Cambridge City Centre Heat Network: Detailed Project Development

Approved Scrutiny 1 paper

Environment and Community Scrutiny Committee approved this item on Thursday 29 June 2023. Below is the council's own wording, with the papers it was decided on.

Item23/6/EnC

Resolved

Decision AECOM’s ‘Mapping and Masterplanning Study’ (Work Package 1) suggested that the Cambridge City-Centre Heat Network was likely to be feasible. The subsequent ‘Feasibility Study’ (Work Package 2) was scheduled to report in summer 2023, enabling the Cambridge City-Centre Heat Network to move to Detailed Project Development stage. The decision required related to Council approval and match-funding needed to move to the next stage of Detailed Project Development. The Detailed Project Development would provide a more thorough assessment of the physical and financial aspects of the project. It could include options analysis and advice on governance, financing and commercial models. Once the Detailed Project Development stage had been completed, a further decision on whether and how to proceed with build-out and delivery of a network, and if, or what investment, would be required. Decision of Executive Councillor for Climate Action and Environment i. Provided ‘in-principle’ approval to use up to £180,000 of the Council’s Climate Change Fund for match-funding of the next phase of Detailed Project Development, subject to a satisfactory outcome from the feasibility study; a successful second government Heat Network Delivery Unit grant application; confirmation of a match-funding contribution from the University of Cambridge, clarification of additional expected resourcing requirements and sources and approval from the Executive Councillor for Finance and Resources. ii. Approved delegated authority to the Assistant Chief Executive (as heat network Project Sponsor) to make the final decision in consultation with the Executive Councillor, chair of Environment and Communities Scrutiny Committee and opposition spokes, once the Feasibility Study was completed in summer 2023. iii. Noted the potential requirement for a further additional council and partner investment in technical assessment, at a later date, subject to exploration of alternative sources of funding (see section on risks and mitigations on pages 9-11 of the Officer’s report). Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Assistant Chief Executive. The Assistant Chief Executive said the following in response to Members’ questions: i. The project had not happened earlier as officers had been exploring options for some years. It took time to find the finance and appropriate technology to make the project practicable to meet targets in the City Council’s strategies. ii. No-one else had done a heat network in a historic city centre (they had in other settings such as rural areas) so the City Council would be a trail blazer. iii. There would be some disruption to the city centre if the network was installed. The intention to minimise this and further details on ‘how’ were set out in the Officer’s report. The intention was to work with partner organisations to mitigate disruption and risks; plus keep residents informed. iv. Central Government funding would be sought to minimise the cost to the Council. v. There were a lot of finance options for the project at present, and the pros and cons of each would be explored further during the next stage. There was a risk/reward review to decide which to use . vi. The impact of the project on open spaces (and any archaeology therein) would be reviewed (later) in the bore hole part of the project. The Sustainability Co representative said the following in response to Members’ questions: i. The City Council was showing an enabling role by bringing the project forward. ii. The next stage of the project would look at project finance and governance options. iii. The heat network tried to balance aims (e.g. addressing fuel poverty) with what was practicable. The ambition would be to explore the potential to connect the network to social housing in due course in the hope this would lead to decarbonisation of housing stock in future . iv. There would be disruption from boreholes. There was a chance to improve open spaces and increase biodiversity after the heat network was installed. v. It was necessary to do a physical dig on site to check how many bore holes were needed, and if it was suitable to dig them in the first place. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment and Community Scrutiny Committee

Executive summary

The Cambridge City-Centre Heat Network Feasibility Study stage, shortly concluding, has had three objectives: i) Demonstrate a viable pathway to zero-carbon for Cambridge’s historic city-centre: The project aims to help achieve the City Council’s target set out in the Climate Change Strategy 2021-2026. “To reduce direct emissions from Council buildings and assets to net zero carbon by 2030”. This was our initial primary purpose for starting to explore a heat network with renewable heat for the city centre, to help decarbonize council buildings that would otherwise (because of their location or construction) be difficult to treat. It quickly became clear that there were opportunities to develop the project jointly and share the task with partners at the University of Cambridge, who face similar challenges in terms of their city centre estate, and potentially other partners in the tightly constrained urban setting of the city centre. In

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cambridge City Centre Heat Network: Detailed Project DevelopmentReport 1.9 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 13 attended
ID
Councillor Iva DivkovicChair, present
AN
Councillor Antoinette NestorVice-Chair, apologies
IF
Councillor Ingrid FlaubertCommittee Member, present as substitute
JG
Councillor Jean Glasberg Green & Independent (Spokes) for Communities; Open Spaces and City Services; Climate Action and EnvironmentCommittee Member, present
OH
Councillor Olaf Hauk Lib Dem (Spokes) Climate Action and EnvironmentCommittee Member, present
CP
Councillor Cheney Payne Lib Dem (Spokes) Open Spaces and City Services; CommunitiesCommittee Member, apologies, sent representative
DP
Councillor Dinah PoundsCommittee Member, present
RS
Councillor Richard SwiftCommittee Member, present
RW
Councillor Rachel WadeCommittee Member, present
SC
Councillor Sam Carling Executive Councillor for Open Spaces and City ServicesExecutive Councillor, present
AG
Councillor Alice GilderdaleExecutive Councillor, present
MH
Councillor Mairéad Healy Executive Councillor for CommunitiesExecutive Councillor, present

All 13 on the meeting page

On this subject at Cambridge

Search all
  1. Cambridge City Centre Heat Network: Detailed Project DevelopmentThis decision
  2. Cambridge City Council Report MRF Update Dec 2025Noted
  3. Procurement at Cambridge City CouncilNoted
  4. Civic Affairs Committee - Cambridge City Council ConstitutionApproved
  5. Cambridge City Council Performance Management FrameworkApproved
  6. Proposals for revised governance arrangements and updated Cambridge City Council ConstitutionApproved

More from Cambridge Environment and Community Scrutiny Committee

All decisions
MeetingDecisionOutcome
20 Mar 2025 Folk FestivalDecision The Officer’s report was presented following a request for a special meeting of Environment and Community Sc... Noted Open
20 Mar 2025 Market Traders Terms and ConditionsDecision The Officer’s report provided details of the proposed changes to Cambridge General Market (General Market) T... Approved Open
20 Mar 2025 Weekly Food Waste CollectionsDecision The Environment Act 2021 required all councils to align their household waste and recycling services with ne... Approved Open
20 Mar 2025 Leisure Management Contract 2026Decision This report was being presented to update Members and conclude the on ongoing work to review the Council’s l... Agreed Open
20 Mar 2025 Equalities Objectives for 2025/26Decision The Officer’s report sought approval of new equalities objectives applicable from 1 April 2025 to 31 March 2... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies