Environment and Community Scrutiny Committee, Thursday 19 January 2023 at 5.30pm

Extension to Storeys Field Community Centre

Agreed Scrutiny 3 papers

Environment and Community Scrutiny Committee agreed this item on Thursday 19 January 2023. Below is the council's own wording, with the papers it was decided on.

Item23/8/EnC

Resolved

Decision The Storey’s Field Centre (SFC) on the Eddington Development in the Northwest of the City, opened to the public in February 2018 and has been managed and operated by the City Council under a contract for services with the Storey’s Field Centre Trust (SFCT) since June 2016. At some point the intended model for operating the new centre was changed from direct management by the Trust, to a contract for services. It was agreed that the Council would, in the first instance, enter a five-year services contract to operate the centre, partly to contribute community centre management expertise, but also to support establishment of the new centre to be able to meet the needs of a new community in a key city growth area. It was always the Council’s intention for this to be a medium-term arrangement, to support the newly formed Trust until a centre manager and team had been recruited, trained and a centre programme had been established. At the request of SFCT the council’s contract for services has been extended twice, to give the Trust time to review the future direction of the centre, and to complete a procurement process to appoint a new operator. The current contract for services is due to end 31st March 2023. SFCT undertook an open procurement process in July 2022 to seek a new operator, however, this was unsuccessful. The recommendation made in the Officer’s report was for the council to make a further extension to its contract for services with SFCT for 12 months until 31st March 2024, for the following reasons: a. For SFCT to assess the first procurement process and have sufficient time to complete a second tender process if required. b. For SFCT to review and agree the future direction for the centre. c. To give the SFCT staff team greater certainty regarding their ongoing employment. At the end of the contract term on 31st March 2024, the Council Community Services team would focus on working collaboratively with SFCT and The University to ensure a joined-up programme across community facilities in the local area and that requirements in the Section 106 agreement were met. Decision of Executive Councillor for Open Spaces, Food Justice and Community Development i. Agreed to extend the councils contract for management services if required by Storey’s Field Centre Trust (SFCT), until 31 March 2024. ii. Noted that the council’s management and operation of Storey’s Field Centre will end 31 March 2024 and that eight Council employed posts may then transfer under a TUPE arrangement, to a new operator. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Strategic Project Manager. The Strategic Project Manager said the following in response to Members’ questions: i. The City Council were working closely with Cambridge University to reach a sustainable future for the Storey’s Field Centre. ii. The City Council were working with Storey’s Field Centre Trust due to s106 obligations. No details had been given about a new contract operator. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment and Community Scrutiny Committee

Project / Proposal Name or Reference: Storeys Field Community Centre contract extension and handover to a new operator Date: 19.01.2023 Your Name: Allison Conder 1. IMPACT ON CARBON EMISSIONS (MITIGATION OF CLIMATE CHANGE) HOW WILL THIS WHAT IS THE IMPACT CONSIDERED TO BE? CLIMATE CHANGE WILL THE PROJECT WILL THE PROJECT PLEASE DETAIL HERE THE ACTION THAT WILL BE TAKEN HAS A NET ZERO PROJECT/PROPOSAL See guidance in the purple box, below, to help you RATING: MOVE CAMBRIDGE MOVE THE CITY TO AVOID, MITIGATE OR COMPENSATE FOR THE NEGATIVE CARBON OPTION AFFECT THE FOLLOWING assess the degree of the negative and positive Use drop down list CITY COUNCIL CLOSER TO THE IMPACTS AND MAXIMISE POSITIVE IMPACTS? BEEN KEY AREAS: impacts e.g. High, Medium or Low CLOSER TO THE OBJECTIVE OF A CONSIDERED? OBJECTIVE OF NET ZERO CARBON PLEASE PROVIDE BEING NET ZERO CAMBRIDGE BY DETAILS. CARBON BY 2030? 2030? Use drop Use drop down list down list Positive Impact: Energy use will be reduced or renewable Consider: energy will be used ▫ Reducing demand for energy ▫ Specifying energy Nil Impact: No extra energy use is involved efficiency measures (e.g. 1 ENERGY USE Nil No No insulation, low energy lighting) More energy (gas and/ or electricity) will ▫ Generating renewable Negative Impact: energy (e.g. heat pumps, be consumed (by CCC or others) solar photovoltaic panels) Less waste will be generated OR Consider: Positive Impact: amount of waste that is reused/ recycled ▫ Will resources be reduced will be increased or reused? WASTE ▫ Will you use recycled 2 Nil Impact: No waste will be generated Nil No No GENERATION goods? ▫ Will recycling facilities be More waste will be generated (by CCC increased? Negative Impact: or others) The use of transport and/or of fossil fuel- Consider: Positive Impact: based transport will be reduced ▫ Will you purchase an USE OF electric vehicle? 3 Nil Impact: No extra transport will be necessary Nil No No ▫ Will you specifiy the use of TRANSPORT public transport? CCC or others will need to travel more ▫ How will you reduce the Negative Impact: OR transport goods more often/ further need to travel or transport Food will be locally grown and/ or meat- Consider: Positive Impact: ▫ Use of locally grown/ free SUSTAINABLE produced food 4 Nil Impact: No change in supply of food Nil No No ▫ Reducing use of imported FOOD food Food will travel long distances and ▫ Reducing use of meat Negative Impact: include meat

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Climate Change Rating Tool: SFC 19.01.23 /8/EnCReport 179 KB DownloadRead as text
PDF
EqIA Storeys Field 19.01.23 /8/EnCReport 611 KB Download
PDF
Extension to Storeys Field Community CentreReport 213 KB Download

At this meeting

Whole meeting

Who was there

10 of 13 attended
DP
Councillor Dinah PoundsChair, present
SC
Councillor Sam CarlingVice-Chair, present
HC
Councillor Hannah Copley Green and Independent SpokesCommittee Member, present
ID
Councillor Iva DivkovicCommittee Member, apologies
OH
Councillor Olaf Hauk Lib Dem Spokes for Environment, Climate Change & BiodiversityCommittee Member, present
CH
Councillor Cameron HollowayCommittee Member, present
CP
Councillor Cheney Payne Lib Dem Spokes for Recovery, Employment & Community Safety; Equalities, Anti-Poverty & Wellbeing; Open Spaces, Food Justice & Community DevelopmentCommittee Member, present
NS
Councillor Niamh SweeneyCommittee Member, apologies
RS
Councillor Richard SwiftCommittee Member, present
DL
Councillor David LevienReserve, in attendance
AC
Councillor Alex Collis Executive Councillor for Open Spaces, Food Justice and Community DevelopmentExecutive Councillor, present
MH
Councillor Mairéad Healy Executive Councillor for Equalities, Anti-Poverty and WellbeingExecutive Councillor, present

All 13 on the meeting page

On this subject at Cambridge

Search all
  1. Extension to Storeys Field Community CentreThis decision
  2. Revisions to Governance Arrangements and an Extension to the Contract For Services for Storeys Field CentreAgreed
  3. Extension to Storeys Field Community Centre Contract for ServicesAgreed

More from Cambridge Environment and Community Scrutiny Committee

All decisions
MeetingDecisionOutcome
20 Mar 2025 Folk FestivalDecision The Officer’s report was presented following a request for a special meeting of Environment and Community Sc... Noted Open
20 Mar 2025 Market Traders Terms and ConditionsDecision The Officer’s report provided details of the proposed changes to Cambridge General Market (General Market) T... Approved Open
20 Mar 2025 Weekly Food Waste CollectionsDecision The Environment Act 2021 required all councils to align their household waste and recycling services with ne... Approved Open
20 Mar 2025 Leisure Management Contract 2026Decision This report was being presented to update Members and conclude the on ongoing work to review the Council’s l... Agreed Open
20 Mar 2025 Equalities Objectives for 2025/26Decision The Officer’s report sought approval of new equalities objectives applicable from 1 April 2025 to 31 March 2... Approved Open