Environmental Improvement Programme

Approved Committee 3 papers

West Central Area Committee approved this item on Thursday 5 March 2020. Below is the council's own wording, with the papers it was decided on.

Item20/9/WAC

Resolved

Resolved- To approve the recommendations in paragraph 2 of the officer report.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to West Central Area Committee

Item Environmental Improvement Programme

To: West Central Area Committee 5 March 2020 Report by: John Richards, Public Realm Engineering & Project Delivery Team Leader Tel: 01223 458525 Email: [email protected] Wards affected: Castle, Market, Newnham

Key Decision: No

1. Executive Summary 1.1 This report outlines changes to the Council’s Environmental Improvement Programme (EIP) during 2018/ 19, and reviews the latest round of applications received within West Central area.

2. Recommendations The West Central Area Committee is recommended to: 1. Note the operating amendments to the programme agreed by the Executive Councillor for Streets and Open Spaces following Environment and Community Scrutiny on 21 March 2019 2. Note the allocation of funding to continue with a programme across all areas for the period 2019-21 3. Note those new West Central area project aspirations received in the latest 2019/ 20 round recommended to the Executive

Report page no. 1 Agenda page no. Councillor for Streets and Open Spaces for funding from the new central, city-wide, strategic EIP allocation 4. Consider those new West Central area project aspirations received in the latest 2019/ 20 round for funding as part of the local West Central area programme for 2019/ 20 5 Support those projects selected for implementation, subject to them being viable, obtaining consents as necessary, positive consultation and final approval by the Council’s Place Board, Ward and Executive Councillors, where required.

3. Background 3.1. The Council’s Environmental Improvement Programme (EIP) has been operating as a rolling programme since 2004. The programme budget, which has been £170,000 per annum for the most recent period up to 2018/19, has been devolved to Area Committees to allocate to outdoor public realm improvement schemes, identified through Ward Councillors. The creation of direct, lasting and noticeable improvements to the appearance of the public realm environment has been at the heart of the programme, since its introduction. The current EIP eligibility criteria are set out along with the programme application form in Appendix B. 3.2 The programme has been subject to periodic review to improve flexibility, ensure good value and help speed up project delivery. That said, there have been delivery difficulties where project aspirations have complexities, such as where they involve the public highway. Such difficulties have led to a disproportionate impact on staffing resource, with the associated projects often taking a significant amount of time and staffing to deliver.

Report page no. 2 Agenda page no. 3.3 Year 2018/ 19 was the last of the previous four-year programme funding commitment and so, it was appropriate to use the opportunity to consider the future focus and composition of any extended programme. EIP work remains much valued by councillors and communities alike, but warranted review and potential re-focus to ensure it continues to best meet strategic objectives and the needs of a rapidly expanding city.

4. Programme Review and Funding

4.1Since 2011/ 12, approaching two hundred separate EIP projects were added to the programme by the four Area Committees city-wide. These varied in cost between a few hundred to tens of thousands of pounds. Of the prioritised projects, just over three quarters were completed by the end of the funding period to March 2019. The remainder are being progressed as resources allow.

4.2Over the years many submitted and approved EIP projects have focused on improvements to core highways and transport infrastructure, which is dependent on agreement with the County Council, as Highway Authority and, in certain cases, such as Traffic Regulation Orders, to statutory processes. In order not to further complicated programme development and delivery, such aspirations have more recently been directed towards the County’s Local Highways Improvement (LHI) programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EIP SCHEMES 2019-20: WEST CENTRAL (1) /9/WACAppendix A 19 KB Download
PDF
EIP Application Form & Eligibility Criteria 2019-20 (1) /9/WACAppendix B 150 KB Download
PDF
Environmental Improvement ProgrammeReport 278 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
AM
Councillor Anthony MartinelliChair, present
KP
Councillor Katie PorrerVice-Chair, present
TB
Councillor Tim BickCommittee Member, present
RC
Councillor Rod CantrillCommittee Member, apologies
GC
Councillor Greg ChadwickCommittee Member, present
MG
Councillor Markus GehringCommittee Member, present
JH
Councillor John Hipkin Independent SpokesCommittee Member, apologies
JM
Councillor Josh MatthewsCommittee Member, present
CP
Councillor Cheney PayneCommittee Member, present
NH
Councillor Nichola Harrison Cambridgeshire County Councillor for MarketCommittee Member, present
LN
Councillor Lucy NethsinghaCommittee Member, present
CR
Councillor Claire Richards Cambridgeshire County Councillor for CastleCommittee Member, apologies

On this subject at Cambridge

Search all
  1. Environmental Improvement ProgrammeThis decision
  2. Review of the Environmental Improvement ProgrammeAgreed
  3. Environmental Improvement ProgrammeAgreed
  4. Environmental Improvement ProgrammeAgreed
  5. Environmental Improvement Programme 2017-18Noted
  6. Environmental Improvement ProgrammeDeferred

More from Cambridge West Central Area Committee

All decisions
MeetingDecisionOutcome
14 Sep 2023 Environmental Report - WCACAgreed that the needle pick up across the wards seemed high but compared to the data over 24 months the number of nee... Agreed Open
15 Jun 2023 Policing and Safer Neighbourhoods WCACAgreed to speak with Inspector McNeill on how to improve the message of successes and if a briefing note could be cir... Agreed Open
16 Mar 2023 Open ForumAgreed with the points raised as experienced the same issues. ii. Had recently spoken with the traffic warden who wer... Agreed Open
5 Mar 2020 WCAC Area Committee Grants 2020-21Resolved- To approve the recommendations in paragraph 2 of the officer report. Approved Open
20 Jun 2019 Election of Chair and Vice Chair - WCACResolved (by 8 votes to 0 – unanimously by all present) that Councillor Martinelli be Chair for the ensuing year. Cou... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies