Decision of the Leader of the Council: · Note the progress and next steps reports for the project workstreams. · Note the increased risks arising as a result of the inflationary pressures and delegate authority to the Director to work on further risk mitigation to assure the Council that the programme remains on track for delivery. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations A Public Speaker made a statement. The Director of Enterprise and Sustainable Development introduced the report. The Director of Enterprise and Sustainable Development said the following in response to Members’ questions: i. The Area Action Plan cannot come forward until the final determination of the Development Consent Order (DCO). ii. The DCO would be subject to inspection. iii. The North East Cambridge landowner group were seeking to appoint an independent chair. There were a number of independent task groups. One of those is the general infrastructure. They were re-engaging with utilities, water management, connectivity. They were re-engaging in regard to energy. Early evidence raised some risks in regard to an AAP wide energy provision. They were looking at key sites and neighbourhoods, whichever is more efficient. However this will all be reviewed. The Committee noted the report. The Leader of the Council agreed to note the report. Any Alternative Options Considered and Rejected Not applicable.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
ITEM: North East Cambridge Core Site Update Report
Cambridge City Council
To: Leader of the Council Report by: Fiona Bryant, Director of Enterprise and Sustainable Development
Relevant scrutiny Strategy & Resources January 2023 committee: Scrutiny Committee
Wards affected: East Chesterton
NON-KEY REPORT FOR INFORMATION ONLY 1.0 Executive Summary
1.1This report provides an update on progress to date and next steps for the North East Cambridge (NEC) Core Site project, and the Housing Infrastructure Fund programme delivery. 1.2 The whole NEC area encompasses around one square kilometre within the City and South Cambridgeshire geographies.
1.3The North East Cambridge (NEC) Core Site, situated south of the A14, west of the science park and north of the Cambridge business park, is one of the last large scale brownfield development regeneration sites suitable for housing development in Cambridge. The location beside the A14, Cambridge North Station, the guided bus way and the Chisholm Trail, make this a highly accessible and sustainable location. The Core Site of around 49ha is owned by Anglian Water Authority and Cambridge City Council and is located within Cambridge City Council’s boundary. It currently houses the Cambridge Waste Water Treatment Plant (CwwTP). The relocation of this plant is key to unlocking the potential both for this site and for the wider area.
1.4There are three key projects associated with the Council and relating to the proposed Core Site development which include:
1. Planning Framework North East Cambridge Area Action plan (NEC AAP or AAP) and the emerging Greater Cambridge Local Plan (GCLP)– led by Greater Cambridge Shared Planning Service.
2. Cambridge Waste Water Treatment Plant Relocation - Cambridge Waste Water Treatment Plant Relocation Project (CwwTP) – led by Anglian Water and funded through HIF. Cambridge City Council is the grant recipient from Homes England for the HIF funding. Grant Monitoring meetings occur monthly.
3. NEC Core Site Development – led by Cambridge 4 LLP, a joint venture between Anglian Water and Cambridge City Council (with reserved matters to Cambridge City Council and Anglian Water), with master developers U&I and TOWN. The project board, comprising members from U&I, Anglian Water and the City Council, meets quarterly and reports to the LLP Board. The LLP Board, comprising members from Anglian Water and the City Council, meets quarterly and is administered by Anglian Water. All reserved matters are referred for decision to the Anglian Water Board and to Executive Cllr/scrutiny committee at the Council. Quarterly reports are also submitted to the Executive Members.
1.5It should also be noted that other key landowners are also progressing development proposals and consented plans within the wider NEC area. Whilst the Core site project team are actively engaged with other landowners, this report does not focus on progress other than for the Core Site. The Planning framework and the CwwTP projects are only covered in very high level summary owing to the Core site project’s interdependency with them.
1.6Key progress has been mainly focussed this year on the Development Consent Order application, which is due to be submitted in early 2023. For the Core Site, 2022, like 2021, has been focussed on the widest possible engagement programme, focussed on the vision, values and very early master planning stages. Key elements include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.