range of contribution types, to help mitigate the impact of local development prior to the changes to the national regulations in 2015. An overview can be found at: www.cambridge.gov.uk/our-approach-to-s106.

3.2S106 funding has to be used for intended purposes. Here are some examples of eligible project spend: a. ‘Provision for children and teenagers’ S106 contributions can be used for play equipment for children and teenagers, and safety surfacing in Council play areas. b. ‘Informal open space’ S106 contributions can be used for the following types of spend within the city’s parks and green spaces: paths, landscaping (including skate parks), fencing, lighting related to the open space itself, signposting, new trees and shrubs, drainage improvements, habitat creation, new benches, bins and noticeboards.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2019 S106 Priority-Setting (Play Areas and Open Spaces)Report 388 KB DownloadRead as text
PDF
Amended recommendation /25/PnTReport 125 KB Download

At this meeting

Whole meeting

Who was there

11 of 12 attended
MS
Councillor Martin SmartChair, apologies, sent representative
PS
Councillor Patrick SheilVice-Chair, present
DB
Councillor Dave BaigentCommittee Member, present
TB
Councillor Tim Bick Lib Dem Spokes for Planning PolicyCommittee Member, present
GC
Councillor Greg ChadwickCommittee Member, present
AC
Councillor Alex CollisCommittee Member, present
KG
Councillor Kelley GreenCommittee Member, present
JH
Councillor John HipkinCommittee Member, present
CM
Councillor Colin McGertyCommittee Member, present
GB
Councillor Gerri BirdCommittee Member, present
NM
Councillor Nicky MasseyExecutive Councillor, apologies
KT
Councillor Katie ThornburrowExecutive Councillor, present

On this subject at Cambridge

Search all
  1. 2019 S106 Priority-Setting (Play Areas and Open Spaces)This decision
  2. 2016/17 S106 Priority-Setting Round SACApproved
  3. S106 priority-setting (Streets and Open Spaces)Approved
  4. S106 Priority-Setting Arrangements (Streets & Open Spaces)Approved
  5. S106 Priority-Setting Arrangements (Communities)Agreed
  6. 2015/16 S106 Priority-Setting: Follow-up ReportApproved

More from Cambridge Planning and Transport Scrutiny Committee

All decisions
MeetingDecisionOutcome
25 Mar 2025 Cambridge Neighbourhoods Design Code for Arbury, Kings Hedges and Parts of West Chesterton Supplementary Planning DocumentDecision of the Executive Councillor for Planning, Building Control and Infrastructure i. Considered the main issues ... Agreed Open
25 Mar 2025 Cambridge Biomedical Campus Supplementary Planning Document AdoptionDecision of the Executive Councillor for Planning, Building Control and Infrastructure i. Considered the main issues ... Agreed Open
25 Mar 2025 Greater Cambridge Planning Obligations Supplementary Planning Document AdoptionDecision of the Executive Councillor for Planning, Building Control and Infrastructure i. Considered the main issues ... Agreed Open
25 Mar 2025 Health Impact Assessment Supplementary Planning Document AdoptionDecision of the Executive Councillor for Planning, Building Control and Infrastructure i. Considered the main issues ... Agreed Open
14 Jan 2025 Authority Monitoring Report 2023-24Decision of the Executive Councillor for Planning, Building Control and Infrastructure i. Agreed the Cambridge City C... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies