Detailed General Fund Budget Proposals 2024/25 and an Update to the Budget Setting Context

Approved Scrutiny 2 papers

Strategy and Resources Scrutiny Committee approved this item on Monday 15 January 2024. Below is the council's own wording, with the papers it was decided on.

Item24/6/SR

Resolved

Decision i. This report updates the financial context for budget setting and presents GF budget proposals and allocations of general reserves for scrutiny (Appendix 1). ii. Following scrutiny and the completion of the budget consultation, the GF budget setting report (BSR) will be produced for consideration by The Executive on 5 February 2024 and recommendation to Full Council for 15 February 2024. Decisions of Executive Councillor for Finance and Resources The Executive Councillor is asked to: i. Approve the GF revenue and capital proposals as presented in Appendices B(a), B(b), and C, pages 16 to 23, of the attached report, for inclusion in the GF BSR. ii. Note the impact of the revenue proposals on the five year savings requirement identified in the GF Medium Term Financial Strategy (MTFS), section 3 page 9. iii. To approve for inclusion in the GF BSR: · the creation of the Civic Quarter Development Reserve with the remit set out in section 5, pages 11 and 12. · the allocation of £20m of general reserves to this new reserve. · the allocation of £750k of general reserves to the Climate Change Fund, as set out in section 5, page 11. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Chief Finance Officer. The Chief Finance Officer, City Services Director, the Assistant Chief Executive, The Leader, the Executive Councillor for Finance and Resources, the Executive Councillor for Open Spaces and City Services, the Executive Councillor for Planning, Building Control and Infrastructure and the Council’s representative on the Cambridge and Peterborough Combined Authority (CPCA) said the following in response to Members’ questions: i. Reserves were being brought forward for substantial Capital schemes. ii. The title Civic Quarter was a working title. It encompasses the refurbishment of the market and the Corn Exchange. That coincided with successful bid to the CPCA with a contribution of £1.5 million. Council required to prepare an outline business case. All government arrangement would be reported to 29 January Committee. iii. The Guildhall would also be refurbished as part of the Council’s accommodation strategy. iv. £20 million would be earmarked for Civic Quarter project, the funding arrangements are currently confidential due to competitive tender. This would be reported in due course. v. Business rates retention scheduled to be reset in 2025/2026, however need to campaign for it to continue to Government. vi. Central provision had been reduced. There was approximately £300,000 remaining. vii. Income had reduced at the crematorium. Mitigations in place include: · Entering into new markets. · Partnering with other District Councils. · Partnering with the Rosie bereavement. · Would reduce operational costs. viii. Reduced income from Market, however Cambridge was considered a successful market. Mitigations in place include: · Cutting down fixed costs. · Encourage traders to manage their own waste. · Reviewing electricity usage. · Exploring satellite markets. · Would review casual trading policy which may boost occupancy. ix. There was a green burial option at the crematorium, it was advertised on the Councils website however there had been a low take up. x. Recruiting younger market stall holders was a national problem. xi. There was a dedicated team of 3-4 people who operate the market service and who seek new customers. xii. The purpose of £50,000 contribution to Innovate Cambridge from the Council was assisting with the University and affiliated business’s goal to promote Cambridge as a city and to support local residents and communities. Chief Executive of Cambridge City Council Robert Pollock sat on the Innovate Cambridge board. xiii. The removal of the bus subsidy was due to the confidence that the Council had that the CPCA would take it over. It was currently in the proposed budget of the CPCA. xiv. The bus subsidy of the CPCA was not conditional on additional precept. That was something that has already been factored into budget. xv. Allotment income had increased not due to an increase in fees but due to an increase in plots. xvi. There was a 7% increase in fees and charges for events. The number of events on open spaces would remain the same. xvii. The number of events taking place on open spaces is constrained by the event policy. There was still an opportunity for councillors to provide feedback on what events take place during scrutiny committee. xviii. The priorities for use of Donkey Common uses were still a work in progress. xix. Resources would be provided for the District Heat Network project and Energy Efficiency works and retrofit on the Council’s corporate assets. The Scrutiny Committee approved the recommendations by a vote of 6-1 (2 abstentions). The Executive Councillor for Finance and Resources approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Version 1.0 Strategy and Resources Scrutiny Committee 15 January 2024

Budget proposals and context 2024/25

January 2024 2024/25

Cambridge City Council Contents Section No. Topic Page No.

1 Introduction 2

2 Update to national policy context 3

3 General Fund revenue proposals and impact on savings requirement 8

4 General Fund capital proposals and funding 10

5 Reserves 11

Appendices Reference Topic Page No.

A Budget proposals by portfolio 14

B(a) Budget proposals by type – pressures and bids 16

B(b) Budget proposals by type – savings 19

B(c) Budget proposals by type - external bids (if required) -

C Capital proposals 22

D Equality Impact Assessment 24 Section 1 Introduction

Purpose The General Fund Medium Term Financial Strategy (GF MTFS) was approved in November 2023, and

set out the financial strategy for the council in light of local context and external factors and the

outlook for public sector funding. It reviewed key assumptions and risks, confirming the framework for detailed budget work for 2024/25 and beyond. This report, which should be read in conjunction

with the MTFS (MTFS: (cambridge.gov.uk), builds on the MTFS, setting out budget proposals for

scrutiny and updating the context for budget setting where necessary.

The MTFS identified a total net savings requirement of around £11.1m for the 5-year period.

Alternative scenarios were modelled, giving a range of savings requirements between £9.7m to

£19.0m. These savings requirements stem from reductions in government funding, the additional net

cost of services for every new home in the city and unavoidable cost increases and income pressures.

£000 2024/25 2025/26 2026/27 2027/28 2028/29 Total

Net savings requirement 2,339 1,028 4,589 1,846 1,251 11,053

Key member decision-making dates Date Task Strategy and Resources Scrutiny Committee considers the budget context 15 January 2024 and budget proposals (this report). draft BSR (all GF portfolios) and the outcome of the budget consultation 5 February 2024 The Executive reviews the Budget Setting Report (BSR), including the results and implications of the budget consultation, and recommends the final BSR to Council 15 February 2024 Council approves the budget and sets the council tax for 2024/25

2 Section 2 Update to national policy context

National policy framework Economic factors Inflation has reduced but remains a source of concern

The global economic environment continues to be finely balanced. Whilst inflation in many major economies has cooled, there is an acceptance that the causes of ongoing inflation are not imported.

This is because inflation is above target despite the impact of high energy costs being absent from

the index as energy costs have fallen when compared year-on-year. In the UK, inflation has fed through to domestic pricing to a greater extent than previously forecast. This has led to recognition that

inflation is likely to remain above the Bank of England target of 2% for longer. Therefore, it is likely to

be further into the future before central banks, including the Bank of England, can consider reductions

in the base rate.

The chart below sets out changes in the OBR’s projections for CPI inflation between March and November 2023:

Gloomy prospects for future economic growth

The recent autumn statement saw the government confirm the progress it had made towards

3 achieving its three economies priorities of halving inflation, growing the economy and reducing debt.

Whilst the first priority has now been achieved, the statement gave an update on the measures being undertaken to achieve the other two priorities.

Fears of a recession have eased, and real GDP is now 2% above its pre-pandemic level. However, the

OBR has concluded that, even after fiscal policy intervention to reduce the tax burden on individuals and businesses, real GDP is only expected to grow modestly over the forecast period with real GDP

growth slowing from 4.3% in 2022 to 0.6% in 2023 and 0.7% in 2024. Cumulatively over the forecast

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Combined BSR with appendices /6/SRReport 2.2 MB DownloadRead as text
PDF
Detailed General Fund Budget Proposals 2024/25 and an Update to the Budget Setting ContextReport 358 KB Download

At this meeting

Whole meeting
24/3/SRPublic QuestionsOn the agenda 24/4/SRCapital StrategyApproved 24/5/SRTreasury Management Strategy Statement 2024/25 to 2026/27Approved
24/6/SRDetailed General Fund Budget Proposals 2024/25 and an Update to the Budget Setting ContextThis decision

Who was there

11 of 12 attended
RR
Councillor Richard RobertsonChair, present
DB
Councillor Dave BaigentVice-Chair, present
TB
Councillor Tim Bick Lib Dem (Spokes) Community Wealth Building and Community Safety; Leader’s PortfolioCommittee Member, present
JG
Councillor Jenny Gawthrope WoodCommittee Member, present
TG
Councillor Tim GriffinCommittee Member, present
CH
Councillor Cameron HollowayCommittee Member, present
PS
Councillor Patrick SheilCommittee Member, present
KY
Councillor Karen Young Lib Dem (Spokes) Finance and ResourcesCommittee Member, present
NB
Councillor Naomi Bennett Green (Spokes) for Community Wealth Building and Community Safety; Finance and Resources; Leader’s PortfolioCommittee Member, present
MD
Councillor Mike Davey LeaderExecutive Councillor, present
AG
Councillor Alice Gilderdale Executive Councillor for Community Wealth Building and Community Safety and Deputy Leader (Statutory)Executive Councillor, expected
SS
Councillor Simon Smith Executive Councillor for Finance and ResourcesExecutive Councillor, present

On this subject at Cambridge

Search all
  1. Detailed General Fund Budget Proposals 2024/25 and an Update to the Budget Setting ContextThis decision
  2. Detailed General Fund Budget Proposals 2025/26 and an Update to the Budget Setting ContextApproved

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open