Decision This report provides an update on the housing development programme. Decision of Executive Councillor for Housing i. Noted the continued progress on the delivery of the approved housing programme. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of the Housing Development Agency . The Head of the Housing Development Agency said the following in response to Members’ questions: i. Reports for housing redevelopment schemes usually contained an external grant funding option and an option funded without grant funding for viability. Currently grant is from Homes England or Right to Buy receipts. Neither of these funding sources would fund replacement dwellings (i.e.: development had to be for new housing). ii. ERDF stood for European Regional Development Fund. iii. ERDF funding had been sought for the development of housing at St Thomas and Paget Road unfortunately due to criteria the scheme was ineligible for the funding. The cost for delivering the development as a net zero carbon development was however still built into the budget. The Committee unanimously resolved to endorse the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1This report provides an update on the housing development programme. 1.2. 502 homes have been completed across 13 sites under the City Council programme, with 260 being net new Council homes
1.3In parallel with this committee report quarterly update statistics for the Councils Affordable housing delivery will be published to the Councils website to facilitate public perusal.
Recommendations
The Executive Councillor is recommended to:
2.1Note the continued progress on the delivery of the approved housing programme.
3. Reporting 3.1 This is a regular quarterly report showing progress on the City Council’s new housing developments. 4 Delivery Programme 4.1 The current delivery programme confirms the 500 devolution programme consisting 930 (including market sale) homes in total and 538 net affordable homes the 10-year New Homes Programme consisting of 343 homes with scheme approval, delivering 117 net Council rented HRA homes.
The tables below show the breakdown of homes and the stage they are at:
500 Homes Programme- net Completed On site Approved Totals Total Homes 502 426 2 930 Replacement homes -31 -45 0 -76 Market Sale -211 -105 0 -316 Net new Council rented HRA homes 260 276 2 538 % of target 108%
10yr New Homes Programme Completed On site Approved Totals Total Homes 0 154 189 343 Replacement homes 0 0 -71 -71 Affordable (80% of market rents) 0 -61 -94 -155 Market Sale 0 0 0 0 Net new Council rented HRA homes 0 93 24 117 % of target 12%
Modular Homes Project Completed On site Approved Totals Total Homes 16 0 0 16 Replacement homes 0 0 0 0 Market Sale 0 0 0 0 Net new homes (not HRA) 16 0 0 16
4.2Appendix 1 shows the current programme, indicating total housing provided per scheme as well as the net gain of Council homes. The Budget Setting Report to this Committee includes all financial information for respective scheme budgets and net cost to the Council’s Housing Revenue account. 5 Profile of Start on Sites
Table 1: Start on Site Forecast Profiles for Council rented affordable homes in HRA.
500 Programme (net of replacements) Progress to 500 starts on site 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Starts by year 2 159 158 203 14 0 2 Cumulative total 2 161 319 522 536 537 538
10yr New Homes Programme (net of replacements and 80% market rents) Forecast Progress 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 Starts by year 10 67 30 10 0 0 0 0 Cumulative total 10 77 117 117 117 117 117 117
6 Scheme details 6.1 Schemes Completed:
Net Market Replace- Scheme Name Affordable Sale ment Delivery Completion Date Uphall Road 2 0 0 E&F Jan-18 Nuns Way & Wiles Close 10 0 0 Tender Aug-19 Ditchburn Place Community Rooms 2 0 0 Tender Sep-19 Queens Meadow 2 0 0 CIP Jun-20 Anstey Way 29 0 27 CIP Jun-20 Colville Garages 3 0 0 CIP Jul-20 Gunhild Way 2 0 0 CIP Jul-20 Wulfstan Way 3 0 0 CIP Sep-20 Markham Close 5 0 0 CIP Sep-20 Ventress Close 13 0 2 CIP Feb-21 Akeman Street 12 0 2 CIP May-21 Mill Road 112 116 0 CIP In progress Cromwell Road 65 95 0 CIP In progress Total 260 211 31
6.2Schemes on Site:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.