Greater Cambridge Local Development Scheme (local plan timetable)

Agreed Planning 2 papers

Planning and Transport Scrutiny Committee agreed this item on Tuesday 14 January 2025. Below is the council's own wording, with the papers it was decided on.

Item25/7/PnT

Resolved

Decision of the Executive Councillor for Planning, Building Control and Infrastructure i. Agreed the Greater Cambridge Local Development Scheme (local plan timetable) 2025 at Appendix 1 of the Officer’s report be confirmed as the Local Plan Timetable ii. Approved the Greater Cambridge Local Development Scheme (local plan timetable) 2025 be shared with Government and be published on the Greater Cambridge Planning website, superseding the Greater Cambridge Development Scheme 2022. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Strategic Planning Manager. In response to comments from Members, the Strategic Planning Manager, the Joint Director for Planning and Economic Development and Executive Councillor said the following: i. Noted the comment that extending the Plan period seemed sensible to accommodate the growth required. ii. Members would be kept informed as Officers moved forward with the Local Plan preparation to produce a Plan which could be submitted to the Sectary of State by December 2026 iii. The Government were aware of key issues that sat behind the emerging Local Plan through the Cambridge Delivery Company, discussions with the Combined Authority and other external stakeholders. iv. In all the engagement, opportunities were being taken to highlight the work on the emerging Local Plan and issues raised, with Ministers, through the CPCA and the Water Scarcity Group v. Had stressed the significance of the decision on the Development Consent Order as part of Cambridgeshire’s growth ambition with all external partners. vi. Would expect to bring a report on progress at a future meeting. vii. The proposal to submit the Greater Cambridge Local Plan by the end of December 2026, was not just about the proposed sites in the area but highlighted the Council’s policies, standards and quality. Would continue to engage with South Cambridgeshire District Council and opposition parties on this work. The Committee voted unanimously to endorse the Officer recommendations. The Executive Councillor for Planning, Building Control and Transport approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted). None.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Planning and Transport Scrutiny Committee

Greater Cambridge Local Development Scheme (local plan timetable)

January 2025

Cambridge City Council South Cambridgeshire District Council

PO Box 700, South Cambridgeshire Hall, Cambourne Cambridge, CB1 0JH Business Park, Cambridge, CB23 6EA This updated Greater Cambridge Local Development Scheme (local plan timetable) 2025 was approved by:

Cambridge City Council Executive Councillor for Planning, Building Control and Infrastructure, following debate by the Planning and Transport Scrutiny Committee – 14 January 2025

South Cambridgeshire District Council Cabinet – 14 January 2025

It took effect from XX.

2 Greater Cambridge Local Development Scheme (local plan timetable) 2025

Introduction

1. The Planning and Compulsory Purchase Act 2004, Section 15 requires that Local Planning Authorities must prepare and maintain a document to be known as their Local Development Scheme (noting that the Levelling Up and Regeneration Act 2023 (Schedule 7, 15B), which was enacted in 2023, but which will be brought into force at a future date, updates this requirement to prepare and maintain a “local plan timetable”). This Local Development Scheme provides information on the Development Plan Documents that the Councils intend to produce and sets out the timetable for their production.

2. The Local Development Scheme (LDS) is designed to help the local community and all our partners interested in development and the use of land and buildings in Greater Cambridge to understand what plans the Councils intend to produce.

3. Cambridge City Council and South Cambridgeshire District Council (“the Councils”) have committed to work together to prepare a new Local Plan for Greater Cambridge. They have also committed to prepare jointly an Area Action Plan for North East Cambridge.

4. This LDS is therefore prepared and agreed jointly by both Local Planning Authorities. This LDS updates and replaces the LDS adopted in 2022, together with the Addenda added to it in March and November 2024.

What new Development Plan Documents are to be prepared? Context

5. The plans and timetables addressed in this version of the LDS are based on the current plan-making system. The Levelling Up and Regeneration Act was given Royal Assent in November 2023, which proposes changes to the plan- making system. On 12th December 2024, Government confirmed a new National Planning Policy Framework, and also confirmed a transitional date for plans under the current plan-making system to be submitted of December 2026.

