Agreed with a Councillor’s comment that there would be light from the streetlights on the busway path which spilled on to the area with solar light studs. x. The path was proposed to be maintained by the City Council; therefore repair / maintenance / replacement of the solar studs would be managed by the City Council and these obligations would be secured through the Section 106 Agreement. xi. The solar light studs would have bat hats on them. xii. Camcycle’s objection stated that they wanted the path to be lit with something more substantial than solar light studs (for example street lighting) for safety purposes enabling cyclists to use and access the new train station. xiii. The Case Officer had assessed the proposal and considered lighting through solar light studs acceptable. It distills to a difference ... view the full minutes text for item 24/29/JDCC
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
21/02957/COND27 West Anglia Main Line Land Adjacent to Cambridge Biomedical Campus
Application details
Report to: Joint Development Control Committee
Lead Officer: Joint Director of Planning and Economic Development
Ward/parish: Trumpington
Proposal: Submission of details required by condition 27 (Lighting Scheme) of the deemed planning consent associated with the Network Rail (Cambridge South Infrastructure Enhancements) Order 2022 (Local Planning Authority Reference 21/02957/TWA)
Applicant: Network Rail
Presenting officer: Mairead O’Sullivan, Principal Planner, Strategic Sites
Reason presented to committee: Third party representations contrary to the officer recommendation.
Member site visit date: N/A
Key issues:
1. Compliance with approved parameter plans and Design Principles 2. Compliance with the requirements of condition 27 3. Responding to local context and the impact on Hobson’s Park and the Green Belt
Recommendation: Approve and discharge condition 21/02957/COND27 (Lighting scheme) in part Report contents Document Document heading section 1 Executive summary 2 Site description and context 3 The proposal 4 Relevant site history 5 Policy 6 Consultations 7 Local groups 8 Planning background 9 Assessment 10 Principle of development 11 Compliance with parameter plans and Design Principles 12 Impact on residential amenity 13 Impact on biodiversity 14 Other matters 15 Third party representations 16 Planning Balance 17 Recommendation Table 1 Contents of report
1. Executive summary 1.1 The application seeks to discharge condition 27 of the deemed planning consent associated with the Network Rail (Cambridge South Infrastructure Enhancements) Order. The Transport and Works Act Order (TWAO) was granted in December 2022 with a deemed planning consent which included 39 conditions. Condition 27 controls the detailed lighting scheme for Cambridge South Station. The lighting scheme only relates to works within Cambridge City Council administrative area.
1.2The lighting scheme covers Hobson’s Park and follows on from the approval of the detailed landscaping scheme for the park, which was approved by the Joint Development Control Committee in March 2024. The lighting scheme is supported by consultees including Environmental Health and Ecology. The application has been subject to pre-application advice.
1.3A third party representation from CamCycle has been received in objection to the lighting scheme. Camcycle consider that street lighting should be used instead of solar studs. They also raise concerns about the placement of and distance between the solar studs. 1.4 During the course of the application, amended plans were submitted to reduce the interval spacing of the studs, and move them to either side of the cycle way element of the shared path. The 14m spacing between studs was selected as this aligns with what is currently on the existing nearby cycle way NC11. The placement of the studs at either side of the path helps to guide cycles along the route. The use of solar studs rather than street lighting is considered positive given the sensitive ecological nature of Hobson Park.
1.5Both Cambridge Past Present and Future and the Trumpington Residents Association have reviewed the proposals and have no comments to make on the discharge of the lighting condition.
1.6The details submitted comply with the Cambridge South Station Design Principles (NR-15-1 dated March 2022) in accordance with condition 3 of the deemed planning permission association with the TWAO.
1.7Officers recommend that the Joint Development Control Committee approve and partially discharge conditions 21/02957/COND27.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.