Procurement of Planned Maintenance Contractor

Approved Scrutiny 1 paper

Housing Scrutiny Committee approved this item on Tuesday 18 June 2024. Below is the council's own wording, with the papers it was decided on.

Item24/28/HSC

Resolved

Decision The Council had two long-term planned maintenance works contracts in place. One was with Foster Property Maintenance Limited, and one is with TSG Building Services. The contract with Foster Property Maintenance Limited was due to expire in September 2025. It was proposed that the Council carried out a procurement exercise to award a replacement contract so planned maintenance service delivery could continue uninterrupted at the end of the current contract. Decision of Executive Councillor for Housing i. Approved the issue of tenders and, following evaluation of tenders, authorise the Director City Services to award a contract(s) to a contractor(s) to carry out planned building maintenance works and associated services to Council housing and other buildings for a period of five years from September 2025 to September 2030, with an option to extend for one or more year(s) up to a maximum extension of three years. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Asset Manager . The Asset Manager said the following in response to Members’ questions: i. Any potential bidders for the maintenance contract would need to set out how they would meet the requirements set out in the detailed specification document as part of their bid. ii. Noted concerns raised by members regarding the current contract and that issues had arisen with the use of sub-contractors who may not be aware of the council’s ethos. iii. There were monthly meetings held with the current contractor and there were key performance indicators (KPIs) that their performance was assessed against. Customer feedback was also collected. iv. Noted member’s request to be provided with more information about the key performance indicators. In terms of the flexibility to undertake repairs, work at the weekend was usually restricted to 8-12 noon on a Saturday as it could cause disruptions on estates. Urgent work would be carried out as required. v. Took on board the Committee’s concerns regarding supply chain management and that the council needed to ensure the full supply chain was engaged. vi. There were specific rules which governed a procurement process which must be followed. Existing contractors could not be excluded from submitting a bid for the new contract. The Committee unanimously resolved to endorse the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Background

3.1In 2017, following an OJEU compliant tendering exercise, Foster Property Maintenance Limited were appointed as main contractors to deliver the (mainly) external elements of the Council’s planned building maintenance programme of work.

3.2The contract delivers planned building maintenance to all types of Council-owned buildings. Most services are delivered to HRA property.

3.3The five-year contract was extended for three years in 2022 and is now due to expire on 25 September 2025.

3.4There is still an on-going demand for the services covered by this contract, so it is proposed that a new procurement exercise is carried out to establish a replacement contract(s).

3.5It is expected that one replacement contract will be awarded, but the procurement will be carried out in a way that will allow flexibility to award more than one contract if this is advantageous to the Council.

3.6The estimated value of the future contract is around £6m to £7m per annum – making a total estimated contract value of £30m and £35m between 2025 and 2030, or up to £56m, if the full three-year extension period was used.

3.7The proposed services / works to be covered by the new contract are as follows:

Internal and external finishes.

Report page no. 2 Agenda page no. Re-roofing works including roof structure works. Rainwater goods, facias and soffits, chimney works. Replacement doors and windows. External and internal insulation works. External and internal structural works. External hard and soft landscaping works, including paving and resurfacing. Fencing. External and internal painting and repairs. Garage improvements. Asbestos removal. Improvement works to internal and external communal areas including balconies, walkways, handrails and works arising from housing health and safety rating system surveys, lighting, and electrical works. Small new building extensions, refurbishment projects, and structural works. Estate Improvement works. Installation and maintenance of renewable energy installations. Maintenance / repair of green roofs and other estate drainage systems including SUDS, petrol interceptors and the like.

3.8It is proposed that the contract is set up so that services will be available for all Council-owned built assets and for services delivered by the Council to privately-owned property. The Cambridgeshire Home Improvement Agency will also be able to access the contract.

3.9If other services are added in the future then the value of the contract may increase.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of Planned Maintenance ContractorReport 215 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 16 attended
TG
Councillor Tim GriffinChair, present
RR
Councillor Richard RobertsonVice-Chair, present
DB
Councillor Dave BaigentCommittee Member, present
JG
Councillor Jenny Gawthrope WoodCommittee Member, present
DL
Councillor Daniel LeeCommittee Member, present
AM
Councillor Anthony Martinelli Lib Dem (Spokes) Housing and HomelessnessCommittee Member, present
RS
Councillor Richard SwiftCommittee Member, present
BT
Councillor Baiju Thittala VarkeyCommittee Member, present
ET
Councillor Elliot Tong Green (Spokes) Housing and HomelessnessCommittee Member, present
GB
Councillor Gerri Bird Executive Councillor for HousingExecutive Councillor, present
CH
Councillor Cameron Holloway Executive Councillor for Community Safety, Homelessness and WellbeingExecutive Councillor, present
DB
Diane Best Leaseholder RepresentativeCo-Optee, expected

All 16 on the meeting page

On this subject at Cambridge

Search all
  1. Procurement of Planned Maintenance ContractorThis decision
  2. Procurement of Contractor(s) to Deliver Planned Building Maintenance Work - 2022-2028Approved

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open