Housing Advisory Board, Monday 6 October 2025 at 5.30pm

Strategic Procurement Pipeline for Repairs, Maintenance, and Compliance Contracts

Noted Committee 5 papers

AI summaryCambridge City Council's Housing Advisory Board has noted a report on a procurement pipeline of about 13 contracts worth around £74m for housing repairs, maintenance and compliance, to be let over the next six months. Cabinet will be asked to delegate contract award authority to the Director of City Services.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedHousing Advisory Board noted the pipeline report
Moneyapproximately £74mcombined value of around 13 contracts over six months
What happens nextCabinet to considerCabinet to note pipeline and delegate award authority
Who it affectsCouncil tenants and buildingshousing stock, community centres and offices

What was decided

The Housing Advisory Board noted the report on the strategic procurement pipeline for repairs, maintenance and compliance contracts.

Why

The Council is required under the Procurement Act 2023 to publish a pipeline of contracts, ensuring transparency, forward planning and statutory compliance. Report 4.1

Bringing the procurements together as one programme gives medium-term visibility, supports best value and avoids multiple separate Cabinet approvals. Report P5, 4.4

What happens next

Cabinet is asked to note the pipeline and delegate authority to the Director of City Services, in consultation with relevant Cabinet Members and Chief Officers, to award the contracts. Report P2

A supplier engagement event is planned for early to mid-September to alert the market to upcoming opportunities. Report 6.1

Contracts will be awarded over the next six months, with the schedule set out in Appendix 1. Report 4.4, 4.9

The money

  • approximately £74m combined value of approximately 13 contracts in the pipeline Report 4.4
  • £4.4m threshold above which Cabinet Office reporting is mandatory for contracts Report 4.8

Options considered

  • Chosen: Approve the pipeline and delegate award authority to the Director of City Services. Provides medium-term visibility, best value and avoids multiple individual Cabinet reports. Report P2, 4.4
  • Rejected: Seek separate Cabinet approval for each procurement. Reduces overall programme visibility, increases administration and makes coordination harder. Report P8
  • Rejected: Use urgent decisions by the lead member outside Cabinet. Bypasses the planned transparent process, reduces scrutiny and risks fragmented procurement. Report P8

Implications

  • Financial: No additional funding is sought: the spend is already included in approved budgets and the Medium-Term Financial Strategy, with contingency built in for areas such as damp, condensation and mould treatment. Report 4.5, 8.2
  • Legal: The pipeline is required by the Procurement Act 2023; all contracts will follow the Council's Contract Procedure Rules and applicable UK procurement regulations. Report 4.1
  • Equalities: An Equality Impact Assessment has been completed, with attention to vulnerable tenants and reasonable adjustments where required. Report 8.4
  • Climate: Climate Change Rating is assessed as High Positive: specifications will require carbon reduction, energy efficiency, waste minimisation, reuse and local sourcing. Report 8.5, P46, P47, P48
  • Risk: Risks identified include market capacity, procurement delays, cost inflation, contractor performance, compliance, operational pressures, tenant disruption and reputational harm, each with mitigation steps. Report P35, P36, P37, P38, P39, P40, P41, P42
  • Other: The programme supports community wealth building by structuring contracts to be accessible to SMEs, social enterprises and local contractors, with social value requirements for apprenticeships and fair supply chains. Report P32

Who and where

  • Tenants of Cambridge City Council housing stock, who should see quicker repairs, improved safety on fire, asbestos and water risks, and clearer communication. Report P31
  • Users of council-owned buildings including community centres and offices. Report 4.3
  • Potential suppliers, including small and medium-sized enterprises and local contractors. Report P24, P32
  • Ward councillors, resident associations and community stakeholders who will be kept informed of forthcoming works. Report 6.3

Timeline

  • Early to mid-September: Supplier engagement event to alert the market to upcoming opportunities. Report 6.1
  • Next six months: Approximately 13 contracts to be let as a coordinated programme. Report 4.4

Plain English for the jargon

  • MTFS: Medium-Term Financial Strategy: the Council's financial plan covering spending and income over several years.
  • PA23: Procurement Act 2023: UK legislation governing how public bodies procure goods, works and services.
  • DCM: Damp, condensation and mould treatment, flagged as an area where contingency is built in.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item2x/17/HAB

Resolved

To note the report.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Advisory Board

Recommendations

1.1It is recommended that Cabinet:

1. Note the procurement pipeline for repairs, maintenance, and compliance works as set out in the appendix to this report. 2. Delegate authority to the Director of City Services, in consultation with relevant Cabinet Members and Chief Officers, to award contracts within this pipeline following completion of the appropriate procurement processes

2. Purpose and reason for the report

2.1A medium-term procurement pipeline has been developed for repairs, maintenance, and building compliance work. This covers planned and responsive maintenance as well as specialist compliance activities, including damp, condensation, and mould treatment. The coordinated approach strengthens in-house delivery, helps the Council meet its statutory obligations, and supports wider goals such as improving tenant satisfaction and service resilience. By publishing the contract pipeline in line with the Procurement Act 2023, the Council is ensuring transparency, enabling providers to plan effectively, and aligning activity with its corporate direction.

Bringing this pipeline together provides visibility over the medium term and supports the achievement of best value for the Council. It does not require additional funding and is already incorporated into approved budgets and the Council’s Medium-Term Financial Strategy (MTFS).

The purpose of this report is to present the pipeline for public visibility and to seek formal approval and delegated authority to proceed with the procurements and award the resulting contracts, ensuring best value for the Council.

Alternative options considered

3.1As each procurement and its resulting contract exceeds the threshold for a key decision, Member approval is required. In determining how best to secure this approval, two alternative approaches were considered:

1. Separate approvals for each procurement – Requires multiple Cabinet reports and decisions, reducing visibility of the overall programme, increasing administrative effort, and making it harder to coordinate procurement activity to achieve best value. Option discounted. 2. Urgent decisions by the lead member outside Cabinet – This would bypass the planned, transparent decision-making process the pipeline is intended to provide. Relying on urgent, out-of-cycle decisions would reduce scrutiny, increase the risk of fragmented procurement activity, and undermine the benefits of a coordinated approach. Option discounted.

4. Background and key issues

4.14.1 In order to comply with the Procurement Act 2023 (PA23), the Council is required to maintain and publish a pipeline of contracts that shows a clear schedule of letting. This ensures transparency, forward planning, and compliance with statutory procurement obligations. It also provides greater foresight for potential providers which supports market development and widens opportunities for providers and partnerships to plan ahead for new business opportunities.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 6. Appendix 1 Repairs and Maintenance Procurement Approach, 25/09/2025 Cabinet /17/HABAppendix 180 KB Download
PDF
Item 6. Appendix 2 Climate Change Rating Tool Strategic Procurement Pipeline for Repairs, Maintenance, and Compliance Contracts, 25/09/2025 Cabinet /17/HABAppendix 202 KB Download
PDF
Item 6. Appendix 3 EqIA Strategic Procurement Strategic Procurement Pipeline for Repairs, Maintenance, and Compliance Contracts, 25/09/2025 Cabinet /17/HABAppendix 201 KB Download
PDF
Item 6. Appendix 4 Market Engagement Event for Multiple Responsive Repairs Contracts, 25/09/2025 Cabinet /17/HABAppendix 91 KB Download
PDF
Strategic Procurement Pipeline for Repairs, Maintenance, and Compliance ContractsReport 177 KB DownloadRead as text

At this meeting

Whole meeting
2x/15/HABMinutesAgreed
2x/17/HABStrategic Procurement Pipeline for Repairs, Maintenance, and Compliance ContractsThis decision
2x/18/HABNorth Cambridge Framework for ChangeNoted 2x/21/HABHousing ComplaintsOn the agenda 2x/22/HABHousing Performance 2024-25On the agenda

Who was there

10 of 11 attended
RR
Councillor Richard RobertsonCo-Chair, present
DM
Diana MinnsCo-Chair, present
JG
Councillor Jenny Gawthrope WoodCommittee Member, present
TG
Councillor Tim GriffinCommittee Member, present
NL
Councillor Nadya LokhmotovaCommittee Member, present
AM
Councillor Anthony MartinelliCommittee Member, present
ET
Councillor Elliot TongCommittee Member, present
GB
Councillor Gerri BirdCommittee Member, present
DB
Diane BestCommittee Member, present
HB
Harmony BirchCommittee Member, apologies
MP
Mandy Powell-HardyCommittee Member, present

On this subject at Cambridge

Search all
  1. Strategic Procurement Pipeline for Repairs, Maintenance, and Compliance ContractsThis decision
  2. Cabinet: Strategic Procurement Pipeline for Repairs, Maintenance, and Compliance ContractsNoted

More from Cambridge Housing Advisory Board

All decisions
MeetingDecisionOutcome
15 Jun 2026 Election of Co-Chair (Councillor)(i) That Councillor Haithcock be elected Co- Chair (Councillor Side) of the Housing Advisory Board for the ensuing Mu... Decided Open
15 Jun 2026 Appointment of Independent MemberThat the Assistant Director for Housing and Health be requested to submit a written report to the next meeting on the... Decided Open
15 Jun 2026 Housing Advisory Board Terms of ReferenceThat the Housing Advisory Board Terms of Reference be approved. Approved Open
15 Jun 2026 New Build Working Group – New Build Repairs and Maintenance After the Defects Period( i ) That the following Housing Advisory Board Members be appointed to the New Build Working Group: · Councillors: D... Decided Open
15 Jun 2026 Housing Improvement Plan - June UpdateResolved : ( i ) To note the report. (ii) That a Glossary of Acronyms and their meaning be included in future reports. Noted Open