6. The LDS uses seasons in the timetables for plan making. These are using standard definition as used by the Meteorological Office as set out below. Where a key stage falls in Winter of a particular year, it will be followed by brackets saying ‘late’ for December and ‘early’ for January to February to 3 avoid confusion about the part of the year involved.

Spring Summer Autumn Winter March to June to September to December May August November to February

Greater Cambridge Local Plan

7. The Councils have committed to work together to prepare a new Local Plan, for the combined area of Cambridge and South Cambridgeshire, described as “Greater Cambridge”. The timetable for the Greater Cambridge Local Plan is set out below, which intends to submit a Local Plan under the current plan making system by December 2026.

North East Cambridge and Cambridge Waste Water Treatment Plant (CWWTP) Development Consent Order (DCO)

8. The Councils are also working together to prepare an Area Action Plan for the North East Cambridge area (the geographic extent of this area is shown at Appendix 1).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App.A_Greater Cambridge Local Development Scheme-2025 /7/PnTReport 532 KB DownloadRead as text
PDF
Greater Cambridge Local Development Scheme (local plan timetable)Report 180 KB Download

At this meeting

Whole meeting

Who was there

9 of 11 attended
AN
Councillor Antoinette NestorChair, present
DB
Councillor Dave BaigentVice-Chair, present
TB
Councillor Tim BickCommittee Member, present
HC
Councillor Hugh Clough Green (Spokes) Planning, Building Control and InfrastructureCommittee Member, present
ID
Councillor Iva DivkovicCommittee Member, present
TG
Councillor Tim GriffinCommittee Member, present
KP
Councillor Katie Porrer Lib Dem (Spokes) Planning, Building Control and InfrastructureCommittee Member, present
RS
Councillor Richard SwiftCommittee Member, present
KT
Councillor Katie Thornburrow Executive Councillor for Planning, Building Control and InfrastructureExecutive Councillor, present
HC
Hannah Coetseeex-Officio, expected
SM
Stuart MorrisOfficer, expected

On this subject at Cambridge

Search all
  1. Greater Cambridge Local Development Scheme (local plan timetable)This decision
  2. Greater Cambridge Local Plan: Proposed Submission (Regulation 19) publicationAgreed
  3. Consultation on the establishment of a centrally led Urban Development Corporation for Greater CambridgeAgreed
  4. Greater Cambridge Local Plan – Draft Regulation 18 plan for consultation and updated Local Development SchemeAgreed
  5. Greater Cambridge Local PlanDecided
  6. Greater Cambridge Planning Obligations Supplementary Planning Document AdoptionAgreed

More from Cambridge Planning and Transport Scrutiny Committee

All decisions
MeetingDecisionOutcome
25 Mar 2025 Cambridge Neighbourhoods Design Code for Arbury, Kings Hedges and Parts of West Chesterton Supplementary Planning DocumentDecision of the Executive Councillor for Planning, Building Control and Infrastructure i. Considered the main issues ... Agreed Open
25 Mar 2025 Cambridge Biomedical Campus Supplementary Planning Document AdoptionDecision of the Executive Councillor for Planning, Building Control and Infrastructure i. Considered the main issues ... Agreed Open
25 Mar 2025 Greater Cambridge Planning Obligations Supplementary Planning Document AdoptionDecision of the Executive Councillor for Planning, Building Control and Infrastructure i. Considered the main issues ... Agreed Open
25 Mar 2025 Health Impact Assessment Supplementary Planning Document AdoptionDecision of the Executive Councillor for Planning, Building Control and Infrastructure i. Considered the main issues ... Agreed Open
14 Jan 2025 Authority Monitoring Report 2023-24Decision of the Executive Councillor for Planning, Building Control and Infrastructure i. Agreed the Cambridge City C... Agreed Open