Briefing on Greater Cambridge Partnership Infrastructure Projects

Noted Planning 1 paper

Planning and Transport Scrutiny Committee noted this item on Tuesday 21 March 2023. Below is the council's own wording, with the papers it was decided on.

Item23/15/PnT

Resolved

Decision To give Members an opportunity to ask questions about the officer’s progress with applications for the Greater Cambridge Partnership (GCP) projects, this report provided an overview of the projects, (for which the Director for Planning and Economic Development has delegated authority) together with a high-level programme for the projects. The GCP projects covered by the delegation were as follows: i. Cambourne to Cambridge Rapid Transport Route (C2C) public transport corridor project. ii. Cambridge South-East Transport Route (CSET) public transport corridor project Phase 2. iii. Cambridge Eastern Access public transport corridor project. iv. Waterbeach to Cambridge public transport corridor project. v. Greater Cambridge Greenways (various routes). Decision of the Executive Councillor for Planning Policy and Infrastructure i. Noted the update report in respect of the GCP projects identified in criteria (i) to (v) of Paragraph 1.3 of the Officer’s report (as shown above). Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations In response to Member’s comments and questions the Strategic Sites Delivery Manager and the Joint Director of Planning and Economic Development said the following: i. The Shared Services response and input was determined by the project programmes that were being led by the GCP which were at various stages. ii. The dialogue at pre-application stage was not publicly available. These conversations were based around technical advice around planning matters/evidence resting with the Planning Authority. GCP was the project promoter and drew upon SPS advice as required. iii. Conversations involving planning policy officers working on the emerging Local Plan had been held. The LPA had referred GCP to its technical studies on the Local Plan and assisted with understanding and interpretation. iv. In terms of the Waterbeach to Cambridge public transport corridor project there was a phase one series of interventions that were required before 1600 dwellings approximately had been completed. Officers could not confirm whether the Waterbeach Public Transport Corridor was part of those phase 1 works but would advise further. Until there was a substantive number of residents, the trip effects and the transport mitigation were not required immediately. However, the cycleway enhancements along the A10 had been completed (one part of the mitigation proposals). v. Noted the statements read out by Councillor Copley on the projects referenced in the Officer’s report. vi. Welcomed members views, whether individually or collectively on these projects, which would be taken into consideration as part of the preparation of the Council’s responses vii. The Council’s formal position at the point of statutory consultation would be formed either through the Out of Cycle decision process, approved by the Executive Councillor, in consultation with the Chair and Opposition Spokes or if possible through the Committee – but timelines for responses are fixed and not within the Control of the Council. viii. Noted the comment that shared space cycle/pedestrian facilities were not favoured by members - there should be separate pedestrian and cycles ways with clear signage ix. Welcomed the comments that good bridle ways should also be considered. The Committee i. By a show of hands (6 votes to 0) to note the update report in respect of the GCP projects identified in criteria (i) to (v) of Paragraph 1.3 of the Officer’s report. The Executive Councillor thanked Councillor S Smith for chairing the committee during the municipal year 2022/23, who had been rigorous in their reading of the emerging Local Plan and committee items. Members appreciated all the input made as Chair. The Chair thanked all Members for their work for the Committee. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted). No conflicts of interest were declared by the Executive Councillor .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Planning and Transport Scrutiny Committee

Item

Update on Greater Cambridge Partnership (GCP) Infrastructure Projects

To: Councillor Katie Thornburrow, Executive Councillor for Planning Policy and Infrastructure, Planning and Transport Scrutiny, 21 March 2023 Report by: Stephen Kelly, Joint Director for Planning and Economic Development [email removed] Wards affected: All

1. Executive Summary 1.1 At the 17 January 2023 meeting of Planning and Transport Scrutiny meeting, it was confirmed that an update on the Greater Cambridge Partnership (GCP) main infrastructure access corridor projects would be provided at the 21 March 2023 meeting. 1.2 This report focuses on presenting an overview of the projects which the Director for Planning and Economic Development has delegation for, together with a high-level programme for these projects, to enable an opportunity for members to express their views to officers. 1.3 The GCP projects covered by the delegation are: (i) Cambourne to Cambridge Rapid Transport Route (C2C) public transport corridor project. (ii) Cambridge South-East Transport Route (CSET) public transport corridor project Phase 2. (iii) Cambridge Eastern Access public transport corridor project. (iv) Waterbeach to Cambridge public transport corridor project. (v) Greater Cambridge Greenways (various routes) 2 Recommendations

2.1The Executive Councillor is recommended to:

(i) Note this update report in respect of the GCP projects identified in criteria (i) to (v) of Paragraph 1.3 above.

3 Background Cambridge City and South Cambs Transport Strategy

3.1The GCP strategy is driven by the Transport Strategy for Cambridge and South Cambridgeshire (TSCSC) which was adopted by Cambridgeshire County Council (CCC) in 2014 and supports the 2018 Cambridge City and South Cambridgeshire District Local Plans. 3.2 The strategy provides a detailed policy framework and programme of schemes for the Greater Cambridge area, consistent with the Cambridgeshire Local Transport Plan 2011-26. It also details the transport infrastructure and services necessary to deliver this growth Legislative Context - Transport and Works Act order

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Briefing on Greater Cambridge Partnership Infrastructure ProjectsReport 263 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 12 attended
SS
Councillor Simon SmithChair, present
DB
Councillor Dave BaigentVice-Chair, present
TB
Councillor Tim Bick Lib Dem Spokes for Planning and InfrastructureCommittee Member, apologies
SD
Councillor Sam Davies Green and Independent SpokesCommittee Member, apologies
LH
Councillor Lewis HerbertCommittee Member, apologies
KP
Councillor Katie PorrerCommittee Member, apologies
JS
Councillor Jocelynne ScuttCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present
RS
Councillor Richard SwiftCommittee Member, present
HC
Councillor Hannah CopleyReserve, present
JP
Councillor Jennifer Page-CroftReserve, present
KT
Councillor Katie Thornburrow Executive Councillor for Planning Policy and InfrastructureExecutive Councillor, expected

More from Cambridge Planning and Transport Scrutiny Committee

All decisions
MeetingDecisionOutcome
25 Mar 2025 Cambridge Neighbourhoods Design Code for Arbury, Kings Hedges and Parts of West Chesterton Supplementary Planning DocumentDecision of the Executive Councillor for Planning, Building Control and Infrastructure i. Considered the main issues ... Agreed Open
25 Mar 2025 Cambridge Biomedical Campus Supplementary Planning Document AdoptionDecision of the Executive Councillor for Planning, Building Control and Infrastructure i. Considered the main issues ... Agreed Open
25 Mar 2025 Greater Cambridge Planning Obligations Supplementary Planning Document AdoptionDecision of the Executive Councillor for Planning, Building Control and Infrastructure i. Considered the main issues ... Agreed Open
25 Mar 2025 Health Impact Assessment Supplementary Planning Document AdoptionDecision of the Executive Councillor for Planning, Building Control and Infrastructure i. Considered the main issues ... Agreed Open
14 Jan 2025 Authority Monitoring Report 2023-24Decision of the Executive Councillor for Planning, Building Control and Infrastructure i. Agreed the Cambridge City C... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies