Cambridge City Council
Housing Scrutiny Committee, Tuesday 17 September 2024 at 5.30pm

Report on Outcome of Rooftop Feasibility Study

Approved Scrutiny 1 paper

Housing Scrutiny Committee approved this item on Tuesday 17 September 2024. Below is the council's own wording, with the papers it was decided on.

Item24/44/HSC

Resolved

Decision The report set out the outcomes of the feasibility study conducted since its approval in September 2023, considering both upward extension of existing housing blocks and deep-retrofit of existing properties as a parallel approach to regeneration. Decision of Executive Councillor for Housing i. Noted the outcome of the Feasibility Study conducted, confirming the officer recommendation that no deliverable scheme proceed. ii. Approved that 243 - 313 Odds Lichfield Road, 1-12 Bracondale, 1-18 Fernwood, and 1-18 Heatherfield be removed from short term redevelopment consideration, and that any further long-term review remained aligned with business-as-usual maintenance and management consideration of these properties, as it does with all council housing stock. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Assistant Director (Development). The Committee were reminded that an Equality Impact Assessment had been published separately to accompany this report. It was noted that a resident of Lichfield Road had handed a petition to the Committee Manager just before the start of the meeting which had 21 signatures which opposed the redevelopment of Lichfield Road. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Recommendations

1.1It is recommended that the Executive Councillor for Housing:

1. Note the outcome of the Feasibility Study conducted, confirming the officer recommendation that no deliverable scheme proceed. 2. Approve that 243 - 313 Odds Lichfield Road, 1-12 Bracondale, 1-18 Fernwood, and 1-18 Heatherfield be removed from short term redevelopment consideration, and that any further long-term review remain aligned with business-as usual- maintenance and management consideration of these properties, as it does with all council housing stock.

2. Purpose and reason for the report

2.12.1.1. This report sets out the outcomes of the feasibility study conducted since its approval in September 2023, considering both upward extension of existing housing blocks and deep-retrofit of existing properties as a parallel approach to regeneration. 2.1.2. The Council is aware of a growing discrepancy between the condition of ageing stock against new build housing being delivered to high sustainability levels. This Study aimed to provide detailed evidence of stock condition across two areas of sheltered housing, to understand both the current condition, and the possible level to which improvements could be enacted in future. Key priorities for this work were energy efficiency, security and level access.

Alternative options considered

3.1The only alternative considered is option 1: do nothing. These properties are and remain in the Councils rolling programme of maintenance and improvement works across all council stock. While leaving them as such would mean no disturbance to tenants, it would however also not have allowed an improvement in the understanding of the current property conditions. This proposal to conduct the feasibility study has provided significant evidence of both condition, maintenance related costs and indication of the cost of enacting significant improvements which can inform decision on both the flat blocks considered as well as council housing stock more broadly across the city.

These properties as noted in September 2023 do require ongoing maintenance expenditure, and works will continue to come forward. These include, but are not limited to: 1. Wall insulation – limited to existing cavity wall insulation extraction and refill. 2. Replacement heating systems, as a number of the flats have old electric storage heaters and there is an ambition to upgrade to a more energy efficient alternative. Officers will review whether there is possibility to develop ground source heat pump proposals further as an utcome of this feasibility work. 3. Most flats have old doors which require replacing. 4. New roof coverings are required, which will include new roof insulation 5. Resident responses in regard to Condensation, damp and mould are being provided to the responsible team for follow-up investigation.

4. Background and key issues

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report on Outcome of Rooftop Feasibility StudyReport 522 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 17 attended
TG
Councillor Tim GriffinChair, present
RR
Councillor Richard RobertsonVice-Chair, present
DB
Councillor Dave BaigentCommittee Member, present
JG
Councillor Jenny Gawthrope WoodCommittee Member, present
DL
Councillor Daniel LeeCommittee Member, present
AM
Councillor Anthony Martinelli Lib Dem (Spokes) Housing and HomelessnessCommittee Member, present
RS
Councillor Richard SwiftCommittee Member, present
BT
Councillor Baiju ThittalaCommittee Member, apologies, sent representative
ET
Councillor Elliot Tong Green (Spokes) Housing and HomelessnessCommittee Member, present
DP
Councillor Dinah PoundsCommittee Member, present
GB
Councillor Gerri Bird Executive Councillor for HousingExecutive Councillor, present
CH
Councillor Cameron Holloway Executive Councillor for Community Safety, Homelessness and WellbeingExecutive Councillor, in attendance

All 17 on the meeting page

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies